AS9100 Clause 8.5.1.3 Production Run Verification

W

WonderCNC

We are a machine shop currently ISO9001:2008 registered. We plan to have our AS9100D audit this September. In our machine shop, we have 25+ CNC machines. The machines can be grouped in work centers, or types: 3-axis, 5-axis, horizontal, lathe. Our machines are made by the same manufacturer and the fixturing and tooling can be interchanged within work centers.

My question is about the 8.5.1.3 Production Process Verification requirement.

The parts we make typically have multiple operations and can be any combination of machine type/work center. The first time we run a job, we will do a full documented FAI and send to the customer. The next time we run the job, we may run one or more of the machine operations in a different machine- but the machine is the same type and same work center (as the first run). For every machine operation, we verify the setup with dimensional checks and record that the setup has been verified, but we do not do a formal FAI. Do we need to do a formal documented FAI if we change machines (within the same work center)? In our experience, changing machines in this manner would not invalidate the original results because we consider the machines to be equivalent and we are checking the setup and doing in process inspection to verify that the parts meet print each time we run the part. Will this meet the AS9100 requirement? Thank you.
 

dsanabria

Quite Involved in Discussions
Re: Please help: Clarification of AS9100 first production run verification 8.5.1.3

We are a machine shop currently ISO9001:2008 registered. We plan to have our AS9100D audit this September. In our machine shop, we have 25+ CNC machines. The machines can be grouped in work centers, or types: 3-axis, 5-axis, horizontal, lathe. Our machines are made by the same manufacturer and the fixturing and tooling can be interchanged within work centers.

My question is about the 8.5.1.3 Production Process Verification requirement.

The parts we make typically have multiple operations and can be any combination of machine type/work center. The first time we run a job, we will do a full documented FAI and send to the customer. The next time we run the job, we may run one or more of the machine operations in a different machine- but the machine is the same type and same work center (as the first run). For every machine operation, we verify the setup with dimensional checks and record that the setup has been verified, but we do not do a formal FAI. Do we need to do a formal documented FAI if we change machines (within the same work center)? In our experience, changing machines in this manner would not invalidate the original results because we consider the machines to be equivalent and we are checking the setup and doing in process inspection to verify that the parts meet print each time we run the part. Will this meet the AS9100 requirement? Thank you.

First - What is your customer requiring. This needs to be clarified at contract review.

Second - There is a difference between first piece and first Piece Inspection report.

Third - If your customer invokes AS9102 - FAIR, then you need to comply with those requirements.
 

Mike S.

Happy to be Alive
Trusted Information Resource
Do we need to do a formal documented FAI if we change machines (within the same work center)? In our experience, changing machines in this manner would not invalidate the original results because we consider the machines to be equivalent and we are checking the setup and doing in process inspection to verify that the parts meet print each time we run the part. Will this meet the AS9100 requirement? Thank you.

To answer your question, IMO what you are doing will meet AS9100 8.5.1.3 requirements IF there are no overriding additional customer requirements.
 
J

joburum

Depends on the customer. The larger companies may go deep enough to require a delta FAI be complete with any machine change whereas others may only need process and material specification.
 
W

WonderCNC

Thank you for your responses. This forum is very helpful. I'm trying to delve a little further for clarification.

AS9100C had clause 7.5.1.2 Control of Production Process Changes, which is no longer in AS9100D. Does the removal of this clause change the interpretation of the FAI requirement?

AS9100C had provision for making process changes. I'm trying to understand how removal of that provision affects the FAI requirement, if at all.

In other words, per AS9100D, and if the customer does not invoke AS9102 or a similar requirement, is there any justification for which we can make process changes and not have to redo the FAI? If ,due to our knowledge/expertise of our processes and methods, we can justify that the change does not invalidate the original FAI, will that satisfy the requirement?
 
S

sunnycosta

I was wondering if anyone could share, a procedure or flowchart, to cover the following new clauses:
8.1.4 Prevention of Counterfeit parts,
8.1.3 Product Safety,
8.1 Integrated Phased Processes,
7.1.4 Human Factors.

I just cannot understand what is meant by:
8.1 Integrated Phased Processes,
 

Mike S.

Happy to be Alive
Trusted Information Resource
Thank you for your responses. This forum is very helpful. I'm trying to delve a little further for clarification.

AS9100C had clause 7.5.1.2 Control of Production Process Changes, which is no longer in AS9100D. Does the removal of this clause change the interpretation of the FAI requirement?

AS9100C had provision for making process changes. I'm trying to understand how removal of that provision affects the FAI requirement, if at all.

In other words, per AS9100D, and if the customer does not invoke AS9102 or a similar requirement, is there any justification for which we can make process changes and not have to redo the FAI? If ,due to our knowledge/expertise of our processes and methods, we can justify that the change does not invalidate the original FAI, will that satisfy the requirement?

Have a look at 8.5.1.3 and see if your answer is not in there.
 

matkins

Starting to get Involved
sunnycosta,
there is another thread here that discusses "integrated phased processes". Search that phrase to find it.
 

Big Jim

Admin
We are a machine shop currently ISO9001:2008 registered. We plan to have our AS9100D audit this September. In our machine shop, we have 25+ CNC machines. The machines can be grouped in work centers, or types: 3-axis, 5-axis, horizontal, lathe. Our machines are made by the same manufacturer and the fixturing and tooling can be interchanged within work centers.

My question is about the 8.5.1.3 Production Process Verification requirement.

The parts we make typically have multiple operations and can be any combination of machine type/work center. The first time we run a job, we will do a full documented FAI and send to the customer. The next time we run the job, we may run one or more of the machine operations in a different machine- but the machine is the same type and same work center (as the first run). For every machine operation, we verify the setup with dimensional checks and record that the setup has been verified, but we do not do a formal FAI. Do we need to do a formal documented FAI if we change machines (within the same work center)? In our experience, changing machines in this manner would not invalidate the original results because we consider the machines to be equivalent and we are checking the setup and doing in process inspection to verify that the parts meet print each time we run the part. Will this meet the AS9100 requirement? Thank you.

Most of the time what you are doing would not trigger the need for another "first article". What it hinges on is when there is a change that invalidate the previous one, and that would depend on circumstances. It is possible, in some limited situations, that simply breaking set-up would trigger the need for another first article.

What is in AS9100 C and AS9100D about first article is very limited or very brief. You would be required to always live to what is there. What you need to be aware of is that customer requirements could over-ride that. Customers could add pretty much anything they want. What they usually do add (if anything) is AS9102, a separate and stiffer standard about first article.

First piece is not necessarily first article. First article is a representative sample of the first production run. It may or may not be the first piece. First piece is exactly that, the first piece, which is often confirmed as being correct before building more.
 

howste

Thaumaturge
Trusted Information Resource
AS9100C had clause 7.5.1.2 Control of Production Process Changes, which is no longer in AS9100D. Does the removal of this clause change the interpretation of the FAI requirement?

7.5.1.2 is essentially intact in clause 8.5.6 now.
 
Thread starter Similar threads Forum Replies Date
M Changes Assessment as per AS9100 Clause 7.5.1.2 Control of Production Process Changes AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
G AS9100 Clause 7.5.1.1 Production Process Verification Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
J Production Process Verification - AS9100 Clause 7.5.1.1 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
A Understanding AS9100 Clause 7.5.2 Validation of Processes for Production and Service AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
W Interpretation of Production Planning per AS9100 CLAUSE 7.5.1 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
H Does this clause mean i must be in compliance with AS9100 or is 9001 enough? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
D AS9100 Rev D - Clause 8.7 Control of Non conforming outputs AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
Q Connecting AS9100 D Clause 4.2 to 9.3.2 b - Interested parties and relevant issues AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 24
A Definition of "Sensitive Products" Clause 8.5.4 (c) in AS9100 Rev. D AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
C AS9100, Clause 8.5.1.3 - First Article Inspection Costs AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 16
J Not Design Responsible - Can we exclude all or parts of AS9100 clause 8.3 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
I How to satisfy with AS9100 Clause 8.4.3 a, Information for external providers? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 24
O How will you handle Clause 6.1 - Risks and Opportunities for AS9100 Rev. D Auditors? Risk Management Principles and Generic Guidelines 22
howste AS9100 Rev D Clause 10.2 - Is Cause always required? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 39
W Evidence for Review of Requirements - AS9100 Clause 7.2.2 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 2
A AS9100 Clause 7.1.1 Project Management - Process vs Project. AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
W Checklist for AS9100 Clause 7.2.2 Review Of Requirememts Related to Product AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
W AS9100 Clause 8.2.3.C Monitoring and Measurement of Processes AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
S Process Monitoring and Measurement - AS9100 Clause 8.2.3 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
R Verification of Process Changes (AS9100 clause 7.5.1.2) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
Z AS9100 Clause 7.4.2.d Revision Letter Flow Down to Suppliers AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 12
M Management Review - AS9100 Clause 5.6.3 Review Output AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 12
V Application of AS9100 clause 7.5.1.1 - Tooling Supplier AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
G AS9100 clause for Repeat Orders AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
M Compliance with AS9100 clause 7.5.1.3 Ctrl of Equipment, Tools and SW Programs AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
Q AS9100 Clause 8.3 - Control of Nonconforming Product Process for Approving Personnel AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
M Understanding AS9100 Clause 7.5.1.4 Post-Delivery Support Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
K AS9100 Clause 7.2.2 - Documenting "Special Requirements" and risks AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
M Interpreting AS9100 Clause 8.2.2 Internal Audit Requirements Internal Auditing 28
J AS9100 Clause 7.4.3 Verification of Purchased Product - OEM C of C required? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
B AS9100 Clause 8.2.3.C Monitoring and Measurement and 8.5.2 Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
C AS9100 C Clause 8.3 - Personnel Approval Process AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
C AS9100 Rev C Clause 8.5.2 - CAR (Corrective Action Request) Format AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 14
B AS9100 Clause 7.3.3 - Design and Developement Requirements d and e AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
Q AS9100 Clause 7.4.1 Purchasing Process and Approved Supplier List Records AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 37
M AS9100 Clause 4.2.3 requirements - Documents required by the QMS shall be Controlled AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 13
R AS9100C Special Process Procedure - Work Instruction for AS9100 Clause 7.5.2 wanted AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
G AS9100 Clause 7.1.4 Control of Work Transfers clarification AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 12
S AS9100 Clause 8.3 - Control of Nonconforming Product Q AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 13
Q AS9100 Clause 8.3 Control of Nonconforming Product - Clarification wanted AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
P Intercompany Work Transfer according to AS9100 Clause 7.1.4 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
O Clause Interpretations related to AS9100 Implementation AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 14
I Standard vs. Specification & AS9100 Clause 7.4.2 (d) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
H Planning of Product Realization - AS9100 Clause 7.1 - Can we exclude 7.1f? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
S Is Configuration Management Mandatory? AS9100 Clause 7.1.3 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
S Problem Collecting In-Service Data (AS9100 Clause 7.5.1.4) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
Q What is considered a Training Record? AS9100:2004 Clause 6.2.2 Records and Data - Quality, Legal and Other Evidence 8
B Question about the word "Design" in AS9100 Clause 8.3 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
M New to AS9100 - Clause 7.5.3 - Do you have to identify each part produced AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
J Project Management Procedure - AS9100 Clause 7.1.1 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 15

Similar threads

Top Bottom