IATF 16949 section 9.3.2.1 requires inputs into management reviews for process effectiveness and process efficiency. Could anyone share some examples of metrics that they are using for each of these?
 
Elsmar Forum Sponsor

AMIT BALLAL

Super Moderator
#3
Re: IATF 16949 Cl. 9.3.2.1 - Management Review Inputs - Process Effectiveness and Eff

Hi!

You can identify your own metrics. Following is the definition of effectiveness and efficiency measures.

Efficiency:
The extent to which time, effort or cost is well used for the intended task or purpose

Eg. Average time taken for closure of ticket
Mean Time To Repair (MTTR)
Time taken to fulfill an order
No. of tickets closed
No. of inquiries closed
Cost of a dish (At hotel)
Time taken to deliver the food order (Waiting time)
No. of audits planned Vs completed
Inventory carrying cost

Effectiveness:
Quality of output / Whether a desired objective is fulfilled

Eg. Customer PPM
No. of customer claims
OEE
No. of breakdowns
Compliance to delivery schedules

Best approach for identifying effectiveness and efficiency measures is by identifying what output is required from Processes / using a turtle chart (Refer output column). I found it very useful.

Eg. For QMS process, outputs are Internal audits conducted as per plan, No repetitive nonconformities in Internal audits, management review meetings are conducted as per the plan, etc.

Here, No. of audits planned Vs completed (%) would be an efficiency measure since it tells whether adequate efforts are taken

No. of repetitive Nonconformities would be an effectiveness measure, since it is the desired result out of QMS process.


I hope it helps! I would like to hear from other covers as well.


Thanks,
Amit Ballal
 

AMIT BALLAL

Super Moderator
#4
Re: IATF 16949 section 9.3.2.1

We use OEE (Overall equipment efficiency) and Performance.
Thanks for reply. But OEE is Overall Equipment Effectiveness, which would be one of the effectiveness measures for Production (Preferably).

Just correcting, so that the question can be answered properly.


Thanks,
Amit
 

jfriess

Involved In Discussions
#5
Re: IATF 16949 Cl. 9.3.2.1 - Management Review Inputs - Process Effectiveness and Eff

No problem!! Thanks you for fixing it :bonk:
 

jfriess

Involved In Discussions
#6
Re: IATF 16949 Cl. 9.3.2.1 - Management Review Inputs - Process Effectiveness and Eff

Just wondering what could be used to satisfy the "measuring and monitoring results? Would an overall CPK (average CPK) work?
 

AMIT BALLAL

Super Moderator
#7
Re: IATF 16949 Cl. 9.3.2.1 - Management Review Inputs - Process Effectiveness and Eff

Just wondering what could be used to satisfy the "measuring and monitoring results? Would an overall CPK (average CPK) work?

It is not one of the inputs required for management review.

But if the question is related to "Monitoring and measurement of manufacturing process" as per caluse 9.1.1.1, then process capability indices (Pp/Ppk or Cp/Cpk) would work.

As per this clause, you should determine capability of new manufacturing processes. If capability study is not possible, you can also calculate PPM or process yield.

Average Cpk is not a good idea, because Cpk is only for that specific process. I've never seen use of average Cpk anywhere.

I hope it helps!


Thanks,
Amit
 

jfriess

Involved In Discussions
#8
Re: IATF 16949 Cl. 9.3.2.1 - Management Review Inputs - Process Effectiveness and Eff

In 9.3.2.c.5, it references monitoring and measurement results. I am probably overthinking it, but I am trying to determine what would fulfill this?
 

AMIT BALLAL

Super Moderator
#9
Re: IATF 16949 Cl. 9.3.2.1 - Management Review Inputs - Process Effectiveness and Eff

In 9.3.2.c.5, it references monitoring and measurement results. I am probably overthinking it, but I am trying to determine what would fulfill this?
Sorry for ignoring the requirement of ISO9001. It becomes difficult to browse through two different standards, hence missed.

Process effectiveness, efficiency measures, KPIs (If you have any - not requirement of the standard), Quality objectives would fulfill this requirement.

You are not overthinking. Questions are good to have.


Thanks,
Amit
 
Last edited:

Sebastian

Trusted Information Resource
#10
Re: IATF 16949 Cl. 9.3.2.1 - Management Review Inputs - Process Effectiveness and Eff

Just wondering what could be used to satisfy the "measuring and monitoring results? Would an overall CPK (average CPK) work?
It is no related to product measuring only. It is related to measuring and monitoring of system process indicators.
 
Thread starter Similar threads Forum Replies Date
A IATF 16949 4.3.1 - Determining the scope of the quality management system - supplemental IATF 16949 - Automotive Quality Systems Standard 9
R IATF 16949 Clause 8.5.1.6 a) maintenance and repair facilities - Production tooling management and personnel IATF 16949 - Automotive Quality Systems Standard 4
S List of requirements for Management Review in IATF 16949 IATF 16949 - Automotive Quality Systems Standard 10
B How to comply with IATF 16949:2016 9.3.2.1k - Management review IATF 16949 - Automotive Quality Systems Standard 2
L IATF 16949 Warranty Management System examples IATF 16949 - Automotive Quality Systems Standard 0
L IATF 16949 Clause 9.2.2.2 Quality Management System Audit IATF 16949 - Automotive Quality Systems Standard 9
J 3 Questions about Management Review - ISO 9001 and IATF 16949 Management Review Meetings and related Processes 4
W IATF 16949 Clause 6.1.1 - My first Major NCR (Management Review) IATF 16949 - Automotive Quality Systems Standard 57
J IATF 16949 container management requirements? IATF 16949 - Automotive Quality Systems Standard 2
S IATF 16949 Supplier Management - Supplier Tooling Requirements Supplier Quality Assurance and other Supplier Issues 1
J IATF 16949 Cl. 8.4.2.3 - Supplier Quality Management System Development IATF 16949 - Automotive Quality Systems Standard 59
B IATF 16949 Clause 9.3.2.1 - Management Review Inputs IATF 16949 - Automotive Quality Systems Standard 1
K Top Executive Management ISO 9001:2015 and IATF 16949 Overview IATF 16949 - Automotive Quality Systems Standard 4
W IATF 16949 Clause 8.4.2.4.1 Second Party Audits (Supplier Management) IATF 16949 - Automotive Quality Systems Standard 45
T IATF 16949 Quality Management System (QMS) Scope Requirements IATF 16949 - Automotive Quality Systems Standard 18
S ISO/TS 16949 IATF Rules: 2.9 Management of Impartiality IATF 16949 - Automotive Quality Systems Standard 8
Ashland78 Need IATF 16949 ISO Gap Analysis Excel File Internal Auditing 3
T Justification of "Design Excluded" in IATF 16949 Design and Development of Products and Processes 5
Sidney Vianna Job Opening in the USA - IATF 16949 Lead Auditor Position Job Openings, Consulting and Employment Opportunities 0
Ron Rompen IATF 16949 8.5.1.4 IATF 16949 - Automotive Quality Systems Standard 7
P IATF 16949:2016 Letter of conformity IATF 16949 - Automotive Quality Systems Standard 5
D IATF 16949 SI 10, External non-accredited lab IATF 16949 - Automotive Quality Systems Standard 4
S IATF 16949 - Summary at a glance Clause wise - changes from ISO TS IATF 16949 - Automotive Quality Systems Standard 4
T IATF 16949 Recording inspection results IATF 16949 - Automotive Quality Systems Standard 2
S IATF 16949 Supplier selection criteria 8.4.1.2 IATF 16949 - Automotive Quality Systems Standard 2
D IATF 16949 M&TE Laboratory scope IATF 16949 - Automotive Quality Systems Standard 7
M IATF 16949 SI # 10: Integrated self-calibration of measurement equipment- Needs for explanation IATF 16949 - Automotive Quality Systems Standard 2
Q ISO 9001/IATF 16949 Audit Finding Question - Document Retention IATF 16949 - Automotive Quality Systems Standard 11
J IATF 16949 Calibration/Verification records question ISO 26262 - Road vehicles – Functional safety 6
D Bulk Materials (Greases) and IATF 16949 IATF 16949 - Automotive Quality Systems Standard 11
J IATF 16949 Internal Audit question - Auditor's responsibility Internal Auditing 6
S IATF 16949 Internal Audit Example IATF 16949 - Automotive Quality Systems Standard 18
B Remote IATF 16949 audit preparation General Auditing Discussions 10
R IATF 16949 Certification for new site with transferred product--what is the impact with CSR and scorecards? IATF 16949 - Automotive Quality Systems Standard 4
B IATF 16949 Cert Expire- New certification body IATF 16949 - Automotive Quality Systems Standard 5
M IATF 16949 - Audit of Remote Location/Support Site and IT IATF 16949 - Automotive Quality Systems Standard 4
O Informational Ford Motor Company Customer Specific Requirements for IATF 16949:2016 - 08 Jan 2021 Customer and Company Specific Requirements 0
B Updated IATF 16949 - Will IATF 16949 get revised when ISO 9001:202X is released? IATF 16949 - Automotive Quality Systems Standard 4
O Release of Sanctioned Interpretations (SIs) related to Rules 5th Edition and Sanctioned Interpretations related to IATF 16949:2016 IATF 16949 - Automotive Quality Systems Standard 0
S Thoughts on managing ISO 9001, 13485, IATF 16949 and 17025 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 33
P IATF 16949 requirement - error-proofing in control plan IATF 16949 - Automotive Quality Systems Standard 3
R IATF 16949 - Outsourcing of internal audits Internal Auditing 11
eule del ayre Documented Information - Periodic Review of Documents? IATF 16949:2016 / ISO 9001:2015 IATF 16949 - Automotive Quality Systems Standard 34
Crimpshrine13 Laboratory Scope - Calibration vs. Test Methods - IATF 16949 IATF 16949 - Automotive Quality Systems Standard 3
earl62 What is the best way to control special characteristics in Control plan? Is it Mandatory to have SPC for IATF 16949? IATF 16949 - Automotive Quality Systems Standard 12
L IATF 16949 certification costs IATF 16949 - Automotive Quality Systems Standard 3
B FCA US Customer Specific IATF 16949- Critical Characteristics 8.6.2 Customer and Company Specific Requirements 2
B IATF 16949 News Six month extension on all valid IATF 16949 certs IATF 16949 - Automotive Quality Systems Standard 10
earl62 IATF 16949 Clause 9.1.1.1 - What is the batch conformance to specification method? IATF 16949 - Automotive Quality Systems Standard 3
B FCA US IATF 16949 Customer Requirements updates Customer and Company Specific Requirements 3

Similar threads

Top Bottom