Hi all, learning the Quality game and I was wondering if any experienced players could chip in their advice. I'm reading the AS9102 spec specifically to learn more about form 1.
  1. What is the difference between a detail part and an assembly FAI? My understanding is an assembly FAI is for products that we have assembled from smaller parts/components, and the rest are detail parts. So if we receive a casting and machine it, that's a detail part. Same if we make a part from raw material and ship it to the customer.
  2. If it's a detail part, listing parts in the Index list is not necessary?
  3. Full FAI/Partial FAI and FAI Complete/FAI Incomplete. It seems like whenever it's a Full FAI that means it's also FAI Complete. Are there any situations where it could be Full FAI + FAI Incomplete, or Partial FAI + FAI Complete?
  4. FAIR number. I'm very confused on what this represents. We've been putting 1 for everything. I don't think that can be right.
It's a lot of questions so any help is super appreciated. Thanks!
 
Elsmar Forum Sponsor

Mike S.

Happy to be Alive
Trusted Information Resource
#3
You are far from the first person to be confused by AS9102, nor will you be the last.

I am not an expert on AS9102 but here is my understanding, FWIW:

It's a detail part of no parts were assembled to make it.

Form 1 # 15-18 is not required for a detail part.

You can have a full FAI incomplete if there was a nonconforming characteristic or the customer asked you to provide the product missing something (a part that was unavailable or minus paint, etc.)

Forms 1, 2, 3 box 4 FAIR number is a reference number you create. Mine are all unique.
 
#4
Thank you Mike I appreciate the help. We don't serialize our reports and in the FAIR column for assemblies we've been "1" for every component. I figured that cannot possibly be right.

One last question, we've been using the AS9102 forms to describe a manufacturing lot, while the standard itself seems to imply that you should be using them to describe an individual piece. For example in 3. Serial Number, we put the lot number. Does that seem like an appropriate way to use it? Thank you.
 

Mike S.

Happy to be Alive
Trusted Information Resource
#5
Thank you Mike I appreciate the help. We don't serialize our reports and in the FAIR column for assemblies we've been "1" for every component. I figured that cannot possibly be right.

One last question, we've been using the AS9102 forms to describe a manufacturing lot, while the standard itself seems to imply that you should be using them to describe an individual piece. For example in 3. Serial Number, we put the lot number. Does that seem like an appropriate way to use it? Thank you.
You are to use the s/n of the individual part that you selected to measure as your first article.
 

darkopsghost

Involved In Discussions
#6
FAIR = First Article Inspection "Report". This would/ should distinguish it from the one you did yesterday and the one you did 5 years ago. It can be sequential or anything you want it to be by including the year for instance, but build a log and keep it simple.

As far as for the difference between Detail and Assembly, Assembly is the collection of all the Detail Parts that go into making that upper assembly.

As for Partial vs Full, the simplest way to describe what a Partial is, is when there is a change to a drawing, a process, or a change which could affect form, fit, and function of the part, or if a previous FAIR had a Non-Con associated with it, to close that CA. This would be an "addendum" to the original Full.

For every part that requires an FAI, there are sometimes pages and pages and for every A/C ever built, there are mountains of paperwork that goes with it, sometimes out weighing the A/C.

Get into First Part Qual on new manufacturing and there is even more paperwork. The Military has SDRLs and SSOWs. Through in a few Initial Production Evaluation (IPE)s and several Destruct Tests and you will go bonkers.

Be thankful if you are only required to do a FAIR!
 
Thread starter Similar threads Forum Replies Date
S Questions about AS9102 - Section 5.5.3 & Form 3 block 10 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
P AS9102 Form 3 Inclusions AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
M AS9102 FAI Report formats - Boxes in form 1, 2, 3 of AS9102 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
P AS9102 Form 3 Dimension Results Inspection, Prints (Drawings), Testing, Sampling and Related Topics 1
B Documenting hardware on Form 2 of AS9102 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
B AS9102 COTS Form 1 vs. 2 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
L AS9102 Form 1 Section 13 Detail or Assembly Question AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
J FAI per AS9102 affecting Fit, Form, Function AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
C AS9102 Form 2 Information - Special Processes - Plating AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
C AS9102 FAIR Form 1 Content Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
M AS9102 Form #3 modification AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
G Is it mandatory to record all processes in form 2 of AS9102 FAI report AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
S AS9102 Interpretation on Form 2 field 6 - Specification AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
D AS9102 FAI - Detail vs Assembly FAI (Form 1, Box 13) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
P What is the acceptable content on FAI form 3? AS9102 Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
K AS9102 Form 3 for Assemblies - Verification that the Assembly is Correct AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
K AS9102 - Tolerance Block on Enginerering Drawings to Form 3 of AS 9102 FAIR AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
T Another FAI AS9102 form question Document Control Systems, Procedures, Forms and Templates 3
S AS9102 Form 1 Item 19 FAI Complete / Not Complete Box - Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
S Form AS9102 line 19 requirement clarification/verification AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
C AS9102 Form 3 - Design Requirements Uniquely Identified AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
D AS9102 - How to title the attached form and how to identify the characteristics AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
C AS9102 Form 2 and Standard Hardware clarification AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
K AS9102 Form - Do you hate it as much as I do? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 27
B FAI (First Article Inspection) per AS9102 Form 2, sections 5 & 6 question Document Control Systems, Procedures, Forms and Templates 10
T AS9102 FAI (First Article Inspection) Form example Document Control Systems, Procedures, Forms and Templates 35
Q Need help with AS9102 form #2. AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
briteme4 AS9102 FAIR Requirement AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
briteme4 AS9102 First Article Inspection - do I need a second reviewer and signer? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
B AS9102 - 3D printing a special tool required for assembly (counterfeit risk?) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 12
R AS9102 FAI Change in Material / Process Supplier AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
D Partial FAI - AS9102 - One single drawing has 10 part numbers AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
D AS9102 - Assembly FAI for Use As Is or Repaired Parts AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
M Conformal Coating & AS9102 - Is conformal coating material a COTS part AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
A AS9102 Delta FAI Require after Rework stock item from stock AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
B AS9102 - Completing Partial FAI's for Baseline Part Numbers AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
E AS9102 FAI - What makes a COTS modified? (PCB assemblies) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 11
B AS9102 FAI & Lower Level Drawings - How should we perform the FAI? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
P AS9102 full FAl or a partial FAI after production inactivity period AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
B AS9102 Supplier Flow Down Method AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
M FAI AS9102 - What does a First Article Inspection cover? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 11
W FAIR to AS9102 additional documentation Document Control Systems, Procedures, Forms and Templates 5
O AS9102 FAI report Forms 1-3 Document Control Systems, Procedures, Forms and Templates 6
R AS9102 - Are FAIs against a Customer Red-Lined Drawings Allowed? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
J AS9102 - What needs to be Bubbled on a Contract or Purchase Order AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
R AS9102 FAI with No Drawings Supplied AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
S AS9102 - Clarification - PO asking for an Assembly at Rev B (Print at Rev C) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
M AS9102 Training - Seeking third party agency that provides online AS9102 training AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
APHX02 AS9102 FAI Requirements that pertain to a Dimension 'delta' AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
S Qualification Builds & Process Changes (AS9102 - First Article Inspection) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1

Similar threads

Top Bottom