Delivery Monitoring procedure - What is expected in the tracking of delivery?

F

fduguay

#1
Hi Marc and Dawn
Thank you for your reply. What the team members really want to know is , how exactly and what is expected to be seen in the tracking of delivery. Do we track delivery through percentages including lead times? Do we track including PPM scores. I personally have a strong background in SPC, but very little in what is required in monitoring Delivery performance. Is there a simple ABC way for me to convey this to the individuals responsible for this particular benchmark? Also, is this the correct forum Marc, to address these types of questions?
Thank you in advance for the thought you will be putting into answering my question. signed; A green QS9000 Coordinator
 
Elsmar Forum Sponsor
D
#2
I track our on-time delivery by a total of orders shipped as a ration to total orders late. If you ship 100 orders, and you have 1 late that month, your on-time delivery is calculated as a percentage. I have never seen it done any other way and would be curious to see if anyone else has.
 
A

Andy Bassett

#3
Im sure there are many different ways of doing this, the question is are you going to get much help from your company software to do the statistics.

If not i suggest you pick the easiest method of mesurement and use it simply consistently.

One i have used quite frequently is on one particular day of the week (ie Thursday) note how many order positions are late per supplier.

Very rough i know, but it is at least easy to measure and as we have said before in this forum, most important with statistics is that they are apllied consistently.

------------------
Andy B
 

Kevin Mader

One of THE Original Covers!
Staff member
Admin
#4
Is on-time shipping the same as on-time delivery?

In my opinion, they are not. I am aware of what is written in the QS specification, but does on-time shipping gaurantee on-time delivery? What is the Customer expecting?

The Customer expects parts to be there by the promised date (need date). Parts shipped late, meaning being shipped by a mode that requires three days to deliver but you only have two, cause production delays. In order to avoid this, parts may be shipped utilizing 'premium' freight methods to ensure on-time delivery. This is why we track premium freight. Why didn't we hit the ship date (window)? Have we issued corrective actions where necessary? Have we optimized shipping costs?

This item of QS9000 bothers me a bit since the way it is stated does not meet the intent as I understand it. It has folks measuring data that is less useful, but perhaps, more readily available.

Anyway, just a thought popping out of my head....

Back to the group.....


Kevin

(It occurred to me later that the customer may also not want an EARLY delivery as this may also have an adverse affect on their system, especially for direct line suppliers)

[This message has been edited by Kevin Mader (edited 17 November 1999).]
 
Thread starter Similar threads Forum Replies Date
F 100% On-Time Delivery Performance Monitoring Misc. Quality Assurance and Business Systems Related Topics 3
Marc Supplier Delivery Performance Monitoring - Critical Path Scheduling - TE - 4.15.6 Supplier Quality Assurance and other Supplier Issues 2
L On Time Delivery - what percentage is the norm? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 28
Q Customer Satisfaction through On-Time Delivery ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 9
qualprod On Time Delivery KPI for sales? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
M Informational US FDA Final Guidance – Intravascular Catheters, Wires, and Delivery Systems with Lubricious Coatings – Labeling Considerations Medical Device and FDA Regulations and Standards News 0
DuncanGibbons Why is 8.4 post-delivery activities before 8.6 release of products and services in AS9100D? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
S Medical Device Initial Importer (DII) Requirements - Delivery Address 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 0
AnaMariaVR2 Pharmaceuticals News Transdermal and Topical Delivery Systems: FDA & EMA Guidance US Food and Drug Administration (FDA) 0
D Delivery Schedule Performance - IATF 16949 Cl. 9.1.2.1-d IATF 16949 - Automotive Quality Systems Standard 3
N Where I can find an Excel sample/template for recording Delivery Time and Cost Excel .xls Spreadsheet Templates and Tools 2
Y What Clinical Data is required for Drug Delivery System EU Medical Device Regulations 1
Pmarszal Delivery Confirmation? Do we need to save? 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 3
B AS9100 Scope of Registration - Post-Delivery Activities N/A? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
K What can be considered a "Post Delivery Activity" (ISO 9001:2015 Clause 8.5) ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 17
W Business Procedure/Service Delivery Procedure Design and Development of Products and Processes 8
S Boss wants customer delivery signature specimen form Customer and Company Specific Requirements 16
L OTD (On Time Delivery) Tracking and Reporting Misc. Quality Assurance and Business Systems Related Topics 13
A Outsourced Processes Control (Finished Medical Device Delivery, Storage) ISO 13485:2016 - Medical Device Quality Management Systems 10
M Partial Incoming (Receiving) Inspection Delivery Inspection. Inspection, Prints (Drawings), Testing, Sampling and Related Topics 4
M Calculating Capability of Delivery Performance Capability, Accuracy and Stability - Processes, Machines, etc. 5
E Clinical Evaluation Report for a Delivery System ISO 13485:2016 - Medical Device Quality Management Systems 2
R Service Delivery Quality Tracker Document Control Systems, Procedures, Forms and Templates 2
S ANOVA and Test Method Validation for a Drug Delivery Device Statistical Analysis Tools, Techniques and SPC 4
B Is there a necessity of two sets of KPIs for Delivery Process Quality Manager and Management Related Issues 15
K ISO 9001 vs AS9100 Gap Analysis on Delivery Performance and Document Control AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
K AS9100 Post Delivery Support Template AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
B Corrective Action for Deviation (delay) in the Delivery Schedule Quality Manager and Management Related Issues 10
A 2 Aspects of Services Design - Design of the Service and Design of Service Delivery Service Industry Specific Topics 2
S How do you Calculate On Time Delivery? Misc. Quality Assurance and Business Systems Related Topics 17
J Relationship between Quality, Reliability, Price and Delivery Misc. Quality Assurance and Business Systems Related Topics 7
M Understanding AS9100 Clause 7.5.1.4 Post-Delivery Support Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
T CAR (Corrective Action Request) for On Time Delivery Nonconformance and Corrective Action 7
S Delivery Process Owner(s) in an IT Company ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 6
M Delivery Routing VRP (Vehicle Routing Problem) Problem Service Industry Specific Topics 2
D Route Delivery Efficiency Formula - Miles driven, number of deliveries, and time(hrs) Benchmarking 3
M Supplier Rating Form with Quality, Cost, Delivery wanted Document Control Systems, Procedures, Forms and Templates 4
D "On Time Delivery" Flowdown from Large Corporation AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
Q AS9100B Clause 7.5.1.5 - Where did it go in AS9100C? Servicing/Post Delivery Support AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
A Delivery Terminology - When is a product considered "Delivered" AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
S On Time Delivery - Non conformance? Root Causes, Corrective Actions ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 10
E Use of MS Excel for Customer Delivery Tracking Statistical Analysis Tools, Techniques and SPC 6
L Lateness Delivery Notice to Customer ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 7
Q Shipping Measurements (Measurables) other than On-Time Delivery ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
Ajit Basrur Dashboard Software for representing Quality Metrics like DPPM, On Time Delivery, etc. Quality Tools, Improvement and Analysis 4
F Concentrate Delivery System for Hemodialysis - MDD Classification EU Medical Device Regulations 6
H On Time Delivery Report and Tracking spreadsheet template Excel .xls Spreadsheet Templates and Tools 2
D Performance Measurement Data ? Delivery Process Statistical Analysis Tools, Techniques and SPC 2
M Excel sheet for calculating Measurement of Delivery Performance Lean in Manufacturing and Service Industries 2
S Internal Audit Conundrum - Failure to meet On Time Delivery Quality Manager and Management Related Issues 13

Similar threads

Top Bottom