I had a question regarding what is required of scheduling as far as AS9100. I am creating a process matrix with AS9100 clauses to link each process but I am having trouble covering scheduling which is located within the production process.

For example, IATF16949 8.5.1.7 states:

"The organization shall ensure that production is scheduled in order to meet customer orders/demands such as Just-In-Time (JIT) and is supported by an information system that permits access to production at key stages of the process and is order driven."


Is this mentioned in AS9100D in some way that I may have overlooked while reading it?
 

howste

Thaumaturge
Trusted Information Resource
Look at AS9100 clause 8.1:
As appropriate to the organization, customer requirements, and products and services, the organization shall plan and manage product and service provision in a structured and controlled manner including scheduled events performed in a planned sequence to meet requirements at acceptable risk, within resource and schedule constraints.
I believe that's as close as you'll find in AS9100. It's much more generic than IATF 16949 in that it includes program management (pre-production activities) as well as production.
 

Sidney Vianna

Post Responsibly
Leader
Admin
And, don’t forget, on-time delivery performance is an expectation. So, adequate production planning is a critical input into OTD.
 
B

BoardGuy

So does that mean I can get my orders with more than a day or 2 lead time? :)
[FONT=&quot]Yes it’s called contract review. Clause 8.2.3 states that when “the organization determines that some customer requirements cannot be met or can only partially be met, the organization shall negotiate a mutually acceptable requirement with the customer”. If you customer want’s it in one day and your lead time is 5 days (WIP, material procurement, etc.) then you negotiate.[/FONT]
 

Golfman25

Trusted Information Resource
[FONT=&quot]Yes it’s called contract review. Clause 8.2.3 states that when “the organization determines that some customer requirements cannot be met or can only partially be met, the organization shall negotiate a mutually acceptable requirement with the customer”. If you customer want’s it in one day and your lead time is 5 days (WIP, material procurement, etc.) then you negotiate.[/FONT]

Of course. But that doesn't change behavior. Everyone wants it yesterday. :)
 
B

BoardGuy

Of course. But that doesn't change behavior. Everyone wants it yesterday. :)
[FONT=&quot]This is true but if you continually accept these types of orders without the negotiation of longer lead-time, you will fall victim of Clause 8.2.2.b, which states, “When determining the requirements for the products and services to be offered to customers, the organization shall ensure that… the organization can meet the claims for the products and services it offers”.[/FONT]
 

J.Enger

Involved In Discussions
Not necessarily. For example, I want it the day before yesterday.
For one of our customers (approx 60% of our business), they agree to set time, then a few weeks later will say we need it yesterday, we bust our @$$ to get it done only to have them go "No we dont need it for 2 month now".
 
Thread starter Similar threads Forum Replies Date
K Maintenance requirements for Production Equipment in AS9100D General Auditing Discussions 8
LincolnQA AS9100D, Clause 8.4.1.1d - actions to take when external providers do not meet requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 18
T AS9100D Work Transfer Plan Analysis AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
T Company AS9100D External Audit Preparation AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 17
T AS9100D Risk-Based Internal Audit Schedule AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
C AS9100D to CMMI Dev 2.0 Mapping & Comparison Matrix Software Quality Assurance 1
H AS9100D Exclusions, if Not Excluded Is it Automatically Applicable? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
P AS9100D clause 8.6 - Documentation required to show evidence of conformity AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
F Surveillance Audit for AS9100D and new ERP system incorporated Document Control Systems, Procedures, Forms and Templates 4
Q Purchasing Clauses in AS9100D AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
Quality Specialist AS9100D Approved Supplier List requirements and how to apply Supplier Quality Assurance and other Supplier Issues 11
T Combining 2 companies with separate AS9100D certificates! AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
D AS9100D 8.4.2 Note 2 Significant Operational Risk AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
D AS9100D 8.5.1.3 First Article AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
Stefan Mundt AS9100D Engineering sample purchases - Supplier not approved AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
A AS9100D new certification cost?? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
A Moving from AC7004 to AS9100D AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
I RCCA per AS9100D 7.5.2 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 22
M Best accreditation body for AS9100D Lead facility auditor? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
M AS9100D Registrar pre-audit requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 15
R AS9100D internal audit checklist or ISO 9001 2015 to AS9100 D AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
K AS9100D 8.2.1 Review Requirements for Products and Services AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 14
A AS9100D - Clause 8.1 Operation - Coating service company AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
T AS9100D Clause 10.2.1g Supplier Corrective Action for each and every nonconformity? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
B AS9100D 7.1.5.2 Calibration or Verification Method using outside cal lab AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
T Transition from ISO9001 to AS9100D: O&G to Aerospace AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
H AS9100D clause 8.5.1 f) & 8.5.1 g) - Special Processes AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
A AS9100D 8.1.4 Prevention of Counterfeit Parts AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
DuncanGibbons Should the requirements FAA/EASA Part 21 be addressed within the QMS and AS9100D quality manual? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
B Purchasing AS9100D Standard in Japanese AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
Stefan Mundt AS9100D Major nonconformity due to recurrence of a NC during a subsequent CB audit. AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
B AS9100D Sampling Plan AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
A What To Clauses Exclude - AS9100D AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
F AS9100D Internal auditing requirements Internal Auditing 11
A AS9100D FAI requirements needed? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
F AS9100D, raw material standards are a requirement for manufacturing? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
F AS9100D Process Matrix for a small cnc machine shop AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
C AS9100D -8.5.1j - Accountability For All Products Tiny Parts AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
B Free downloadable AS9100D audit checklist ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 22
K AS9100D Clause 7.5.2.a) - What is considered to be "documented information"? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
T AS9100D - Scope of QMS for New Company - Only Choosing a Function Subset Due to Management AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 14
Nicole Desouza AS9100D - Calibration of Dies & Tooling - Plastic Extrusion AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
Q What is the difference between AS9100D 9.3.2.f and 9.3.3.a AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
S AS9100D PEAR - Examples for organization's method for determining process results? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
DuncanGibbons Why is 8.4 post-delivery activities before 8.6 release of products and services in AS9100D? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
K AS9100D 8.4.1.1 external providers question - Walmart, Home Depot, our lawn care team. etc. AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 20
W Core Process Metrics AS9100D for Product Planning? Quotes and sales? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
C Taking exception to customer requirements or specifications & AS9100D AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
I AS9100D Non-conformance for 10.2.1 b 2 and 10.2.1. b 3 e and f - Corrective Action AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
M AS9100D Competence and Training Records - X-Ray AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2

Similar threads

Top Bottom