I would like to know which parts of the design and development file need to be updated following a significant design change to an existing device, which has already undergone design transfer.

Obviously the change has to be documented, verified, validated, reviewed and approved. But do the Design Input and Design Output parts of the file need to be updated accordingly?
Or is it enough that the description of the change and the affected documents are recorded in the change form?

Would truly appreciate your reply.
 
Elsmar Forum Sponsor

Jen Kirley

Quality and Auditing Expert
Staff member
Admin
#2
Is this a change of feature?

What are the inputs of the file?

What are the outputs? Besides drawings and/or other specifications, approvals, communications and anything else that is part of this process.
 

somashekar

Staff member
Admin
#3
Hi everyone,

I would like to know which parts of the design and development file need to be updated following a significant design change to an existing device, which has already undergone design transfer.

Obviously the change has to be documented, verified, validated, reviewed and approved. But do the Design Input and Design Output parts of the file need to be updated accordingly?
Or is it enough that the description of the change and the affected documents are recorded in the change form?

Would truly appreciate your reply.
Such a change as you mention must have triggered from some input. Relevant outputs must have been changed accordingly. All that changing are in between. These are the starts and finishes of the change cycle. If these are not recorded, you are delinked.
 
T

Turquoise202

#4
Thank you both for your replies. I am actually not asking this following a specific planned change rather than as a general question for the purpose of writing design control and change control SOPs.
 

somashekar

Staff member
Admin
#5
Thank you both for your replies. I am actually not asking this following a specific planned change rather than as a general question for the purpose of writing design control and change control SOPs.
Such a change control SOP must begin with review of the design inputs with a view to add new inputs or modify existing inputs. Thereon the activities can flow to get to the new design outputs that meet the changed new design inputs.
 

yodon

Staff member
Super Moderator
#6
It would also be a good idea to assess the impact of the change on the Risk Analysis and any Usability aspects.

Since you indicate it's an existing device, it would also be a good idea to assess any impact on the existing product. If this is, for example, a change to improve safety, you might need to take actions for product already distributed and in inventory.
 
Thread starter Similar threads Forum Replies Date
J Managing design verification regression testing of design changes Design and Development of Products and Processes 1
M Handling design changes with use-as-is inventory disposition Quality Manager and Management Related Issues 6
J Ethicon suture box design changes - 2019 Other Medical Device Regulations World-Wide 2
S Design changes a week after regulatory submission 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 1
C Partial Design Validation and changes to a critical supplier 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 4
J Design Verification - Managing Changes Design and Development of Products and Processes 4
O PFMEA - Reducing Severity (S) Ranking - Manufacturing Process Design Changes FMEA and Control Plans 4
Q Looking for documents relating to Medical Device Design Changes Document Control Systems, Procedures, Forms and Templates 5
A Reporting of Design Changes (Color Change Only) EU Medical Device Regulations 5
Uriel Alejandro Small changes on Design Outputs AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 11
A When to verify and when to validate Design Changes 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 4
R Dealing with Device/Design changes by a "Letter to File" vs. 60601 Retesting IEC 60601 - Medical Electrical Equipment Safety Standards Series 10
M Clause 7.3.7 Design and Development Changes - Requirements Scope? IATF 16949 - Automotive Quality Systems Standard 6
K 7.3.7 Control of Design & Development Changes AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
M Doubt about Customer Changes to Product Design Features AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
T How to link Process Design Changes in Serial Production to Design & Development? Design and Development of Products and Processes 6
A Design/Change Control Procedure - How to cope with Changes during Development? 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 26
K Procedure for Categorising Substantial Changes to Design CE Marking (Conformité Européene) / CB Scheme 4
V Procedure to notify Health Canada, FDA and Japan Pal for Minor Design Changes Canada Medical Device Regulations 5
Le Chiffre 510(k) Changes: More bench testing and stricter design controls? 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 1
D ISO 9001 - Customer Approval of Design Changes ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 6
Q ISO 9001:2008 - 7.3.7 - Review of Evaluation of Design and Development Changes ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 1
G Job Traveler Guidance - Frequent changes in the part design Document Control Systems, Procedures, Forms and Templates 6
A DoD Classification of Class 1 and 2 Design Changes and what spec it's called out in Design and Development of Products and Processes 2
A What is the proper definition for Class 1 & 2 design changes AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
L Testing of Small appliances design changes Reliability Analysis - Predictions, Testing and Standards 1
C How to make risk analysis for design changes to existing devices ISO 14971 - Medical Device Risk Management 17
J Can We Exclude ISO9000:2000 Clause 7.3.7 (Control Of Design And Development Changes)? Design and Development of Products and Processes 7
C QS-9000 Clause 7.3.7 - Design Changes - How is this interpreted? Design and Development of Products and Processes 7
W 7.3.7 Control of Design & Dev. Changes Design and Development of Products and Processes 5
Stuart Andrews Design Record Changes and PPAP Re-submission? Design and Development of Products and Processes 13
W Custom production shop with design changes Design and Development of Products and Processes 2
S Is the Design Service Provider required to be ISO 13485 certified? ISO 13485:2016 - Medical Device Quality Management Systems 12
M How to show the effect of the failure mode on the manufacturing process as a customer of product design process? FMEA and Control Plans 0
C MDR - Annex II _3. DESIGN AND MANUFACTURING INFORMATION_a EU Medical Device Regulations 3
C Items used for Design Verification Design and Development of Products and Processes 4
S Software design document NMPA guidance and consultant China Medical Device Regulations 3
L Corrective and Preventive Actions aligned to design related defects. After Work and Weekend Discussion Topics 5
E DESIGN VALIDATION, USABILITY AND CLINICAL EVALUATION request Medical Device and FDA Regulations and Standards News 0
Watchcat REGULATORY WATCHCAT De Novo Post-Mortem 4 – Design Controls Other US Medical Device Regulations 0
D Finding Optimum Design Parameters using Taguchi method? Using Minitab Software 2
S ISO13485:2016 7.3.9 design and development change ISO 13485:2016 - Medical Device Quality Management Systems 3
K Design History File - Looking for Examples of DHF's. 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 5
Watchcat Software validation vs design V&V? Other US Medical Device Regulations 27
S Design & Development records for Medical Devices Packaging and Labelling ISO 13485:2016 - Medical Device Quality Management Systems 8
D Using electronic lab notebooks in the design control process ISO 13485:2016 - Medical Device Quality Management Systems 3
L Essential Design Outputs for SAMD 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 2
T Justification of "Design Excluded" in IATF 16949 Design and Development of Products and Processes 5
H Contract Manufacturer as Design Owner ISO 13485 ISO 13485:2016 - Medical Device Quality Management Systems 6
B Drawings - Design Rules Inspection, Prints (Drawings), Testing, Sampling and Related Topics 26

Similar threads

Top Bottom