Hi All, There was an old post regarding when and what to flow down to our sub-tier supplier. We are a mid-size AS9100 contract manufacturer. On one of our customer's PO, it states that "A first article inspection report will be conducted by supplier on the first time build. The FAIR should be in format meeting AS9102 requirements using Form 1 and Form 2." There is no statement that this requirement be flowed down to our PCB supplier. Are we required to ask our supplier to use the same Form 1 and 2 that we are to use???? Help! Thanks in advance.