I have a customer that is requiring a "Inspection Point Program". They already require WPS, WQTRs, Detail Quality Control Plan, Manufacturing Procedures, Repair Procedures, Dimensional Control Procedure, Visual Inspection Procedure, NDT Procedure, MTRs, Quality Inspection Test Program and my ISO QC manual as well as my Level II and III procedures. I am lost. What information do they want that I havent coverd already? What is the "Inspection Plan Program"? The only thing I acan think of is a list of all the hold points. Please clue me in.
Thanks
 
Elsmar Forum Sponsor

Marc

Fully vaccinated are you?
Leader
#2
I personally haven't heard of an "Inspection Point Program". Maybe one of the other here can help, but my first advise is to ask your customer for a description (in writing) of what an "Inspection Point Program" is, as well as their expectations.
 
#3
Does the one customer require ALL these documents? What industry is this?

It seems that at least two documents listed could be the same thing as is being requested, however, we need to know a little more about what's (currently) in each.
 
T

tonefordays

#4
They may be wanting documented "Hold Points" or inspection points to assure that inspection is conducted in sequence with part production. Based on the qualification requirements you listed, I'm assuming this is for a part that requires welding with nondestructive inspection.

Welding is a process that requires inpsection before, during, and after actual welding has taken place.

Below is a summarized list of some things to consider.

Inspection before welding:
-Review all applicable drawings and standards.
-Check PO to ensure base and filler materials are properly specified.
-Identify materials as they are recieved against the PO
-Check the CMTR's against any specified requirements.
-Check the condition of the filler metals.
-Check the adequacy and condition of equipment to be used.
-Verify weld joint geometry.
-Verify joint fit up.
-Verify joint clenliness
-Verify WPS and WQTR
-Verify any preheat temps, if required.

Inspection During Welding:
-Check welding parameter and techniques for compliance with WPS.
-Inspect the quality of the individual weld pass. Very important on multi-pass welds.
-Inspect interpass cleaning. (should also be specified on the WPS)
-Verify interpass temperature, if applicable
-Verify that in-process NDT is performed if required.

Inspection after Welding:
-Inspect finished weld appearance to applicable standard.
-Inspect weld size and length.
-Verify dimensional accuracy of completed weldment.
-Select production test samples if needed.
-Evaluate test results.
-Verify that additional NDT is performend, if needed.
-Verify that any PWHT (post weld heat treat) has been performed, if needed.

It is crucial that inspection take place at planned or pre-determined intervals to ensure product conformity. Once welding is complete, many of the things listed above are impossible to inspect. I have a feeling this is what your customer may be trying to get at.
 
B

bowdie

#5
Tonefordays,
They do want everything you listed, it is covered per their specification in the Inspection Test Plan. Their specification is quite clear on that point. We have tried to fish more information about the Inspection Point Program from them but there is a language barrier that makes this difficult.
 
Last edited by a moderator:
B

bowdie

#6
AndyN,
This is for a structural steel job.
As for your comment, "It seems that at least two documents listed could be the same thing as is being requested, however, we need to know a little more about what's (currently) in each." it's worse than that they want a Quality Control Manual, Detailed Quality Control Manual, Manufacturing Procedure and Inspection Test Plan. Our QC Manual with it's Level L and II Procedures, which they rejected, covers all of this. Rejected without comment or direction.
 
#7
AndyN,
This is for a structural steel job.
As for your comment, "It seems that at least two documents listed could be the same thing as is being requested, however, we need to know a little more about what's (currently) in each." it's worse than that they want a Quality Control Manual, Detailed Quality Control Manual, Manufacturing Procedure and Inspection Test Plan. Our QC Manual with it's Level L and II Procedures, which they rejected, covers all of this. Rejected without comment or direction.
I'd take the Inspection Test Plan, cut and paste it and re-title it as the Inspection Point Program, highlight in different font the inspection points and submit that...:notme::notme:
 
Thread starter Similar threads Forum Replies Date
C AS9100 Customer requiring PPAP APQP and PPAP 3
D Can anyone share a Customer Complaint procedure not requiring logging complaints ? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
W MSA on a Hardness Tester to satisfy a Customer who is requiring Hardness Cpk Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 17
O Documenting Processes requiring Customer Notification Misc. Quality Assurance and Business Systems Related Topics 2
M PPAP including FAI Parts - Customer is requiring 5000 measurements APQP and PPAP 15
ScottK Customer requiring that we "rubber stamp" our C of C's for them... Records and Data - Quality, Legal and Other Evidence 10
K Inquiry on kinds of document a customer is requiring us to submit? Quality Tools, Improvement and Analysis 2
S Qs-600? A new customer is requiring it! QS-9000 - American Automotive Manufacturers Standard 3
Claes Gefvenberg Customer Requiring Environmental and Health and Safety Efforts Misc. Quality Assurance and Business Systems Related Topics 20
M We have to have a written request from an automotive customer requiring us to certify IATF 16949 - Automotive Quality Systems Standard 1
Ashland78 IATF Process Control Plans not including customer name Manufacturing and Related Processes 13
T Reporting Adverse Events as Customer Complaints EU Medical Device Regulations 2
A Can a customer send a claim during PPAP? IATF 16949 - Automotive Quality Systems Standard 7
T Non-reportable customer complaints and CER EU Medical Device Regulations 2
G Customer complaint AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 22
GStough Suppliers Starting to Charge A Fee for Customer Audits Supplier Quality Assurance and other Supplier Issues 14
A Customer feedback ISO 13485:2016 - Medical Device Quality Management Systems 11
R VDA Potential Analysis - Similar product from other customer and confidentiality VDA Standards - Germany's Automotive Standards 0
B AS9100 Certification Audit Accounting for Additional Customer QMS Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 15
B IATF 16949 clause 10.2 - requirements following a customer complaint. IATF 16949 - Automotive Quality Systems Standard 9
R Customer Returns / RMA's & the need for NCR's AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 16
M 8.4.1.1 Register of approved suppliers and requirements when they are customer-designated AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 0
T Who's responsible for verification of customer specifications? IATF 16949 - Automotive Quality Systems Standard 17
D Is IATF certification required when customer doesn't require it? IATF 16949 - Automotive Quality Systems Standard 19
G Customer specific characteristics symbols Customer and Company Specific Requirements 2
S Defining special characteristics beyond customer drawing FMEA and Control Plans 11
M Customer PPm (CPPM) on Pass-Thru Items Statistical Analysis Tools, Techniques and SPC 0
V Would the customer drawing change necessitate re-PPAP of the Product? APQP and PPAP 3
S Do we have to create a new PPAP to our customer if our Sub Contractor had to change? APQP and PPAP 10
FuzzyD ISO 13485:2016 Customer Assessment OFI ISO 13485:2016 - Medical Device Quality Management Systems 2
I Restricting scope to one part number for one customer IATF 16949 - Automotive Quality Systems Standard 6
R Customer Listed on Approved Supplier List (ASL) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 0
N 8.3.3.3 Special characteristics - Auditor said we are required to create our own, if no customer char. exist. IATF 16949 - Automotive Quality Systems Standard 10
R Audit from Customer - concerned with IP protection ISO 13485:2016 - Medical Device Quality Management Systems 4
L Documenting internal audit of customer specific requirements IATF 16949 - Automotive Quality Systems Standard 10
L Supplier Performance when your supplier is also the customer ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 17
I Customer Feedback Medical Devices ISO 13485:2016 - Medical Device Quality Management Systems 6
JoeRandom11 Question about Customer Supplied Equipment AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
Moncia Customer satisfaction monitoring - ISO 9001 and 14001 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 24
D Customer Survey Example - ISO 13485:2016 ISO 13485:2016 - Medical Device Quality Management Systems 7
R Customer feedbacks sampling size EU Medical Device Regulations 4
G ISO 9001 - when implementing customer requirement ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 7
P Customer Specific Requirements (Costco Wholesale) IATF 16949 - Automotive Quality Systems Standard 1
S Customer audit report review and approval ISO 13485:2016 - Medical Device Quality Management Systems 3
A Report on handling customer property ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 1
L Customer Complaint Internal Auditing 3
M Corrective action for a defect from customer's mistaken Nonconformance and Corrective Action 1
T Customer Rejecting Part for Basic Dimension Inspection, Prints (Drawings), Testing, Sampling and Related Topics 16
P Customer 8D IATF 16949 - Automotive Quality Systems Standard 8
M Customer Dimensions on Internal Drawing, all of them? IATF 16949 - Automotive Quality Systems Standard 3

Similar threads

Top Bottom