M
mikethepenguin
Hello all,
I am consulting for a company which drastically needs to implement change. They have acknowledged that change is needed but there is resistance which is quite confusing at first. The overall cost per hour to the business is ?50 per hour in this example.
The scenario.
Maintenance - These guys assembly the products together and have had issues in the past with tolerancing, fit issues, and general assembly issues. They have some "gripes" and some "genuine issues" that they have proposed to the design department. However, these have not be taken on board although they have been listened to.
Design - These guys get to hear all the "gripes" and "genuine issues" from Maintenance. However, in the past design time has meant that changes are not made because for example. If a design change is 20 hours = ?1000; however, if the assembly time is 5 hours then there is no justification for this design change.
Today
The assembly line of this product is slow due to the nature of the product and the change would actually reduce assembly time, and iron out all the problems. As to today the assembly time has taken 2 weeks (10 working days in the UK) because of issues relating to this part of the product.
Now as a six sigma consultant do I just steam roller the change through or is there another way to resolve this? If any more information is required please let me know. I didn't want to make this too wordy.
I am consulting for a company which drastically needs to implement change. They have acknowledged that change is needed but there is resistance which is quite confusing at first. The overall cost per hour to the business is ?50 per hour in this example.
The scenario.
Maintenance - These guys assembly the products together and have had issues in the past with tolerancing, fit issues, and general assembly issues. They have some "gripes" and some "genuine issues" that they have proposed to the design department. However, these have not be taken on board although they have been listened to.
Design - These guys get to hear all the "gripes" and "genuine issues" from Maintenance. However, in the past design time has meant that changes are not made because for example. If a design change is 20 hours = ?1000; however, if the assembly time is 5 hours then there is no justification for this design change.
Today
The assembly line of this product is slow due to the nature of the product and the change would actually reduce assembly time, and iron out all the problems. As to today the assembly time has taken 2 weeks (10 working days in the UK) because of issues relating to this part of the product.
Now as a six sigma consultant do I just steam roller the change through or is there another way to resolve this? If any more information is required please let me know. I didn't want to make this too wordy.