E
engjane
We are getting snowed under with Certs of Analysis from our suppliers and we're beginning to question their validity.
Here are some of the thoughts we are having:
1) We dont supply CoA's to our customer so why do we need them from the next level down?
2) We don't do much with them except a quick check and file....couldnt they stay at the suppliers site unless needed?
3) What additional, if any, items should our suppliers be doing to remove the need for COA's.
We havent got round to re-reading TS (we're prepping for a surveillance audit and we're down three team members so its a little busy
) but I thought if I dropped a quick note on Elsmar, perhaps some wise quality warriors out there could help us.
Any wisdom is much appreciated
Jane
Here are some of the thoughts we are having:
1) We dont supply CoA's to our customer so why do we need them from the next level down?
2) We don't do much with them except a quick check and file....couldnt they stay at the suppliers site unless needed?
3) What additional, if any, items should our suppliers be doing to remove the need for COA's.
We havent got round to re-reading TS (we're prepping for a surveillance audit and we're down three team members so its a little busy
Any wisdom is much appreciated
Jane