Another GR&R is what the auditor wants. The feature is on the control plan even though it's not an SC - if it's on the control plan you have to have an R&R - that's a given. My alternate approach is to take it off the control plan.
What bothers me most about this is the cost of this R&R.
50 parts measured on CMM - $937.50
3 operators measuring 50x3 parts - $1125
QE project time - $320
TS Auditor satisfaction - PRICELESS!
What bothers me most about this is the cost of this R&R.
50 parts measured on CMM - $937.50
3 operators measuring 50x3 parts - $1125
QE project time - $320
TS Auditor satisfaction - PRICELESS!