We need to do an FAI for our customer. The PO calls for a special process requirement (approved plater/NADCAP), but the drawing does not. I know the PO is what we have to go by, but if the material of the detailed parts do not comply with the special process requirements, wouldn't that make the FAI incomplete?


Thank you.
 
Elsmar Forum Sponsor

Cari Spears

Super Moderator
Staff member
Super Moderator
#2
Is the PO requirement a standard quality clause that would only be applicable if you were plating?
PO requirements aren't listed on an FAI - only the drawing (or CAD model if model based with no drawings) requirements - dimensions and flag notes and general notes.
If you have plating requirements on the drawing, then the plating source chosen should be in accordance with any PO clauses, but you don't list the PO clause on the FAI.
 

Rocket27

Starting to get Involved
#3
Is the PO requirement a standard quality clause that would only be applicable if you were plating?
PO requirements aren't listed on an FAI - only the drawing (or CAD model if model based with no drawings) requirements - dimensions and flag notes and general notes.
If you have plating requirements on the drawing, then the plating source chosen should be in accordance with any PO clauses, but you don't list the PO clause on the FAI.
Yes, the PO calls out a Quality code for Special Process, which states approved plater or NADCAP certified and the parts are to be plated according to the Finish note on the drawing. The parts used are not from an approved plater or NADCAP, which to me would be an incomplete FAI, correct?
 

Mike S.

Happy to be Alive
Trusted Information Resource
#4
If your FAIR is to be done according to AS9102, I would say you must include PO requirements. You would check "not complete" on box 19 Form 1 due to the nonconformance.

3.10 FIRST ARTICLE INSPECTION (FAI) - ALSO REFERRED TO AS PRODUCTION PROCESS VERIFICATION
A planned, complete, independent, and documented inspection and verification process to ensure that prescribed
production processes have produced an item conforming to engineering drawings, DPD, planning, purchase order,
engineering specifications, and/or other applicable design documents.
 

Rocket27

Starting to get Involved
#6
If your FAIR is to be done according to AS9102, I would say you must include PO requirements. You would check "not complete" on box 19 Form 1 due to the nonconformance.

3.10 FIRST ARTICLE INSPECTION (FAI) - ALSO REFERRED TO AS PRODUCTION PROCESS VERIFICATION
A planned, complete, independent, and documented inspection and verification process to ensure that prescribed
production processes have produced an item conforming to engineering drawings, DPD, planning, purchase order,
engineering specifications, and/or other applicable design documents.
Given this PO requirement, should Field #9 on Form 2 be listed as "Yes" for the plating..?
 

Cari Spears

Super Moderator
Staff member
Super Moderator
#8
I've never been asked or required to list out PO requirements, quality clauses, or supplier quality requirements manual requirements, on a FAIR report. Only what's on the face of the drawing.

Using a plating source that isn't qualified per the PO requirement is still a reason to reject the FAIR and control whatever potential nonconforming product you have.
 
Last edited:

Rocket27

Starting to get Involved
#9
Obviously not, as the PO requirement for the plating house approvals was not complied with.
I was asking because I have a training sheet stating, " Field 9: Indicate if technical approval is required by the customer." .. so given the requirement is in the PO that to me would be percieved as approval is required, but I know it does not conform.
 

Rocket27

Starting to get Involved
#10
I've never been asked or required to list out PO requirements, quality clauses, or supplier quality requirements manual requirements, on a FAIR report. Only what's on the face of the drawing.

Using a plating source that isn't qualified per the PO requirement is still a reason to reject the FAIR and control whatever potential nonconforming product you have.
Thank you!
 
Thread starter Similar threads Forum Replies Date
M When is FAI required? AS9100 8.5.1.3 and 8.4.3 requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
A AS9100D FAI requirements needed? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
M FAI Requirements of Detail and Assembly AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
APHX02 AS9102 FAI Requirements that pertain to a Dimension 'delta' AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
WCHorn AS9102 Paragraph 5.3-5 - Lapse in Production - FAI Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
S AS9102 FAI requirements - Inspecting with fixtures, templates AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
C Opposite Parts - Mirror Image FAI Requirements Inspection, Prints (Drawings), Testing, Sampling and Related Topics 11
D Partial FAI form requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
P What is the acceptable content on FAI form 3? AS9102 Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
D FAI Reporting of Downstream Requirements Inspection, Prints (Drawings), Testing, Sampling and Related Topics 2
S AS9102 Form 1 Item 19 FAI Complete / Not Complete Box - Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
S FAI (First Article Inspection) and Key Characteristics Requirements - AS9100 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
S FAI compliant to AS9102(A) - Quantity - Measurement Range Results Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
I AS9102 lapse in production requirements - Customer FAI request AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
M What are the FAI requirements for an assembly? New to AS9102 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
R Service Company dealing with FAI requirements - Small stocklist broker AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
C Definition ATP Requirements (QAT, FAT, OSAT, FAI) - How to Satisfy FAT and OSAT? Definitions, Acronyms, Abbreviations and Interpretations Listed Alphabetically 5
R Requirements of Inspection Documentation in AS9100 - Mini-FAI - 8.2.4.1 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
D Following AS9102 for FAI Requirements - Does EVERY Component Need Its Own FAI? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 40
DuncanGibbons Pre FAI production terminology AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
NDesouza Is my Partial FAI an Assembly or Detail? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
M Weld Symbol--Bubble Drawings for FAI Document Control Systems, Procedures, Forms and Templates 4
briteme4 Customer Requests FAI on Tooling Fixture AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
F Circuit board FAI reports- How do you folks deal with these? Inspection, Prints (Drawings), Testing, Sampling and Related Topics 2
R AS9102 FAI Change in Material / Process Supplier AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
NDesouza COTS Items CoC for FAI Documentation AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 12
NDesouza FAI Due Date Calculator AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
Q Change the shape of the raw material FAI AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
P FAI Ballooning ASME Y14.5 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
Q Full or Partial FAI? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
D Partial FAI - AS9102 - One single drawing has 10 part numbers AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
M AS9102B Detail Part/Assembly FAI Form 1 box 13; AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
A When there is a 2 year lapse in production, is a full FAI required? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
M AS9102 FAI Report formats - Boxes in form 1, 2, 3 of AS9102 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
R AS9100 DELTA FAI - Sub-supplier for plating changed AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
B FAI and ANSI Y14.5 Trailing Zeros and Print Tolerances Manufacturing and Related Processes 3
D AS9102 - Assembly FAI for Use As Is or Repaired Parts AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
A AS9102 Delta FAI Require after Rework stock item from stock AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
B AS9102 - Completing Partial FAI's for Baseline Part Numbers AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
K First Article Inspection (FAI) - Equipment used - Dimensions vs. Go/No-Go ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 7
E AS9102 FAI - What makes a COTS modified? (PCB assemblies) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 11
C Is a First Article Inspection (FAI) Procedure required by ISO 13485? ISO 13485:2016 - Medical Device Quality Management Systems 3
B AS9102 FAI & Lower Level Drawings - How should we perform the FAI? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
P AS9102 full FAl or a partial FAI after production inactivity period AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
M FAI AS9102 - What does a First Article Inspection cover? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 11
ScottK Statistical basis for 30 pieces for FAI 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 7
U Whether First Article Inspection Report- FAI is mandatory for regular Human Factors and Ergonomics in Engineering 4
D FAI. Form 2, process or functional test? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 0
G FAI Objective Evidence AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
O AS9102 FAI report Forms 1-3 Document Control Systems, Procedures, Forms and Templates 6

Similar threads

Top Bottom