Antena,
I could see no verification plan for:
- Completeness of design inputs
- Design's conformity to input requirements
- Conformity of input materials
- In-process conformity verifications
- Final inspection
- Pre-commissioning verfication
- Close out and handover
Forgive me if I have some of your project's terms wrong but you get the idea.
For each stage your plan should identify the:
- Person responsible
- Method used (including any measuring equipment)
- Witnessed by or Hold point Y/N
- Records kept
- Recovery action (in the event of a nonconformity)
I must say that I expected to see your plan for developing your process-based management system or a quality plan.
I shall respond privately on the former expectation.
John