AS9100C Out Of Tolerance (OOT) Equipment - Customer Approval

AmandaMusser

Quality Rules!
#1
Hello fellow Covers :popcorn:

I hope someone can give me some input on section 7.6 Control of Monitoring and Measuring Equipment.

We are a contract manufacturer of electrical assemblies, we do NO design and have excluded section 7.3 from our QMS. I have a strong and controlled calibration system in place for both company owned and customer owned equipment. If an item is returned from the cal-house OOT, we follow internal processes to evaluate the validity of previous measurements based on our manufacturing and test engineer(s) skills and experience.

Our recent AS9100 Surveillance audit issued an observation for "... company does not have design knowledge, therefore no knowledge of if or how OOT (Out of Tolerance) condition can or will affect product. Company should assign some level for approval from the Customer for equipment that has been received Out of Tolerance"

Do you have any suggestions as to what that level might be or where I should start?
 
Elsmar Forum Sponsor

dsanabria

Quite Involved in Discussions
#2
Re: OOT Equipment / Customer Approval?

For clarification purposes - You send out an equipment to the calibration house and it comes back - rejected "out of tolerance'.

You guys verify the results, make adjustments and put it back into the system as being calibrated and in good working conditions?

Thanks
 

yodon

Staff member
Super Moderator
#3
Re: OOT Equipment / Customer Approval?

I think what the auditor is saying is that you may be assessing the validity of previous measurements but you don't mention completing the loop and coordinating the results / findings with the customer.

It sounds like you know what parts were measured with the (OOT) equipment so do you share your assessment with the customer who received the parts? They will, after all, have to decide if the risk of using the parts as is is too high. They may need to (or ask you to) re-measure the parts to determine if they are acceptable.
 

Sidney Vianna

Post Responsibly
Staff member
Admin
#4
Re: OOT Equipment / Customer Approval?

Do you have any suggestions as to what that level might be or where I should start?
I think you would need to evaluate that, on a case-by-case, depending on the OOT condition. It could very well be that some OOT conditions have CLEARLY no impact on product, while others might have some impact on product conformity.

For those situations where you could establish that you probably shipped nonconforming product due to the OOT condition, AS9100C requires you to
The organization’s nonconforming product control process shall provide for timely reporting of delivered nonconforming product;
From a risk management perspective, it does make sense for you to involve the customer to decide if a suspect product should be recalled and retested in those situations where the full impact of the OOT condition is not easily determined.
 
Last edited:

John Broomfield

Staff member
Super Moderator
#5
Re: OOT Equipment / Customer Approval?

Amanda,

Feed such information into your process for dealing with nonconforming product.

The procedure will specify the actions and interfaces with the designer (customer) to review and approve or reject use-as-is and repair dispositioning proposals.

John
 

dsanabria

Quite Involved in Discussions
#6
Re: OOT Equipment / Customer Approval?

I think you would need to evaluate that, on a case-by-case, depending on the OOT condition. It could very well be that some OOT conditions have CLEARLY no impact on product, while others might have some impact on product conformity.

For those situations where you could establish that you probably shipped nonconforming product due to the OOT condition, AS9100C requires you to


From a risk management perspective, it does make sense for you to involve the customer to decide if a suspect product should be recalled and retested in those situations where the full impact of the OOT condition is not easily determined.
Perfect and interesting perspective,

but now I am wondering :mg:

- if this scenario is true -why didn't the auditor raised it to the non conformance level? :confused:
 

Sidney Vianna

Post Responsibly
Staff member
Admin
#7
Re: OOT Equipment / Customer Approval?

Feed such information into your process for dealing with nonconforming product.
John, an OOT condition does not necessarily mean that the product is nonconforming.

why didn't the auditor raised it to the non conformance level? :confused:
As you know, a valid nonconformity has to be supported by a written requirement. What requirement would have been violated here in this scenario?
 

dsanabria

Quite Involved in Discussions
#8
Re: OOT Equipment / Customer Approval?

John, an OOT condition does not necessarily mean that the product is nonconforming.

As you know, a valid nonconformity has to be supported by a written requirement. What requirement would have been violated here in this scenario?
Just wondering how the auditor came to that observation and why didn't use

Clause 7.6

a. M&M equipment are calibrated (and/or verified) at specified intervals against traceable standards.

as a starting point - (or am I reading too much into it)
 

Sidney Vianna

Post Responsibly
Staff member
Admin
#9
Re: AS9100C Out Of Tolerance (OOT) Equipment / Customer Approval?

The requirement at play here is:
In addition, the organization shall assess and record the validity of the previous measuring results when the equipment is found not to conform to requirements. The organization shall take appropriate action on the equipment and any product affected
Unless the auditor found evidence that the organization failed to comply with that, s/he can not issue a nonconformity, as mentioned in note #3 of paragraph 4.2.2.5 in AS9101D:
NOTE 3: If there is no evidence of non-fulfillment of a requirement, the auditor cannot issue a nonconformity.
 
Thread starter Similar threads Forum Replies Date
P How To Transition From AS9100c to AS9100 Rev. D AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
W Nonconforming product AS9100C, 8.3 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
A AS9100C to D - Has anyone done a gap analysis? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
S AS9100C 8.2.2 - Selected Tools & Effectiveness of IA Process and Performance AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
S AS9100C 7.5.1 Control of Production and Service Provision AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
W AS9100C Process based manual Design and Development of Products and Processes 4
W DCMA and AS9100C - Dedicating a week and 5 auditors to perform a AS9100C audit AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
W Unattached (stand-alone) Forms acceptable for AS9100C? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
A AS9100C to AS9100D Transition Testing AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
M Need help on QMS Development in an AS9100C certified organization AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
I AS9100C Lead Auditor Training Courses being Cancelled AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
Q What are the differences between ISO 13485 vs. AS9100C ISO 13485:2016 - Medical Device Quality Management Systems 3
W Certification on AS9100C - FAI or PPAP? Project Management or APQP? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 11
B AS9100C 7.5.1 d and calibrated equipment in the production areas AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
D AS9100C Clause 8.2.4 Monitoring and Measurement of Product AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
T AS9100C Processes which need to be documented AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
W AS9100C/ISO9001:2008 Dual Certification (to both standards) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
A AS9100C. 7.1.2 Risk Management - Interpretations AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
W AS9100C registration - How long does the system have to run before initial audit? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
I Guidance for Transition from ISO9001:2008 to AS9100C AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
M AS9100C Quality Policy Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 14
M AS9100C Document Control for Machine Set Up Work Instructions AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
alonFAI Update an existing QMS manual or write a new one for AS9100C Certification? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
M AS9100C "Split" Audit Stages AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
H Is instrument ID required in the in-process inspection report per AS9100C AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
D AS9100C 4.2.3 - Obsolete Electronic ERP Documents AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
J Auditing AS9100C Section 7.5.1.2 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 3
M Adding AS9100C Lead Auditor Certification to an IRCA ISO 9001 LA Certification AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
D AS9100C - New requirements to existing standard? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
K AS9100C for Non-Aerospace Military Equipment? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
K How Can I Implement the Process Approach in AS9100C AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
Q Interpretation of Clause 7.1 Planning Of Product Realization in AS9100C standard AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
Q Basic questions about AS9100C Quality Standard Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
D Number of Audit Days for AS9100C Surveillance Audit (20 employees) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
L AS9100C 8.2.4 a-d Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
L Documented procedures requirements for AS9100C requirement 7.5.1 a) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
A AS9100C 7.4.3 Delegation of Verification (to a supplier for a specific circumstance) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
S AS9100C Complete Internal Audit Software Package Recommendations Quality Assurance and Compliance Software Tools and Solutions 13
R Relating Cpk to Sampling Plans - AS9100C Para 8.2.4 & AS9103 Para 4.4 d. Capability, Accuracy and Stability - Processes, Machines, etc. 1
Buckyb AS9100C Clause 7.4.1 Appoved Supplier "Conditional" Status AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
B Example of Production Process Change having Significant Consequences AS9100C 7.5.1.2 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 0
G AS9100C Clause 4.1.1 Requirements Clarification AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
G AS9100C for Multiple Production Department AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
G AS9100C Internal Auditor Eligibility Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
E Risk Management - Planning Stage (AS9100C Section 7.1.2(d)) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
G Detailed Project Plan for Implementing AS9100C AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
G AS9100C Gap Analysis Checklist for Implementation in our Company AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
C Become AS9100C certified...then move the facility. AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
C AS9100C Audit must include FAA Part 145 (FAA Repair Station)? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
C AS9100C Implementation in a Complex Situation AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5

Similar threads