Hi Guys,

Just would like get your opinions, in a control plan, under process name / operation, how to identify inspection, for an example final inspectio. Is it ok , if we final inspection under process name/operation column. For me it seems wrong, because inspection is not a process.

For incoming inspection, we can identify as material receiving process, how about final inspection?

Thank you
Rgds,
Murugan
 
Elsmar Forum Sponsor

bobdoering

Stop X-bar/R Madness!!
Trusted Information Resource
#2
Re: Control plan : How to include final inspection

Just would like get your opinions, in a control plan, under process name / operation, how to identify inspection, for an example final inspection. Is it OK , if we final inspection under process name/operation column. For me it seems wrong, because inspection is not a process.

For incoming inspection, we can identify as material receiving process, how about final inspection?
There should be no problem for both your control plan and process flow to have final inspection as a process step. An inspection step has inputs (parts), activity (measurement), controls and outputs (verified parts or lots) - so it can be a process.

Some people do not to add washes to their control plans because it does not transform the part, but that is also not a good idea. The controls for a wash - including measurement and maintenance of the soap or solvent - can affect the quality of the part. It should be in the process flow and control plan. It may have process rather than product controls.
 
B

brahmaiah

#3
Re: Control plan : How to include final inspection

Hi Guys,

Just would like get your opinions, in a control plan, under process name / operation, how to identify inspection, for an example final inspectio. Is it ok , if we final inspection under process name/operation column. For me it seems wrong, because inspection is not a process.

For incoming inspection, we can identify as material receiving process, how about final inspection?

Thank you
Rgds,
Murugan
You can include final inspection as an operation before dispatch.
V.J.Brahmaiah
 
S

sixsigmais

#4
Re: Control plan : How to include final inspection

If iyou use material receiving process as your incoming inpection
Then you can use finish good packing / assembly process as your final inspection.

Material arrived > put at incoming area > incoming inspection
Finish good > put at finish good area > final inspection
 
Thread starter Similar threads Forum Replies Date
G Control Plan - Include the processes for each sub component? APQP and PPAP 2
V Pre-Launch Control Plan Contents - What should I include? FMEA and Control Plans 4
A Prototype control plan FMEA and Control Plans 2
S Which department should prepare the control plan? could you show me a standard regarding to this matter. FMEA and Control Plans 17
G Control Plan & PFMEA Review Procedure? FMEA and Control Plans 1
P IATF 16949 requirement - error-proofing in control plan IATF 16949 - Automotive Quality Systems Standard 3
earl62 What is the best way to control special characteristics in Control plan? Is it Mandatory to have SPC for IATF 16949? IATF 16949 - Automotive Quality Systems Standard 12
I Control Plan (Product/Process specification/ Tolerance) acceptance FMEA and Control Plans 27
J Control Plan use on the manufacturing floor FMEA and Control Plans 4
E Change in control plan - Do I have to do sampling? IATF 16949 - Automotive Quality Systems Standard 1
D All Dimensions listed on control plan FMEA and Control Plans 10
DuncanGibbons Manufacturing Plan vs Material Specification vs Control Plan Manufacturing and Related Processes 5
S Should safety checks be included in the Control Plan? IATF 16949 - Automotive Quality Systems Standard 5
D Supplied Product on Control Plan - Lot ranging in 40,000 pcs per product FMEA and Control Plans 3
M Is there any pre-defined Control plan format/template acc. VDA? VDA Standards - Germany's Automotive Standards 0
A Redesigning our process flow chart, PFMEA and Control Plan Process Maps, Process Mapping and Turtle Diagrams 4
D Link between FMEA, flow chart and control plan FMEA and Control Plans 10
M Dynamic Control Plan Draft - need review FMEA and Control Plans 2
Ashland78 IATF 16949 Control Plan Authorizations IATF 16949 - Automotive Quality Systems Standard 2
N Control plan evaluation methods - Which methods should be carried over from the PFMEA? FMEA and Control Plans 3
Rameshwar25 What is a Control Plan at "Material Level"? IATF 16949 - Automotive Quality Systems Standard 4
L Control Plan - Multiple Process Steps FMEA and Control Plans 8
O Difference Between PFMEA & Control Plan FMEA and Control Plans 3
W Purchased Part Control Plan (IATF 16949) FMEA and Control Plans 7
J VDA audit, control plan - My hair is almost gone now VDA Standards - Germany's Automotive Standards 5
Howard Atkins MSAs are now required on every feature of the control plan - IATF 16949 IATF 16949 - Automotive Quality Systems Standard 13
Jeff Putman EQI Prelaunch Control Plan - Definition Customer and Company Specific Requirements 0
V How to Add Annual Revalidation requirements to Control Plan? FMEA and Control Plans 5
N Control plan references FMEA and Control Plans 6
L Simple Example for PFMEA / Control Plan Training Training - Internal, External, Online and Distance Learning 1
J Functional group / area responsible on a Control Plan IATF 16949 - Automotive Quality Systems Standard 1
T Should Testing be a separate operation in the Control Plan? FMEA and Control Plans 5
M Annual Layout requirements for PPAP/Control Plan FMEA and Control Plans 6
T IATF 16949 Control Plan and Process Monitoring Requirement(s) IATF 16949 - Automotive Quality Systems Standard 1
J Why Control Plan Review needs to be Approved by the Customer IATF 16949 - Automotive Quality Systems Standard 1
B PFMEA and Control Plan Links APQP and PPAP 2
A Corrective Action Column in Control Plan and aligning PFD, PFMEA and Control Plan FMEA and Control Plans 6
M Control Plan MSA's - Pressure Gages IATF 16949 - Automotive Quality Systems Standard 2
S Family / Generic type of FMEA & Control Plan and Symbols FMEA and Control Plans 3
V Do I need to add everything on print to control plan? FMEA and Control Plans 1
H Control plan example format for CNC machining activities FMEA and Control Plans 3
M Mention "according to Work Instruction" in Control Plan FMEA and Control Plans 3
W Does TS16949 require MSA on all measurement systems in the Control Plan? Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 5
T Software for linking Process Flow Diagram, Process FMEA and Control Plan APQP and PPAP 9
S Attribute G&R for all Visual Controls in Control Plan Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 1
I Any recommendations on software for managing the APQP, PPAP, PFMEA, Control Plan etc? Quality Assurance and Compliance Software Tools and Solutions 2
F What goes into a Control Plan? FMEA and Control Plans 1
J Tighter Tolerances than Control Plan FMEA and Control Plans 1
E Control Plan Contents - Part Number / Latest Change Level FMEA and Control Plans 2
R Recording Control Plan Changes Document Control Systems, Procedures, Forms and Templates 3

Similar threads

Top Bottom