#1
Hi everybody,

I'm freshmen in my field. Currently we are on the way to deploy APQP process with our supplier for my company automotive project. There are something as below:

1. I'm reviewing a supplier timeline and have a concern as below:
as you know, in PTO we need to get samples from supplier to proceed it.
Sample should satisfy DIM,Function & Material, the problem is i don't know how to define those samples is affordable to be used for PTO base on above criteria.
Could you give me some recommendation ?

2. Could you give me your general opinion how to manage Supplier APQP process best to meet project timeline.

Thanks
 

AMIT BALLAL

Trusted Information Resource
Trusted
#5
1. I'm reviewing a supplier timeline and have a concern as below:
as you know, in PTO we need to get samples from supplier to proceed it.
Sample should satisfy DIM,Function & Material, the problem is i don't know how to define those samples is affordable to be used for PTO base on above criteria.
Could you give me some recommendation ?
Thanks
Affordable in what sense? And which criteria has to be met for Production trial run? Please provide more information.

In order to be successful at managing the projects, make sure reviews of projects are done on timely basis, otherwise the project will delay from the given timeline.
 
Top