B
Dear all,
Here is a case of Project Schedule variation, where in which the delivery date for the project is exceeded but still the project execution is in progress and during the data analysis we found the issue.
Kindly suggest me a right process that when the actions to be taken for the deviation in the delivery schedule? immediately after finding it or after the completion of the project?
Thanks in advance
Bhavya
Here is a case of Project Schedule variation, where in which the delivery date for the project is exceeded but still the project execution is in progress and during the data analysis we found the issue.
Kindly suggest me a right process that when the actions to be taken for the deviation in the delivery schedule? immediately after finding it or after the completion of the project?
Thanks in advance
Bhavya