ECO (Engineering Change Order) Implementation checklist/work instruction

T

turnit

#1
Hi all! I am currently looking for an eco implementation checklist/work instruction for use in a job shop type of enviroment where the changes we are implementing are customer driven. This affects many areas production, programming, inventory, purchasing, quality control, document control. I was just hoping to find a nice template or generic starting point rather than starting from scratch. Thanks in advance for any help or suggestions!
 
Elsmar Forum Sponsor
B

brahmaiah

#4
Hi all! I am currently looking for an eco implementation checklist/work instruction for use in a job shop type of enviroment where the changes we are implementing are customer driven. This affects many areas production, programming, inventory, purchasing, quality control, document control. I was just hoping to find a nice template or generic starting point rather than starting from scratch. Thanks in advance for any help or suggestions!
Engineering Dept/Design Dept./Drg.Office is/are responsible for controlling drgs.and specifications and to fix a controlled copy stamp on the documents.They are also responsible to issue revised documents and withdraw obsolete documents.If you are a small set up the same function may be carried out by any designated person.But the function shall be performed without fail.
V.J.Brahmaiah
 

Wes Bucey

Quite Involved in Discussions
#5
Engineering Dept/Design Dept./Drg.Office is/are responsible for controlling drgs.and specifications and to fix a controlled copy stamp on the documents.They are also responsible to issue revised documents and withdraw obsolete documents.If you are a small set up the same function may be carried out by any designated person.But the function shall be performed without fail.
V.J.Brahmaiah
Can you cite an authority for your "shall" and for your statement as to who is responsible for putting "controlled copy" stamp on documents?

To my knowledge, there is NO STANDARD requiring the term "controlled copy" be applied to any document. If you have a citation, may we know it, please?
 
D

DrM2u

#6
:argue:
I disagree with Brahmaiah's statrement because there is no cookie-cutter answer to this situation. The responsibilities and authorities for controlling drawings vary from organization to organization and are not always assigned to Engineering. The methods for reviewing and controlling documents also vary from organization to organziation. However the activities must be performed in compliance with the requirements of the applicable standard(s), established processes and/or documented procedures.
 
Thread starter Similar threads Forum Replies Date
D ECO (Engineering Change Order) process questions ISO 13485:2016 - Medical Device Quality Management Systems 7
D Engineering Change Order (ECO) metrics to track ISO 13485:2016 - Medical Device Quality Management Systems 6
M ECO (Engineering Change Order) Record Filing Question Records and Data - Quality, Legal and Other Evidence 1
T Need help developing an ECO (Engineering Change order) procedure Document Control Systems, Procedures, Forms and Templates 3
C Documents not controlled by the ECO (Engineering Change Order) process ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
D How to process Customer ECO's (Engineering Change Orders) ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
J ECO (Engineering Change Order) Control for Unreleased Products Document Control Systems, Procedures, Forms and Templates 3
Q How to close the circle QMS and ECO (Engineering Change Order)? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
Q Document Control ECO (Engineering Change Order) or QMS? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 14
D ECO (Engineering Change Order) Risk Management Criteria and QA Document Control Systems, Procedures, Forms and Templates 19
M ECO (Engineering Change Order) Tracking and Status Report Document Control Systems, Procedures, Forms and Templates 1
V How to measure ECO (Engineering Change Order) ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 2
M Engineering Change Request/Order (ECR/ECO) or Document Change Request/Order (DCR/DCO) Document Control Systems, Procedures, Forms and Templates 30
R ECO (Engineering Change Order) presentation Document Control Systems, Procedures, Forms and Templates 2
R ECO (Engineering Change Order) Question for all experts (fill the blanks) Document Control Systems, Procedures, Forms and Templates 4
K ECO (Engineering Change Order) Revision - Letter change or part number change? Manufacturing and Related Processes 13
Raffy ECN (Engineering Change Notice) / ECO (Engineering Change Order) System Document Control Systems, Procedures, Forms and Templates 1
N Engineering Changes (ECR, ECO, ECN) and how they should be Structured Document Control Systems, Procedures, Forms and Templates 6
Q Filtering ECR/ECO by quality management? Managing Engineering Changes ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 2
D Question regarding ECO process, specifically for Life Science products and defining form fit and function ISO 13485:2016 - Medical Device Quality Management Systems 1
P ECO Disposition - Deviation Needed for Use As Is? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
T Electronic ECO/ECR Process - Software recommendations Document Control Systems, Procedures, Forms and Templates 3
R Parts included/not included in ECO/ECN Document Control Systems, Procedures, Forms and Templates 1
H Drowning in ECR/ECO/ECN Document Changes Document Control Systems, Procedures, Forms and Templates 7
J ECR to ECO to ECN Procedure and numbering system Document Control Systems, Procedures, Forms and Templates 4
J Introducing a new Product Variant - ECO Process? Document Control Systems, Procedures, Forms and Templates 3
Q Are ECO's closed after they are shown to be Effective? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 9
Q How raise en ECO starting from a NC - ECO after NCR? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 8
L Developing an Access ECO Tracking Database - Need help Document Control Systems, Procedures, Forms and Templates 8
D Official Clarification of ECO, PDR, PCR Acronym Definitions ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 12
M How NCR CAR and ECO Interact - Customer Rejection Document Control Systems, Procedures, Forms and Templates 5
M CAR vs ECO/ECN - How do I merge CAR with ECO or ECR/ECN procedure seemlessly Document Control Systems, Procedures, Forms and Templates 5
M Differences between ISO 14001 and EU Eco-Management and Audit Scheme (EMAS) ISO 14001:2015 Specific Discussions 2
M Looking for an ECO/ECN logging software Document Control Systems, Procedures, Forms and Templates 3
M Documentation for Health & Safety (OSHA) require ECO's? ISO 13485:2016 - Medical Device Quality Management Systems 11
J Drawing Revision History Question... Signature on EO or ECO Document Control Systems, Procedures, Forms and Templates 18
N Corrective Actions and ECOs - If an ECO addresses the issue, why do we do CARs ? Nonconformance and Corrective Action 16
Marc Engineering Technician - Suspense 5 April 2021 Job Openings, Consulting and Employment Opportunities 0
Marc Engineering Technician - Suspense 11 February 2021 Job Openings, Consulting and Employment Opportunities 0
Bev D Essential References for Practical Quality Engineering Misc. Quality Assurance and Business Systems Related Topics 0
Revision36 Engineering Change Order Industry Standards Other Medical Device and Orthopedic Related Topics 4
R Do we need issue ECN (Engineering Change Notice) towards updated Material Specification? Design and Development of Products and Processes 2
J UCLA extension Medical Device Engineering Program Training - Internal, External, Online and Distance Learning 0
G Engineering retest in line - Machine stability issues IATF 16949 - Automotive Quality Systems Standard 8
A FDA and NB audit of Engineering Drawings in DHF and DMR. Medical Device and FDA Regulations and Standards News 1
I Good resources for learning statistics (quality engineering related) Statistical Analysis Tools, Techniques and SPC 10
B Lessons Learned Implementing ISO 50001 (Chemical Engineering Progress) Other ISO and International Standards and European Regulations 0
G Engineering Specifications - APQP APQP and PPAP 5
O Vendor vs Engineering Document Control ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 1
C E signatures on Engineering Change Notes AS9100 / AS9116 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3

Similar threads

Top Bottom