I need some help settling an argument here.
We get an order from a customer for an assembly. While building the first one, we find quite a few parts that do not fit. Basically, it's another case of the customer using us as their prototyping department without telling us up front. That's ok.
The owner of our small company wants us to go ahead and document a first article inspection and submit it, with notes pertaining to what did not fit. (As we sometimes do on much simpler assemblies with only one or two variations - this one has many) We disagree, saying that if they need it to measure fit and function (it's a wire harness) that's fine, but it is not representative of a first article production piece and time should not be spent inspecting it until all the parts issues are resolved. (it's a long inspection)
If we did submit a first article report with missing/wrong parts, we would still need to repeat the process when the actual first piece assembled from final revised prints/bom's, no? This is no simple task with this assembly, about a 2 hour inspection.
It's engineering/QA's position that we could send a "prototype report" listing the problems, and we will submit first article documents when we build the actual first piece that conforms to the customer's prints and is indeed producable.
Am I missing something here?
Thanks,
Tym
We get an order from a customer for an assembly. While building the first one, we find quite a few parts that do not fit. Basically, it's another case of the customer using us as their prototyping department without telling us up front. That's ok.
The owner of our small company wants us to go ahead and document a first article inspection and submit it, with notes pertaining to what did not fit. (As we sometimes do on much simpler assemblies with only one or two variations - this one has many) We disagree, saying that if they need it to measure fit and function (it's a wire harness) that's fine, but it is not representative of a first article production piece and time should not be spent inspecting it until all the parts issues are resolved. (it's a long inspection)
If we did submit a first article report with missing/wrong parts, we would still need to repeat the process when the actual first piece assembled from final revised prints/bom's, no? This is no simple task with this assembly, about a 2 hour inspection.
It's engineering/QA's position that we could send a "prototype report" listing the problems, and we will submit first article documents when we build the actual first piece that conforms to the customer's prints and is indeed producable.
Am I missing something here?
Thanks,
Tym
In retrofitting aerospace avionics, we frequently had to leave "excess tolerance" for final fit on each individual installation of wiring harnesses because each individual aircraft, even of the same type (747-300), could have individual variation of a foot or more in length because of prior retrofits that didn't meet the blueprints.