We're preparing for our AS9100 certification coming up soon and would like your opinion if we're allowed to exclude 7.4.1 & 7.4.2 or not?
Our purchasing group is in another country (Canada), the factory is in the US.
The US group receive orders/requirements from customers and communicate these requirements to purchasing to procure materials.
Selection, evaluation, re-evaluation of suppliers is a joint effort between US functions and Canadian purchasing group.
Verification of purchased materials is done at the US factory and any noncomformance found is then communicated to purchasing to correct with the supplier.
I will discuss this with our CB soon, but would like your thoughts to exclude or not?
Thank you,
We're preparing for our AS9100 certification coming up soon and would like your opinion if we're allowed to exclude 7.4.1 & 7.4.2 or not?
Our purchasing group is in another country (Canada), the factory is in the US.
The US group receive orders/requirements from customers and communicate these requirements to purchasing to procure materials.
Selection, evaluation, re-evaluation of suppliers is a joint effort between US functions and Canadian purchasing group.
Verification of purchased materials is done at the US factory and any noncomformance found is then communicated to purchasing to correct with the supplier.
I will discuss this with our CB soon, but would like your thoughts to exclude or not?

Thank you,