So PPAP has become a standard practice these days. So every time someone breaths, we need to do an updated PPAP. However, customers are really bad at returning a signed warrant. So do you chase them down for a signature? Or just file it and wait.

Note: This question refers to subsequent PPAPs where the part has been running for years, not necessarily PPAPs required for initial part approval.
 
Elsmar Forum Sponsor

TPMB4

Quite Involved in Discussions
#2
We're really bad and only chase when we need it. Just been asked for an old one by the same company but different site. Large company so why can't they access it internally? We've done a PPAP based on switching to this new site so they really shouldn't need it. Instead I've had to chase. They're not really interested in helping us so it'll be a chase for sure. Plus they're on extended shutdown so there's going to be a long wait for a reply.
 

Ron Rompen

Trusted Information Resource
#3
Don't really have a choice, unless you are fishing for an audit finding. Yes, customers are lax in signing off and returning PPAP warrants. However, if you contact the buyer, and inform that unless you receive the signed warrant, you are unable to produce and ship what they ordered, you will be surprised at how quickly you get some action.
 

TPMB4

Quite Involved in Discussions
#4
However, if you contact the buyer, and inform that unless you receive the signed warrant, you are unable to produce and ship what they ordered, you will be surprised at how quickly you get some action.
When that works it's funny to see contact's priorities change.

We're a small company dealing with larger multinational companies. We're low down on their priorities but stopping the BMW line is a serious motivator. However it could be a motivator to look for another supplier. So far we've never had a NC for it but we're only certified to 9001. I don't think it's ever been picked up in the past.
 

Ninja

Looking for Reality
Staff member
Super Moderator
#5
FWIW, not having the signed warrant back is a potential risk direct with the customer (outside of any audit).
Are they just "not getting around to signing it", or are they holding leverage to use it against you in the future?

How can you ship material without having the signed warrant? Ron's approach works quickly and easily...but I would throw that out to engineering, launch team or quality...not to the buyer. Annoying buyers is high risk, letting SQE know they might get blamed for delay is much lower risk.
 

try2makeit

Quite Involved in Discussions
#6
I usually send a Deviation to the Program manager asking for authorization to ship parts without a signed PSW. That usually gets a response, especially if the customer needs parts immediate
 

Johnnymo62

Haste Makes Waste
#7
We used a memo in the PPAP package saying if we don't receive an approved or rejected PSW in 30 days, we will assume it's accepted.

One of our customers would change the status in their portal and we used a screen shot of that as approval. FCA, I think.
 

Golfman25

Trusted Information Resource
#8
FWIW, not having the signed warrant back is a potential risk direct with the customer (outside of any audit).
Are they just "not getting around to signing it", or are they holding leverage to use it against you in the future?

How can you ship material without having the signed warrant? Ron's approach works quickly and easily...but I would throw that out to engineering, launch team or quality...not to the buyer. Annoying buyers is high risk, letting SQE know they might get blamed for delay is much lower risk.
Like I said, these PSWs are for parts that are already in PAPP approved production, in some cases for years. The new PSW don't really affect a thing -- just paperwork.
 

optomist1

A Sea of Statistics
Super Moderator
#9
Without a doubt...Customers have a repsonsibility to their part and in a timely manner...of course tactful diplomacy is always welcomed...
 

Johnnymo62

Haste Makes Waste
#10
I would also double check the Customer Specific Requirements to see if Annual PPAPs need a customer signature or not. Some of our automotive customers just required us to have an Annual PPAP on hand in case they need it, but not sent to them or signed.

I can't think of any other PPAPs that would not be a design change, requiring customer approval.
 
Thread starter Similar threads Forum Replies Date
D PSW with waiver statement (hold harmless clause) IATF 16949 - Automotive Quality Systems Standard 3
S PSW - Requirements for "off-the shelf" component that has multiply manufacturing locations Off the Shelf Item Manufacturing and Related Processes 1
B EMPB (Erstmusterprufbericht) VDA form confusion + PSW VDA Standards - Germany's Automotive Standards 4
J PSW (Part Submission Warrant) and Design Requirements APQP and PPAP 14
S Looking for a PPAP PSW, Part Submission Warrant, in Chinese APQP and PPAP 5
L PSW Requirements for a Distributor APQP and PPAP 1
A Is normal for FORD EU ask for the PSW every year APQP and PPAP 5
S APQP, PPAP and PSW Question from a Rookie APQP and PPAP 4
N Customer wants a PPAP/PSW on some Prototype Parts APQP and PPAP 6
Moncia Part Submission Warrant - Customer Requirements for PSW Submission APQP and PPAP 7
D PSW (Part Submission Warrant) Question for Part Number Change APQP and PPAP 9
M Chrysler PSW Sign Off when your product is rated low risk in CQMS IATF 16949 - Automotive Quality Systems Standard 5
L PPAP Approval Woes - Getting signed PSW's back from Customers Supplier Quality Assurance and other Supplier Issues 15
C Who in the supplier organization has to sign the PSW (Part Submission Warranty)? APQP and PPAP 6
R New PSW due to Company Name Change APQP and PPAP 4
M CPK and MSA for Vision System - Example PSW Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 5
R What is PSW - Statistical Process Package + Level 5 APQP and PPAP 7
P Part Submission Form - Need to submit PSW only once? APQP and PPAP 5
Fender1 PPAP-PSW Accuracy Concern - Laser Cut Holes In Formed Fabricated Steel Part APQP and PPAP 15
V Safety and/or Government Regulation question on a PSW (Part Submission Warrant) APQP and PPAP 6
T Who signs PSW's? (PPAP Part Submission Warrants) APQP and PPAP 1
D PSW for Level 1 for a Part Produced for an Order Last Year APQP and PPAP 11
D Product Shipment without Signed PSW - Customer does not provide signed PSW to us APQP and PPAP 13
E PPAP PSW Approval: Customer Drawing or Supplier Drawing APQP and PPAP 4
V Is it OK to put 2 Part Numbers on 1 PSW (Part Submission Warrant)? APQP and PPAP 12
R Waiver for PPAP PSW Functional Approval APQP and PPAP 3
A Does the PSW (Part Submission Warrant) need to be a controlled document? APQP and PPAP 7
E PSW (Part Submission Warrant) for Service Parts APQP and PPAP 4
M What method/program works in tracking PSW's Excel .xls Spreadsheet Templates and Tools 2
A What is PPAP (Production Part Approval Process) Why submit it and/with PSW APQP and PPAP 2
P PPAP Approval - Customer approval of PSW (part submission warrant) APQP and PPAP 5
S Material Supplier Part Submission Warrant (PSW) APQP and PPAP 2
I Confused on PPAP re-submission - Help on PSW (Part Submission Warrant) APQP and PPAP 3
M Spanish PSW (Part Submission Warrant) Needed APQP and PPAP 8
K Resubmission of PSW required by customer because of part number change IATF 16949 - Automotive Quality Systems Standard 8
L PPAP Part Supplied to Multiple Plants - Submit another PPAP or PSW to the new plants? APQP and PPAP 6
T Do They Submit PPAP with a Uniform PSW from Customer? APQP and PPAP 7
G PSW - Obsolete form from old part submissions - Can I use it? APQP and PPAP 6
W Better Understanding of PSW (Part Submission Warrant) APQP and PPAP 7
B New PSW (Part Submission Warrant) - 4th Edition PPAP Manual APQP and PPAP 38
G Part Submission Warrant (PSW) dispute APQP and PPAP 19
B OEM Signed PSW - How long is it valid? What are Ford requirements? APQP and PPAP 7
M PSW (Part Sample Warrant) - When drawing and part numbers do not match APQP and PPAP 4
S Can anybody tell me what the legal status of the Part Submission warrant (PSW) is? APQP and PPAP 3
Y PPAP requirements: Submission date and PSW (Statistical Process Package) APQP and PPAP 6
S ISIR (Initial Sample Inspection Report) vs. PSW (Part Sample Warrant) IATF 16949 - Automotive Quality Systems Standard 5
R PPAP - When to Send a PSW Warrant IATF 16949 - Automotive Quality Systems Standard 5
N What is PSW? What does it entail? APQP and PPAP 1
P PSW (Part sample Warrant) - Restricted or reportable substances APQP and PPAP 13
S Recycling codes on PSW - Restricted or reportable substances APQP and PPAP 4

Similar threads

Top Bottom