Hi fellows.
I have been preforming CPk analaisys from time ago and I thought I really understand this concept but after read some posts here I'm totally confuse as I was at the beginning
.
My questions are:
1. Based on what I read, what really care is the PPk since is this one is the value that tell us how good (or bad) our process is currently doing and what determine if process should keep going or stopped. Am I right?
2. To perform a PPk analysis do we should ensure our process is statistically on control?
3. Let’s suppose I have new crimping equipment and before release it to regular production I want to be sure if this is capable. Do I should first to prepare Xbar-Rbar graphs? (Let's suppose crimp height is the characteristic and is normally distributed) if so,
4. How many samples with N=5 do I should take to initiate the SPC analysis?
5. Once the SPC graph shows a "Normal" trend, from the data that I use to prepare it, how many values do I should take to prepare the PPk analysis? Do those values should be the Xbar from subgroups or just the Xi values?
Maybe those are a dumb questions but I want to feel comfortable again next time I prepare a capability analysis. By the way I'll really appreciate any input from you guys.
I have been preforming CPk analaisys from time ago and I thought I really understand this concept but after read some posts here I'm totally confuse as I was at the beginning
My questions are:
1. Based on what I read, what really care is the PPk since is this one is the value that tell us how good (or bad) our process is currently doing and what determine if process should keep going or stopped. Am I right?
2. To perform a PPk analysis do we should ensure our process is statistically on control?
3. Let’s suppose I have new crimping equipment and before release it to regular production I want to be sure if this is capable. Do I should first to prepare Xbar-Rbar graphs? (Let's suppose crimp height is the characteristic and is normally distributed) if so,
4. How many samples with N=5 do I should take to initiate the SPC analysis?
5. Once the SPC graph shows a "Normal" trend, from the data that I use to prepare it, how many values do I should take to prepare the PPk analysis? Do those values should be the Xbar from subgroups or just the Xi values?
Maybe those are a dumb questions but I want to feel comfortable again next time I prepare a capability analysis. By the way I'll really appreciate any input from you guys.