I work for a mid-sized medical device manufacturer and am the sole documentation specialist for the organization. We have a difference of opinion on whether our change control documents should be called Engineering Change Request/Order (ECR/ECO) or Document Change Request/Order (DCR/DCO).

The rationale for ECO is that it seems to be the familiar term used by larger medical device companies while the DCO would be more appropriate for changes made outside the engineering area, such as Marketing, Finance, etc. which have nothing to do with Engineering.

Is one more appropriate than the other for a Medical Device Manufacturer? We are currently using ECO and all our documentation references that.

Thank you.
 
Elsmar Forum Sponsor
#2
Re: ECR or DCR?

I tend to favor the idea of keeping two systems. The ECO is appropriate for product - the changes are often the result of a more rigorous process controls.

A DCR (or similar) is good, IMHO, for the 'lesser' documentation you mentioned, including QMS documents. I'd recommend you use both processes.
 

Frank T.

Involved in Discussions
#3
Re: ECR or DCR?

Would it not be easier to call it a change request/order and have some sort of check box that differentiates the two.

Although I am not familiar with Medical Device manufacturing, my philosophy is to K.I.S.
 
Last edited:

ScottK

Not out of the crisis
Staff member
Super Moderator
#4
Re: Engineering Change Request/Order (ECR/ECO) or Document Change Request/Order (DCR/

I also keep two systems but defined them differently than Andy...

ECO's are for engineering drawings. The CAD designer is the owner of the system.
DCR's are for everything else - procedures, external documents, forms, specifications, etc. DC Manager is the owner of that system.

When I came on board the ECO process was set up and functioning well, so I decided to leave it be and built the DCR system.

We are entertaining thoughts of consolidating them in the next year as drawings are really just another document.
 

Kevin Mader

One of THE Original Covers!
Staff member
Admin
#5
Re: Engineering Change Request/Order (ECR/ECO) or Document Change Request/Order (DCR/

I’m with Andy on this one, but I’ve seen this done both ways. It might be helpful to think about this topic in these contexts:

1. Engineering changes are more closely associated with design changes that include design and product level documentation. These documents support design requirements and specifications as part of Design Control. While they might be physically represented on paper spec sheets and drawings, they are product oriented and technical in nature.

2. Documentation changes are more closely associated with changes to documentation used to establish the QMS procedures. Less technical in nature and not product oriented. For instance, you do not need an independent reviewer to establish a change to a procedure where as you need one to make a design change/release.

This said - there is plenty of mud! A good example might be a design verification protocol. While the creation of a protocol will definitely tie into product documentation (e.g. design requirements specification), the document itself is created to support a QMS requirement. Many folks process a review of the protocol under the Document Control hat rather than the Design Control hat.

When folks have difficulty in determining which to process to use for a given change, they tend to perform the more rigorous review which is generally the design review using an independent reviewer. This might be viewed as overkill, but a safe (safer?) way out when reviewing a change. Keep in mind that while both processes are similar, there are enough differences in the contexts of what is reviewed and how changes are reviewed that, in my opinion, warrant keeping the control processes distinct.

Good question by the way.

Regards,

Kevin
 

joshua_sx1

Quite Involved in Discussions
#6
Re: Engineering Change Request/Order (ECR/ECO) or Document Change Request/Order (DCR/

For me, you can use either of two… and to make them more effective in your organization, you have to define their terminologies in your manual and/or procedures – meaning, document their meaning…

…so everybody involved shall have the same interpretation when dealing with your manual and/or procedures…
 

Helmut Jilling

Auditor / Consultant
#7
Re: ECR or DCR?

I tend to favor the idea of keeping two systems. The ECO is appropriate for product - the changes are often the result of a more rigorous process controls.

A DCR (or similar) is good, IMHO, for the 'lesser' documentation you mentioned, including QMS documents. I'd recommend you use both processes.
I agree with bot Andy and Kevin. I would only point out a way to simplify the thinking.

All of them are doc changes. However, Engineering change requests are a subset, and frequently go much deeper, can impact product design, tooling, customer approval requirements, PPAPs, ...many more links and ripples.

So, most organizations have developed a specialized process for doc changes related to Engineering. The others can be done more simply.
 

Kevin Mader

One of THE Original Covers!
Staff member
Admin
#8
Re: Engineering Change Request/Order (ECR/ECO) or Document Change Request/Order (DCR/

Joshua – Yes. Operational definitions are important and key to improving communication within the organization and when communicating to outsiders (e.g. auditors). I’d say your comment on establishing a common language is good advice in all arenas.

Good point Helmut. I can say that even though we have fairly good operational definitions, folks in Engineering seemingly struggle the most with selecting the right process - design changes (special emphasis) vs. document changes (more general). Also of note, folks tend to migrate towards the simpler path (document control) even when the more robust (and involving the most effort) design change control process is warranted.

To ensure less frequent occurrences, I’ve instructed my team to advise on these matters throughout the design/product development process. We also do frequent DHF and DMR audits to ensure that proper reviews using the proper control processes have been followed upon project completion and throughout our sustaining efforts. We’re not perfect, but we have significantly improved.

Good discussion folks!

Regards,

Kevin
 
S

SandraD

#9
Re: Engineering Change Request/Order (ECR/ECO) or Document Change Request/Order (DCR/

In my experience, either term is fine as long as you define the scope of what your ECO / DCR covers (e.g. if you call it a DCR and include non-document items, then just be sure to define that in your procedure). Training is the key - make sure your employees know how to use the form. Also, make sure your procedures are clearly written so regulatory agencies are also clear on how you're using them.

SandraD
 
H

hoef03

#10
Re: Engineering Change Request/Order (ECR/ECO) or Document Change Request/Order (DCR/

I am trying to develop a DCR process, do you have an example of your request form?
 
Thread starter Similar threads Forum Replies Date
J Class 1 Medical Device ECR (Engineering Change Request) Changes 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 4
S Engineering change order versus a design change request ISO 13485:2016 - Medical Device Quality Management Systems 1
Q ECR (Engineering Change Request) or NCR (Nonconformance Report) in Fabrication? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 12
D Launch Change Request Form vs. Engineering Change Form Document Control Systems, Procedures, Forms and Templates 5
T From ECR (Engineering Change Request) to ECN (Engineering Change Note) - double work! Document Control Systems, Procedures, Forms and Templates 2
9 ECR (Engineering Change Request) process - Please critique / review Document Control Systems, Procedures, Forms and Templates 10
W Engineering ECR (Engineering Change Request) and ECN (Eng Change Notice) Procedures Document Control Systems, Procedures, Forms and Templates 3
K When to use an Engineering Change Request (ECR) Document Control Systems, Procedures, Forms and Templates 8
O ECN (Engineering Change Notice) to ECR (Change Request) Database with Email Report Document Control Systems, Procedures, Forms and Templates 8
U Advice on Engineering Change Request (ECR) software Software Quality Assurance 4
sardonyx ECR (Engineering Change Request) Flowchart - Is this a work instruction Document Control Systems, Procedures, Forms and Templates 9
G Engineering Change Request (ECR) / Notice (ECN) - Seeking Example Forms Document Control Systems, Procedures, Forms and Templates 21
Revision36 Engineering Change Order Industry Standards Other Medical Device and Orthopedic Related Topics 4
D ECO (Engineering Change Order) process questions ISO 13485:2016 - Medical Device Quality Management Systems 7
R Do we need issue ECN (Engineering Change Notice) towards updated Material Specification? Design and Development of Products and Processes 2
D Engineering Change Order (ECO) metrics to track ISO 13485:2016 - Medical Device Quality Management Systems 6
C E signatures on Engineering Change Notes AS9100 / AS9116 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
Icy Mountain Engineering Change Order...Modification Order Document Control Systems, Procedures, Forms and Templates 18
A Software Suggestions for Engineering Change/QMS Design and Development of Products and Processes 2
Q Change of fields - Quality Engineering Electronics Vs medical Devices Career and Occupation Discussions 20
M ECO (Engineering Change Order) Record Filing Question Records and Data - Quality, Legal and Other Evidence 1
T Engineering Change Management Systems Document Control Systems, Procedures, Forms and Templates 3
M Engineering Change Management Generic Procedure Manufacturing and Related Processes 3
S Ford Motor Engineering Change Level definition Customer and Company Specific Requirements 6
T Need help developing an ECO (Engineering Change order) procedure Document Control Systems, Procedures, Forms and Templates 3
C Documents not controlled by the ECO (Engineering Change Order) process ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
D How to process Customer ECO's (Engineering Change Orders) ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
J ECO (Engineering Change Order) Control for Unreleased Products Document Control Systems, Procedures, Forms and Templates 3
L Engineering Change Control Software Systems - Recommendations? Document Control Systems, Procedures, Forms and Templates 2
L The Perfect Engineering Change and Concessions Management System Document Control Systems, Procedures, Forms and Templates 8
M Formula for Prioritizing Engineering Change Requests (ECR)? Document Control Systems, Procedures, Forms and Templates 1
Q How to close the circle QMS and ECO (Engineering Change Order)? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
Q Document Control ECO (Engineering Change Order) or QMS? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 14
D Management of Change - MOC Procedure and Forms - Engineering, Project, Safety Systems Manufacturing and Related Processes 1
Q ECR?s (Engineering Change Requests) in Engineering? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
M Is ECN (Engineering Change Notice) Necessary for Part Number Change IATF 16949 - Automotive Quality Systems Standard 4
D ECO (Engineering Change Order) Risk Management Criteria and QA Document Control Systems, Procedures, Forms and Templates 19
Q How to monitor Engineering Change Requests? Document Control Systems, Procedures, Forms and Templates 7
M ECO (Engineering Change Order) Tracking and Status Report Document Control Systems, Procedures, Forms and Templates 1
J Engineering/Document Change Notice Procedure required? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
P How to specify criteria for TECN (Temporary Engineering Change Notice) Document Control Systems, Procedures, Forms and Templates 3
T ECO (Engineering Change Order) Implementation checklist/work instruction Document Control Systems, Procedures, Forms and Templates 6
V How to measure ECO (Engineering Change Order) ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 2
M Definition Engineering Change and Document Change - Definitions Definitions, Acronyms, Abbreviations and Interpretations Listed Alphabetically 2
pammesue Managing ECN (Engineering Change Notice) Blueprints Database..any solutions? Document Control Systems, Procedures, Forms and Templates 2
Q How to implement an External Engineering Change ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 2
J Automated Engineering Specification Change Notifications? IATF 16949 - Automotive Quality Systems Standard 5
J Reducing Engineering Change Orders Document Control Systems, Procedures, Forms and Templates 16
R What's the difference between Engineering (ECN) and Process (PCN) Change Notes? FMEA and Control Plans 4
R ECO (Engineering Change Order) presentation Document Control Systems, Procedures, Forms and Templates 2

Similar threads

Top Bottom