I have confused with the requirement of clause 7.1.3.1 about manufacturing feasibility. In that clause the standard states:

Methods shall be developed and implemented to evaluate manufacturing feasibility for new product or new operations. Manufacturing feasibility assessments shall include capacity planning. These methods shall also be applicable for evaluating proposed changes to existing operations.

My questions are:

1- Has the above requirement anything new in addition to the requirement of clause 8.2.3.1.3 (organization manufacturing feasibility)?

2- Does the verb "evaluate” mean that the organization shall develop a method to evaluate the Manufacturing feasibility assessments? Or, “evaluate” here means to assess, analysis or doing manufacturing feasibility?

Thanks all
 
Elsmar Forum Sponsor
T

TamTom

#3
I don't think it changed much. However, it did add capacity planning to the evaluation.
Hello,

but how will you review it, in the management review, as the evaluation
under point 9.3.2.1 shows this point?
e) assessments of manufacturing feasibility made for changes to existing operations and for new facilities or new product (see Section 7.1.3.1);

Regards,

TamTom
 
T

TamTom

#5
I tried it now, and as we have not much new parts and machines, I just mentioned,
a process Audit for a changed part,
a capaility study for a new machine and
released PPAP documentation by the customer for a new part.
As Input and evidence that the manuafacturing feasibility is still fine.

Will discuss with my maintanace Manager now and hope it fulfill the requirements in November.

TamTom
 

morteza

Trusted Information Resource
#6
Hi all
I ask again my question.

Based on "manufacturing feasibility" definition in clause 3.1 ("an analysis and evaluation of a proposed project to determine if it is technically feasible to manufacture the product to meet customer requirements."), it can be seen that feasibility includes analysis and evaluation.

Based on the following requirement of clause 7.1.3.1:

"Methods shall be developed and implemented to evaluate manufacturing feasibility for new product or new operations. Manufacturing feasibility assessments shall include capacity planning. These methods shall also be applicable for evaluating proposed changes to existing operations."

Does the above requirement says that we shall evaluate the evaluation done during manufacturing feasibility study? (evaluation of the evaluation)
or
Does the above requirement only require the organization to do manufacturing feasibility?

thanks all
 

AMIT BALLAL

Trusted Information Resource
#7
Please help me understand what is required and how to comply for following requirement of the clause:

"The organization shall maintain process effectiveness, including periodic re-evaluation relative to risks, to incorporate any changes made during process approval, control plan maintenance (see section 8.5.1.1) and verification of job set-ups (see section 8.5.1.3)."


Thanks in advance,
Amit
 

Sebastian

Trusted Information Resource
#8
Does the above requirement says that we shall evaluate the evaluation done during manufacturing feasibility study? (evaluation of the evaluation)
or
Does the above requirement only require the organization to do manufacturing feasibility?
Dear morteza, there is written "Methods shall be developed and implemented to evaluate manufacturing feasibility for new product or new operations." and not "Methods shall be developed and implemented to evaluate manufacturing feasibility analysis for new product or new operations." Feasibility is state of being able to do something. State may vary from e.g. "100 % feasible" to "0% feasible" and therefore evaluation according to developed methods is needed. Answer is: organization has to implement feasibility analysis according to developed methods.

Dear AMIT BALLAL, these are examples of cases where change of already validated process might be required. We shall confirm whether changes we want to implement, do not adversely affect process effectiveness (e.g. capacity, defect ratio) or enhance already determined risks or create new one.
When I look at it, it looks like TS 7.5.2 e), but maybe I am wrong.
 
Last edited:

AMIT BALLAL

Trusted Information Resource
#9
Dear morteza, there is written "Methods shall be developed and implemented to evaluate manufacturing feasibility for new product or new operations." and not "Methods shall be developed and implemented to evaluate manufacturing feasibility analysis for new product or new operations." Feasibility is state of being able to do something. State may vary from e.g. "100 % feasible" to "0% feasible" and therefore evaluation according to developed methods is needed. Answer is: organization has to implement feasibility analysis according to developed methods.

Dear AMIT BALLAL, these are examples of cases where change of already validated process might be required. We shall confirm whether changes we want to implement, do not adversely affect process effectiveness (e.g. capacity, defect ratio) or enhance already determined risks or create new one.
When I look at it, it looks like TS 7.5.2 e), but maybe I am wrong.
Thanks sebastian for reply and help. I am also thinking of the same way, but want to be sure since I am writing a quality manual. And failure to understand the requirement may result in a nonconformance in an audit.
I want inputs from other covers too, which will help to understand what are their opinions for this requirement.
Please help

Thanks,
Amit
 
Thread starter Similar threads Forum Replies Date
M Timing to certify new plant to IATF 16949 IATF 16949 - Automotive Quality Systems Standard 2
L IATF 16949 certification costs IATF 16949 - Automotive Quality Systems Standard 0
B FCA US Customer Specific IATF 16949- Critical Characteristics 8.6.2 Customer and Company Specific Requirements 0
B IATF 16949 News Six month extension on all valid IATF 16949 certs IATF 16949 - Automotive Quality Systems Standard 10
earl62 IATF 16949 Clause 9.1.1.1 - What is the batch conformance to specification method? IATF 16949 - Automotive Quality Systems Standard 3
B FCA US IATF 16949 Customer Requirements updates Customer and Company Specific Requirements 3
S Can assembly manufacturing sub-supplier be certified IATF 16949? IATF 16949 - Automotive Quality Systems Standard 6
D IATF 16949 Requirement for CMMI in a Global Company Elsmar Cove Forum Suggestions, Complaints, Problems and Bug Reports 0
M Tips on preparing for IATF 16949 Internal Lead Auditor exam Manufacturing and Related Processes 1
A IATF 16949 4.3.1 - Determining the scope of the quality management system - supplemental IATF 16949 - Automotive Quality Systems Standard 9
S Definition of "worldwide" in view of IATF 16949 and Product conformity IATF 16949 - Automotive Quality Systems Standard 3
R Where does IATF 16949 address Process mapping? IATF 16949 - Automotive Quality Systems Standard 3
A Document "Correspondence IATF 16949 vs ISO13485" available? IATF 16949 - Automotive Quality Systems Standard 0
H Remote product audits in Coivd-19 - IATF 16949 9.2.2.4 IATF 16949 - Automotive Quality Systems Standard 3
S IATF 16949 - Partial traceability of Aftermarket products IATF 16949 - Automotive Quality Systems Standard 5
M IATF 16949 8.5.1.3 Verification of job set-ups - Do we need secondary check? IATF 16949 - Automotive Quality Systems Standard 7
C Industrial scales and MSA (IATF 16949 requirement 7.1.5.1.1) IATF 16949 - Automotive Quality Systems Standard 30
V Generic IATF 16949 Audit Checklist wanted IATF 16949 - Automotive Quality Systems Standard 3
M Scope of Combined ISO 9001 and IATF 16949 QMS - Non-automotive customers ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
D Postpone IATF 16949 audit due to COVID-19 IATF 16949 - Automotive Quality Systems Standard 41
J Does anyone have an excel IATF 16949 Internal Audit checklist I could use? IATF 16949 - Automotive Quality Systems Standard 7
T Reaction Plan To Drive suppliers to IATF 16949 registration IATF 16949 - Automotive Quality Systems Standard 4
B IATF 16949 - Is a Deviation required for sample components in a prototype build? IATF 16949 - Automotive Quality Systems Standard 13
C IATF 16949 - Scope or not? IATF 16949 - Automotive Quality Systems Standard 2
L "IATF-Compliant" IATF 16949:2016 certification? What does this mean? IATF 16949 - Automotive Quality Systems Standard 13
B Go Beyond ISO 9001 WITH IATF 16949 (January 28) [Paid] Training - Internal, External, Online and Distance Learning 1
V IATF 16949 8.4.1 Control of externally provided processes, products and services - Should the CB be on our Approved Supplier List? IATF 16949 - Automotive Quality Systems Standard 10
S Can we provide training plan as corrective action for IATF 16949 Non conformity? IATF 16949 - Automotive Quality Systems Standard 9
C Design and implementation of process audits as defined within IATF 16949 IATF 16949 - Automotive Quality Systems Standard 2
Q VDA 6.3 questions vs IATF 16949 clauses VDA Standards - Germany's Automotive Standards 0
N IATF 16949:2016 7.1.5.3.2 External Laboratory - How to approve the Testing Laboratory without accreditation scope IATF 16949 - Automotive Quality Systems Standard 2
M IATF 16949 (6.1.1 - Planning and Risk Analysis for a remote site) Process Maps, Process Mapping and Turtle Diagrams 5
D IATF 16949 FAQ 24 (8.4.2.2 Countries of Destination) - How is this actually being interpreted? IATF 16949 - Automotive Quality Systems Standard 3
Jimmy123 What is the difference between Error Proofing and Controls? ISO/IATF 16949 - Control Plans FMEA and Control Plans 16
P IATF 16949 8.4.2.4 Supplier Monitoring IATF 16949 - Automotive Quality Systems Standard 2
V IATF 16949 9.2.2.1 Internal Audit Program - "Process Changes" IATF 16949 - Automotive Quality Systems Standard 11
Sidney Vianna IATF 16949 News Presentations from the latest IATF Stakeholder Event - Expectation that IATF 16949 certification should equate with product quality. Misguided? IATF 16949 - Automotive Quality Systems Standard 7
C IATF 16949 8.3 Exclusion - Manufacturing process design and development IATF 16949 - Automotive Quality Systems Standard 5
J IATF 16949 8.4.1.2 Supplier selection process IATF 16949 - Automotive Quality Systems Standard 4
M IATF 16949 CAPITULO 7.3.2 IATF 16949 - Automotive Quality Systems Standard 3
Casana IATF 16949 7.1.5.3.2 External Laboratory - On Site Calibration IATF 16949 - Automotive Quality Systems Standard 8
M IATF 16949 7.2.3 Internal Auditor Competency - Trainer's competency Internal Auditing 7
P IATF 16949 Clause 8.4.2.3 - Justification for non-certified suppliers IATF 16949 - Automotive Quality Systems Standard 14
M IATF 16949:2016 clause 8.4.2.3 - We don't have ISO 9001:2015 certificate IATF 16949 - Automotive Quality Systems Standard 26
T New role Quality Manager IATF 16949, new company, advise how to get started IATF 16949 - Automotive Quality Systems Standard 2
R Material safety data sheet (MSDS) related clause in IATF 16949 manual IATF 16949 - Automotive Quality Systems Standard 17
R IATF 16949 Clause 8.5.1.6 a) maintenance and repair facilities - Production tooling management and personnel IATF 16949 - Automotive Quality Systems Standard 4
C IATF 16949:2016 Section 8.5.1.2 item d) accessible for use at the designated work area(s) IATF 16949 - Automotive Quality Systems Standard 5
QChas IATF 16949 Clause 8.5.1.2 - C -Standardized Work IATF 16949 - Automotive Quality Systems Standard 1
J Manufacturing Process Auditor Requirements - IATF 16949 IATF 16949 - Automotive Quality Systems Standard 9

Similar threads

Top Bottom