Hello all,
not new to the forum but it's been sometime since I wrote, so my old account got cancelled (no big deal).
Question for you all: do I have to report all the dimensions on the customer drawing on my internal drawing? even If I will not check those dimensions during production and the customer knows it since I sent him our Control Plan ? (e.g.: Drawing 50 dimensions, CP 5 dimensions)
I mean, during PPAP phase we will check all the dimensions and provide a report to the customer, using the customer's drawing, but including our "reduced" control plan (we don't include our internal drawing in the PPAP documents and customers never asked for it) so that the customer knows very well that we will not be checking 100% of the dimensions (obviously all S/C are included).
At this point, since 45 out of 50 dimensions will not be checked, is it mandatory to have them on our internal drawing anyway?
By checking the ISO 9001 / IATF 16949 I could not find a conclusive answer, because in the following chapters there is a reference to cutomer requirements and special caharacteristic (which are obviously included in internal drawing and control plan), but no mentions of other characteristics:
So...opinions? Help?
not new to the forum but it's been sometime since I wrote, so my old account got cancelled (no big deal).
Question for you all: do I have to report all the dimensions on the customer drawing on my internal drawing? even If I will not check those dimensions during production and the customer knows it since I sent him our Control Plan ? (e.g.: Drawing 50 dimensions, CP 5 dimensions)
I mean, during PPAP phase we will check all the dimensions and provide a report to the customer, using the customer's drawing, but including our "reduced" control plan (we don't include our internal drawing in the PPAP documents and customers never asked for it) so that the customer knows very well that we will not be checking 100% of the dimensions (obviously all S/C are included).
At this point, since 45 out of 50 dimensions will not be checked, is it mandatory to have them on our internal drawing anyway?
By checking the ISO 9001 / IATF 16949 I could not find a conclusive answer, because in the following chapters there is a reference to cutomer requirements and special caharacteristic (which are obviously included in internal drawing and control plan), but no mentions of other characteristics:
- 8.1.1 - A
- 8.2.3.1 - A
- 8.2.3.1.2
- 8.3.3.2 - A & D
- 8.3.5.2 A & B
So...opinions? Help?