Cristi Cobrac
Cristi
I found different interpretation of rules and contain of Control Plan.
In the last time to different auditors say that Work instruction must be added in Control Plan and for this point the give nonconformity in audit.
I read and reread the APQP (base of Control Plan) and others example from different sources and I have not found this topic as “Work instruction must / have to added in Control Plan” (in text or in example).
In my opinion Work instruction is a document result behind Control Plan (request of product or process characteristic).
There are various opinions that WI should be added at “Specification / Tolerance’ or at “Control Method”...what is true, how it should be?
Thank you!
In the last time to different auditors say that Work instruction must be added in Control Plan and for this point the give nonconformity in audit.
I read and reread the APQP (base of Control Plan) and others example from different sources and I have not found this topic as “Work instruction must / have to added in Control Plan” (in text or in example).
In my opinion Work instruction is a document result behind Control Plan (request of product or process characteristic).
There are various opinions that WI should be added at “Specification / Tolerance’ or at “Control Method”...what is true, how it should be?
Thank you!