Well, now I have been working with PPAP for a week. The goal is that I will help the project department getting a full PPAP for all their new project. This is what I have done, so far.
1)Made a guideline with easy to read and understand demands for each "PPAP requirement" also added a column that shows which requeirements affects each others. Made a clarification on what deparment is responsible for completing each "PPAP requirement". I also stole the PPAP templates from the "sticky" and changed all logos. NOW IT's MY TEMPLATES
2) Made a timeframe connected to the differents stadiums of project development.
What is the next step???? A major problem is that it doesn't exist good control plans, no one used FMEA before, none of Design Records are marked out with specific charistiristics and so on.....
1)Made a guideline with easy to read and understand demands for each "PPAP requirement" also added a column that shows which requeirements affects each others. Made a clarification on what deparment is responsible for completing each "PPAP requirement". I also stole the PPAP templates from the "sticky" and changed all logos. NOW IT's MY TEMPLATES
2) Made a timeframe connected to the differents stadiums of project development.
What is the next step???? A major problem is that it doesn't exist good control plans, no one used FMEA before, none of Design Records are marked out with specific charistiristics and so on.....