Hello Guys,
I have a question about a difference between a PFMEA & Control Plan in the final inspection operation.
in the PFMEA, in the final inspection operation, there are only two possible failure modes:
2500-01 - mixed parts
2500-02 - damaged parts.
In my control plan, besides those failure modes, I need to add all the previous in-process failure modes. But this way (if I keep adding rows), will not be a link between my PFMEA and CP.
I have asked for my process engineer to add all previous in-process failure modes that the inspector will check, but he says this is not possible since in the PFMEA there are only the failure modes that are produced at each station.
I have attached a PPT illustrating my point.
What do you guys think is the better way to cope with this situation?
Thanks in advance for your feedback,
Regards.
I have a question about a difference between a PFMEA & Control Plan in the final inspection operation.
in the PFMEA, in the final inspection operation, there are only two possible failure modes:
2500-01 - mixed parts
2500-02 - damaged parts.
In my control plan, besides those failure modes, I need to add all the previous in-process failure modes. But this way (if I keep adding rows), will not be a link between my PFMEA and CP.
I have asked for my process engineer to add all previous in-process failure modes that the inspector will check, but he says this is not possible since in the PFMEA there are only the failure modes that are produced at each station.
I have attached a PPT illustrating my point.
What do you guys think is the better way to cope with this situation?
Thanks in advance for your feedback,