FMEA - Current control and occurrence rating

#1
Hello

I have some questions about fmea.

1. All current control (prevention and detection control) should be executed?
I think all current contol should be executed becase i should verify effectiveness of current design.
I see in the recommened action step, all action is contolled and monitored visually in the fmea sheet But regarding current control action (date, responsible person, result) there is no comumn in the fmea.

2 As i know Occurence level is affected by prevention contol and detection contorol is affected by detection control. Initially i might rate occurrence and detection level based on planned or progressing current control
At this time , my rating is just estimation because there is no history or evidence.
Suppose after i perform test as a detection control for actual design from prevention control, and no issue is found. In this case can i correct initial occurrence rating (column next to current control) not column after recommended action because i feel more reliable for current design? If so, occurence score will be reduced without any design change. Is my thinking correct?

WS kang
 
Elsmar Forum Sponsor

Bev D

Heretical Statistician
Staff member
Super Moderator
#2
There are several issues with FMEA that result for misunderstanding it’s intent and how some (many) organizations implement it as a check the box form.
Without discussing the meaninglessness of the RPN value, let’s address the detection and occurrence ratings.

Detection can really only be ‘rated’ with data. That means you must perform the necessary MSA tests for everything from an error proofing control to a human visual inspection. Without this you are only guessing.

Occurence can really only be rated after you have tested the product or process at it’s worst case input tolerance limits and worst case use conditions. You could use random samples that span the range of inputs but that would mean very large sample sizes. You must have data to rate the occurrence or else you are only guessing.

The point of FMEA is that you start at the beginning of the development process. The form is populated only with functions. You should have a lot of questions. Severity and potential causes can be determined by your knowledge of science and physics. Then you begin characterizing and developing your design by running screening experiments to determine the critical input characteristics that control your critical outputs. You then proceed to running experiments that determine the ‘design space’ or what limits you need on the inputs to guarantee your outputs meet specifications and requirements. At the same time you develop and test control methods that maintain those input tolerances and test the outputs to ensure they meet specifications. At the end you will have a completed FMEA.

This is an iterative process. The FMEA is guide to keep you on track. Think about it this way: Severity is an input. Occurrence is an output. Detection is a Control.

Those who fill out an FMEA form at the end of the development process are wasting their time. It’s too late to be anything but a frustrating exercise in filling out the form and scrambling to bandaid the design misses.
 
#3
Thanks.
I agree with your opinion. But still have some confusion. At the beginning occurrence level might be relatively high due to not enough field or reliability data. And later reliability test(current detection control) is competed which means detection control is completed and now i have data which prove my design. So i can reduce occurrence score, right? In this case i can reduce occurrence level without design change. If this this situration happen, should i correct occurrence score which i initially wrote not in the final score? I think this is not design change so basically occurrence is not changed. Or should i put it in the cell in the recommended action? I think there is no reason for this because no current control method is changed and just current control is impemented. I would like to make it clear.
 

Bev D

Heretical Statistician
Staff member
Super Moderator
#4
IF your validation/reliability testing indicates that the occurence level is smaller than what you originally guessed THEN you should reduce the rating to the appropriate level. There is no requirement that says that occurence can only be reduced by a design change. Of course the best approach is to not enter any occurence until you actually know what the occurence is through testing.
 
Thread starter Similar threads Forum Replies Date
S FMEA Process Step or Current Control FMEA and Control Plans 3
A Current Control Periodic Document Reviews - Process Updates in the FMEA FMEA and Control Plans 3
T Current Process Controls Prevention - Process FMEA before Control Plan FMEA and Control Plans 5
xfngrs Ford FMEA Handbook - Current Information FMEA and Control Plans 16
Q FMEA and Risk assessment in MS ACCESS FMEA and Control Plans 2
J FMEA Handbook 2019 IATF 16949 - Automotive Quality Systems Standard 3
J Process FMEA Template with examples - Cold and Hot Forged components FMEA and Control Plans 4
B Why the Greek god Hephaestus should have done a design FMEA (DFMEA) on his giant robot APQP and PPAP 1
P Design FMEA - Detection Rating criteria ISO 14971 - Medical Device Risk Management 3
J Which OEM or customers are now requiring the new AIAG/VDA FMEA format? FMEA and Control Plans 2
C AIAG/VDA FMEA - Is the new better? FMEA and Control Plans 0
I Does anybody use Detection in medical device Design FMEA? ISO 14971 - Medical Device Risk Management 18
P VDA AIAG FMEA - Slides for Quality Audience FMEA and Control Plans 4
P Design FMEA for Industrial Machinery FMEA and Control Plans 3
B AIAG/VDA’s FMEA Manual Is a Major Advance (my take on this subject) FMEA and Control Plans 2
B AIAG-VDA FMEA - When the new format will be required FMEA and Control Plans 5
D Where does "as far as possible" stop? FMEA - EN 14971 ISO 14971 - Medical Device Risk Management 29
R What are the changes in 5th Edition of FMEA manual? FMEA and Control Plans 6
M Risk and Corrective actions - Currently no FMEA's - Car systems Risk Management Principles and Generic Guidelines 8
C FMEA Process assessment In the Draft for the AIAG/VDA FMEA Manual is gone FMEA and Control Plans 0
Jimmy123 Example of a P-Diagram for Process FMEA - Uncontrollable noises FMEA and Control Plans 39
Jimmy123 FMEA - Preventive vs Detection Control FMEA and Control Plans 7
M MANUAL FMEA VDA VDA Standards - Germany's Automotive Standards 1
L Which one is more important for FMEA CC or SC, FMEA and Control Plans 6
G FMEA financial benefits APQP and PPAP 2
M Foundation FMEA: what is it? FMEA and Control Plans 15
eule del ayre Merging FMEA and Quality Control Process Flow FMEA and Control Plans 0
K AIAG/VDA FMEA & Process Control Plans FMEA and Control Plans 0
D FMEA-MSR in the AIAG-VDA Aligned Handbook - What is it? FMEA and Control Plans 5
bobdoering Catching up on the new FMEA book! Funny Stuff - Jokes and Humour 2
bobdoering AIAG VDA FMEA Handbook - 2019 - something familiar about this.... FMEA and Control Plans 37
S New AIAG FMEA Process - How to complete the new format FMEA and Control Plans 32
C FMEA - Multiple function failures considerations FMEA and Control Plans 3
J New FMEA aproach - formular Manufacturing and Related Processes 2
B Confusion on the new FMEA guidebook - Are we supposed to replace our FMEAs? IATF 16949 - Automotive Quality Systems Standard 3
Z Using FMEA for Knowledge Management FMEA and Control Plans 6
D Link between FMEA, flow chart and control plan FMEA and Control Plans 10
K PFMEA (Process FMEA) - Can be common for 3000 products? FMEA and Control Plans 2
R The difference b/w FMEA & Risk analysis as per iso 14971 ISO 14971 - Medical Device Risk Management 8
Jimmy123 ISO 31000 vs FMEA FMEA and Control Plans 1
Jimmy123 What is a Reverse FMEA? FMEA and Control Plans 6
I What does "Class" mean in an FMEA? FMEA and Control Plans 16
M FMEA/DCP Structure and Quantity - Similar Parts and Processes FMEA and Control Plans 7
Marc Definition DFMEA (Design FMEA) - Definition Definitions, Acronyms, Abbreviations and Interpretations Listed Alphabetically 0
D Where does FMEA fit in your ISO 14971 Risk Management process? ISO 14971 - Medical Device Risk Management 13
J Looking for FMEA plastic injection molding FMEA and Control Plans 8
Ashok sunder Is it possible to reduce FMEA Occurrence and Detection Ranking after corrective action taken for customer complaints? FMEA and Control Plans 6
D Design FMEA for a component - Should I make the following assumptions? FMEA and Control Plans 7
N In-Process Production Test Stations in PFMEA (Process FMEA) FMEA and Control Plans 18
C VDA Vol.4 - Evaluation of an FMEA FMEA and Control Plans 0

Similar threads

Top Bottom