5
I did a search on CFAT and came up blank so I hope this is the correct place to post this thread.
I am in the middle of setting up testing for a part to be supplied to the military and they have required a CFAT Test Plan, a seven page document that describes the test I am going to perform on this first article (plus verification of all print notes) along with the date of the test, and, once the test is completed, the Test Report that is to be completed within 50 days of the test. My plan was approved and I have been informed the test does not have to be observed by a government rep. The test will be performed without a problem so that is not my concern.
In the template instructions for completing the report once the test has been completed, there are directions that indicate the format/numbering system must be maintained, etc...etc...or the test report will be failed and you start the entire process over. What I'd like to know is if anyone here has completed a CFAT report in the past and could steer me to an example of a completed report. I'm looking for something I can use as a guide.
I've done PPAPs and ISIRs but this CFAT thing is a whole new animal for me.
I am in the middle of setting up testing for a part to be supplied to the military and they have required a CFAT Test Plan, a seven page document that describes the test I am going to perform on this first article (plus verification of all print notes) along with the date of the test, and, once the test is completed, the Test Report that is to be completed within 50 days of the test. My plan was approved and I have been informed the test does not have to be observed by a government rep. The test will be performed without a problem so that is not my concern.
In the template instructions for completing the report once the test has been completed, there are directions that indicate the format/numbering system must be maintained, etc...etc...or the test report will be failed and you start the entire process over. What I'd like to know is if anyone here has completed a CFAT report in the past and could steer me to an example of a completed report. I'm looking for something I can use as a guide.
I've done PPAPs and ISIRs but this CFAT thing is a whole new animal for me.