I'd like to discuss text in 10.2.4 Error-proofing:
"...test frequencies shall be documented in the control plan. (1)
The process shall include the testing of error-proofing devices for failure or simulated failure. (2)
My interpretation of the text:
1st testing is testing of a product or process using e-p device. Frequency esually is 100%, but it could be also 1/50 pieces, or 1/hour etc.
2nd testing is testing of the correct operation (proper working) of the e-p device (Does this device detect nonconforming parts?)
Is this interpretation correct?
"...test frequencies shall be documented in the control plan. (1)
The process shall include the testing of error-proofing devices for failure or simulated failure. (2)
My interpretation of the text:
1st testing is testing of a product or process using e-p device. Frequency esually is 100%, but it could be also 1/50 pieces, or 1/hour etc.
2nd testing is testing of the correct operation (proper working) of the e-p device (Does this device detect nonconforming parts?)
Is this interpretation correct?