Hi all, learning the Quality game and I was wondering if any experienced players could chip in their advice. I'm reading the AS9102 spec specifically to learn more about form 1.
- What is the difference between a detail part and an assembly FAI? My understanding is an assembly FAI is for products that we have assembled from smaller parts/components, and the rest are detail parts. So if we receive a casting and machine it, that's a detail part. Same if we make a part from raw material and ship it to the customer.
- If it's a detail part, listing parts in the Index list is not necessary?
- Full FAI/Partial FAI and FAI Complete/FAI Incomplete. It seems like whenever it's a Full FAI that means it's also FAI Complete. Are there any situations where it could be Full FAI + FAI Incomplete, or Partial FAI + FAI Complete?
- FAIR number. I'm very confused on what this represents. We've been putting 1 for everything. I don't think that can be right.