IATF 16949 6.1.2.3(e) Contingency Plan Testing

KimGr

Involved In Discussions
#21
Is anyone differentiating between Contingency Planning and Emergency Action Planning? It seems like many companies are combining the two. My read is Contingency Planning is more for continuity of business while Emergency Planning is reaction to life and death issues, natural disasters and environmental hazards. I'd appreciate anyone's feedback.
We are using the contingency plan as impact not specifically involving safety and using the EAP as a separate document. The subject matter, like fire, chemical spill, etc. is on both documents. EAP for safety. Once the employees are safe we move to the contingency plan for things like no production, missed work, environmental impact.
 
Elsmar Forum Sponsor

Sebastian

Trusted Information Resource
#22
Testing of contingency plan starts from documenting contingency plan. When it is described in detailed manner, it is easier to develop and conduct testing. Especially when we want to do it in a reproducible way. When it is vague, it is up to contingency plan author's imagination, how to do it.
Maybe someone would share with us both elements, plan and testing evidence. Unfortunately I can't.
 
D

darkmago

#23
I received a Non-conformance regarding this, we have been doing testing or simulation of almost everything. But the most difficult we find is Labour shortages, pretending people do not come to work. Any help on this? I am really worried about it.
 

Golfman25

Trusted Information Resource
#24
I received a Non-conformance regarding this, we have been doing testing or simulation of almost everything. But the most difficult we find is Labour shortages, pretending people do not come to work. Any help on this? I am really worried about it.
I have no idea how you would effectively test "calling in a person from the other shift" without actually doing it. Do you have any experiences when you used a person on another shift to cover for someone? Maybe you can use that as "evidence" you plan could work. Or maybe a confirmation that you have the proper contact information to get in touch with the other people? But I'm sure this will make your company so much better. Good luck.
 

AMIT BALLAL

Trusted Information Resource
#25
I received a Non-conformance regarding this, we have been doing testing or simulation of almost everything. But the most difficult we find is Labour shortages, pretending people do not come to work. Any help on this? I am really worried about it.
Brainstorm with your team to find out what can be done to fulfill the objective / test whether it can work when actually required.

I would at least simulate by calling second shift operators and tell them to come to first shift (Just to get their feedback, I won't want them to actually come). I would like to know their availability, problems and whether we need any extra resources in such situations (transportation facility, etc.).
 
#26
I feel as though we can survive the audit on most of our easier issues like equipment or labor, but how are auditors dealing with fire or serious natural disasters. What kind of contingency plans could you have for a 100% loss of your facility?
 

Golfman25

Trusted Information Resource
#27
I feel as though we can survive the audit on most of our easier issues like equipment or labor, but how are auditors dealing with fire or serious natural disasters. What kind of contingency plans could you have for a 100% loss of your facility?
IMO that contingency is on your customer. Not much you can do if you don't have duplicate facilities. Your customer really needs a plan to re-source the work at different alternatives. Google and read up about the fire that just happened last month to a supplier in Michigan.

Fire, explosions rip through instrument panel plant in Michigan
 

Johnson

Involved In Discussions
#28
Hello,

We handle "contiugency plan" as a part of the actions for "risk management process". The follow is abstracted from our procedure.


3.4.4 Contingency plans
As one form of risk treatment method, contingency
plans should be prepared to maintain product output
and ensure customer delivery, for the following but
not limited to the following events:
a) Facility/equipment failures and interruptions
b) Natural disasters, fires.
c) Supplier quality problem or material supply issue
d) Logistics and transportation issue
e) Delivery of non-conforming product to customer.
f) Lack of competent personnel
In case of contingency plans which may effect the
supply to customer, the customers must be notified
with the possible impact and it’s duration
The first piece product shall be validated when the
production is re-started after the contingency plan is
trigged.
The contingency plan shall be tested annually. Desk
top simulation and other options can be applied.
The management review the contingency plan once a
year.
The contingency plan shall be updated based on the
test and review result.
The contingency plan is put on the production site
and shall be accessible to all employees.
 

Johnson

Involved In Discussions
#29
Hello,

I attach a training material on IATF 196969 requirements on contingency plan testing, and how it can be done, from very simple method and complicated one.

The practice have been verified by the third part auditor.

Should you need further help, you may contact me.



Best Regards,
Johnson Shao
 
Last edited:
Thread starter Similar threads Forum Replies Date
C IATF 16949 6.1.2.3 - Contingency Plans Testing Checklist IATF 16949 - Automotive Quality Systems Standard 3
L IATF 16949 Contingency plan requirements / Sanctioned Interpretations? IATF 16949 - Automotive Quality Systems Standard 33
J IATF 16949 Internal Audit question - Auditor's responsibility Internal Auditing 6
S IATF 16949 Internal Audit Example IATF 16949 - Automotive Quality Systems Standard 7
B Remote IATF 16949 audit preparation General Auditing Discussions 10
R IATF 16949 Certification for new site with transferred product--what is the impact with CSR and scorecards? IATF 16949 - Automotive Quality Systems Standard 0
B IATF 16949 Cert Expire- New certification body IATF 16949 - Automotive Quality Systems Standard 5
M IATF 16949 - Audit of Remote Location/Support Site and IT IATF 16949 - Automotive Quality Systems Standard 4
O Informational Ford Motor Company Customer Specific Requirements for IATF 16949:2016 - 08 Jan 2021 Customer and Company Specific Requirements 0
B Updated IATF 16949 - Will IATF 16949 get revised when ISO 9001:202X is released? IATF 16949 - Automotive Quality Systems Standard 4
O Release of Sanctioned Interpretations (SIs) related to Rules 5th Edition and Sanctioned Interpretations related to IATF 16949:2016 IATF 16949 - Automotive Quality Systems Standard 0
S Thoughts on managing ISO 9001, 13485, IATF 16949 and 17025 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 33
P IATF 16949 requirement - error-proofing in control plan IATF 16949 - Automotive Quality Systems Standard 3
R IATF 16949 - Outsourcing of internal audits Internal Auditing 10
eule del ayre Documented Information - Periodic Review of Documents? IATF 16949:2016 / ISO 9001:2015 IATF 16949 - Automotive Quality Systems Standard 34
Crimpshrine13 Laboratory Scope - Calibration vs. Test Methods - IATF 16949 IATF 16949 - Automotive Quality Systems Standard 3
earl62 What is the best way to control special characteristics in Control plan? Is it Mandatory to have SPC for IATF 16949? IATF 16949 - Automotive Quality Systems Standard 12
L IATF 16949 certification costs IATF 16949 - Automotive Quality Systems Standard 3
B FCA US Customer Specific IATF 16949- Critical Characteristics 8.6.2 Customer and Company Specific Requirements 0
B IATF 16949 News Six month extension on all valid IATF 16949 certs IATF 16949 - Automotive Quality Systems Standard 10
earl62 IATF 16949 Clause 9.1.1.1 - What is the batch conformance to specification method? IATF 16949 - Automotive Quality Systems Standard 3
B FCA US IATF 16949 Customer Requirements updates Customer and Company Specific Requirements 3
S Can assembly manufacturing sub-supplier be certified IATF 16949? IATF 16949 - Automotive Quality Systems Standard 6
D IATF 16949 Requirement for CMMI in a Global Company Elsmar Cove Forum Suggestions, Complaints, Problems and Bug Reports 0
M Tips on preparing for IATF 16949 Internal Lead Auditor exam Manufacturing and Related Processes 1
A IATF 16949 4.3.1 - Determining the scope of the quality management system - supplemental IATF 16949 - Automotive Quality Systems Standard 9
S Definition of "worldwide" in view of IATF 16949 and Product conformity IATF 16949 - Automotive Quality Systems Standard 3
R Where does IATF 16949 address Process mapping? IATF 16949 - Automotive Quality Systems Standard 3
A Document "Correspondence IATF 16949 vs ISO13485" available? IATF 16949 - Automotive Quality Systems Standard 0
H Remote product audits in Coivd-19 - IATF 16949 9.2.2.4 IATF 16949 - Automotive Quality Systems Standard 3
S IATF 16949 - Partial traceability of Aftermarket products IATF 16949 - Automotive Quality Systems Standard 5
M IATF 16949 8.5.1.3 Verification of job set-ups - Do we need secondary check? IATF 16949 - Automotive Quality Systems Standard 7
C Industrial scales and MSA (IATF 16949 requirement 7.1.5.1.1) IATF 16949 - Automotive Quality Systems Standard 30
V Generic IATF 16949 Audit Checklist wanted IATF 16949 - Automotive Quality Systems Standard 3
M Scope of Combined ISO 9001 and IATF 16949 QMS - Non-automotive customers ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
D Postpone IATF 16949 audit due to COVID-19 IATF 16949 - Automotive Quality Systems Standard 41
J Does anyone have an excel IATF 16949 Internal Audit checklist I could use? IATF 16949 - Automotive Quality Systems Standard 7
T Reaction Plan To Drive suppliers to IATF 16949 registration IATF 16949 - Automotive Quality Systems Standard 6
B IATF 16949 - Is a Deviation required for sample components in a prototype build? IATF 16949 - Automotive Quality Systems Standard 13
C IATF 16949 - Scope or not? IATF 16949 - Automotive Quality Systems Standard 2
L "IATF-Compliant" IATF 16949:2016 certification? What does this mean? IATF 16949 - Automotive Quality Systems Standard 13
B Go Beyond ISO 9001 WITH IATF 16949 (January 28) [Paid] Training - Internal, External, Online and Distance Learning 1
V IATF 16949 8.4.1 Control of externally provided processes, products and services - Should the CB be on our Approved Supplier List? IATF 16949 - Automotive Quality Systems Standard 10
S Can we provide training plan as corrective action for IATF 16949 Non conformity? IATF 16949 - Automotive Quality Systems Standard 9
C Design and implementation of process audits as defined within IATF 16949 IATF 16949 - Automotive Quality Systems Standard 2
Q VDA 6.3 questions vs IATF 16949 clauses VDA Standards - Germany's Automotive Standards 0
N IATF 16949:2016 7.1.5.3.2 External Laboratory - How to approve the Testing Laboratory without accreditation scope IATF 16949 - Automotive Quality Systems Standard 2
M IATF 16949 (6.1.1 - Planning and Risk Analysis for a remote site) Process Maps, Process Mapping and Turtle Diagrams 5
D IATF 16949 FAQ 24 (8.4.2.2 Countries of Destination) - How is this actually being interpreted? IATF 16949 - Automotive Quality Systems Standard 3
Jimmy123 What is the difference between Error Proofing and Controls? ISO/IATF 16949 - Control Plans FMEA and Control Plans 16

Similar threads

Top Bottom