Q
quick_silver
hi to all,
I was assigned in developing a worksheet monitoring on OEE. Currently I was doing the Availability calculations. Our plant is very huge there were about 10 departments and roughly 6 hectares(roofed). My superiors wanted to determine the line availability.
1)So my calculations are based on the downtime monitoring of one line. But i was using the rated speed of the slowest machine of the line.
2) A department is consists of several similar lines, I calculated the departments line Availability by using the sum of the downtimes of all lines and the sum of the gross operating hrs less the scheduled downtime. Is this right?
3) There were some departments that have spare machine. I consider it 100% on availability but i think they will have an issue on machine utilization. each area has a spare machine for this department because if the machine will breakdown and no spare it would mean stop production of the whole plant. How is the utilization calculated? am i right that this is not captured in the OEE?
any inputs will be greatly appreciated..Thanks
I was assigned in developing a worksheet monitoring on OEE. Currently I was doing the Availability calculations. Our plant is very huge there were about 10 departments and roughly 6 hectares(roofed). My superiors wanted to determine the line availability.
1)So my calculations are based on the downtime monitoring of one line. But i was using the rated speed of the slowest machine of the line.
2) A department is consists of several similar lines, I calculated the departments line Availability by using the sum of the downtimes of all lines and the sum of the gross operating hrs less the scheduled downtime. Is this right?
3) There were some departments that have spare machine. I consider it 100% on availability but i think they will have an issue on machine utilization. each area has a spare machine for this department because if the machine will breakdown and no spare it would mean stop production of the whole plant. How is the utilization calculated? am i right that this is not captured in the OEE?
any inputs will be greatly appreciated..Thanks