My company is under transition process to ISO 9001:2000.

To comply with ISO 9001:2000 we have undertaken gap analysis. The problems found in this gap analysis is how to audit management responsibility. How to ensure management commitment and how to find evidence that our management is taken responsibility to this system requirements.

Within the analysis, management only make an explanation verbally how they committed to the system.

Please make your advice in this problems.

Hsjahrir
 
M

M Greenaway

This sort of commitment can be viewed objectively through managment review meeting minutes to see who has attended from top management. Allocation of resources is also evidence of top management commitment. As is establishing quality policy and quality objectives.

Any others ??
 

RoxaneB

Change Agent and Data Storyteller
Super Moderator
Communication is also key to Management Responsibility. It's all fine and dandy to have everything in place for a QMS, but this information needs to be communicated to every employee at every level.

It also needs to be stressed why you have a QMS. You may have one to meet Customer requirements or to address statutory/regulatory requirements or (harsh truth here for some industries) just to stay in business.

How components of the QMS are communicated is up to you. We have various tools in place at my company. Everything from a newsletter to huge signs showing results on our "Strong Goals" to crew and department meetings and so on.
 
H

hsjahrir

Thanks for your response.

I need your further comments in specific, how to audit clause 5.2, Customer Focus : "Top Management shall ensure that customer requirements are determined and are met with the aim of enhancing customer satisfaction".

When we have more than 50 customers, how come our top management can ensure that each customer requirements are determined.

Contract or order review is actually done by Sales Department and approved by Production Manager. Shall our top management to be involved in each contract review to meet this clause 5.2 requirements ?

Furthermore, please your comments how to audit clause 5.4.2.(b) : " the integrity of management system is maintained when changes to the quality management system are planned and implemented".

Your comments will be highly appreciated.

Hsjahrir
 
M

M Greenaway

This is a pretty bland requirement in the standard, and I understand your confusion.

Again like my previous comment Top Management ensure this happens by allocation of resources, etc. Not actually doing the job themselves.

The requirement is a bit broader than contract review also. It includes having systems and resources in place to collate data pertaining to customer satisfaction, analysis, and appropriate action.

As to clause 5.4.2.b you can only audit this if changes to the QMS have been implemented. A good example of this might be the acquisition of another company and the integration of its products into your product line - how is the quality of both your own product and the new product maintained. Evidence of quality planning on the new product might be a good starting point.
 
H

hsjahrir

Mr. Greenway,

Since objective evidence of management responsibility can be found from various source (e.g, from MR,sales dept,factory maintenance dept), is it means that no need to audit top management ?

For example, we can audit of communication by auditing sales/marketing. Or auditing factory maintenance to find out management commitment to provide infrastructure.

The only way we can directly audit top management is in management review.

So, what difference of this new standard with ISO 9001:1994 ?

Your comment, please.

Hsjahrir
:frust:
 
M

M Greenaway

Like you suggest I personally dont think, and wouldnt, audit Top Management commitment as an entity in itself.

However audit findings of activities in a certain area might, through audit trail, lead me back to evidence of a lack of top management commitment.

An example of this might be a planned internal audit that has slipped 3 months behind the scheduled date. Investigation might show that the auditor has not been allowed to undertake this audit due to other demands placed on him/her by their manager (this does occur in my experience). THis may suggest a lack of top management commitment to the QMS.
 

barb butrym

Quite Involved in Discussions
the auditor would look at the management review minutes content...what support is offered, followed up and acted on especially for resources...what about the quality planning stuff...do they walk the talk or just give lip service?

It is typically quite clear...the goals ond obj. .... are they communicated and supported at all levels of the facility? Ask the 'why' questions and listen carefully to the answers....pride in the system typically indicates committment on the top most level...is the head houncho involved or absent? each one can be taken individually and excused away, but bottom line.....it is usually quite clear, a gut feel based on facts from the interview and records.
 
V

Vash Stampede

Originally quoted by Hsjahrir:
"How to ensure management commitment and how to find evidence that our management is taken responsibility to this system requirements. "

On our side the management was been performing their daily Operation's Committee Review. In here, they discuss what happen in our production line, downtime's, process-related problem. A minutes of the meeting was documented. Each department had an action item to accomplish. These action items are tracked daily and was been continuously followed up by the GM. In my view, this could be part of management review.
Hope this helps. :bigwave:

Vash :cool:
 
M

M Greenaway

Personally I think there is more to it then looking to see who was at a managment review meeting !
 