Dear All,
I'm trying to better understand such requisite, in order to know if "functional testing" means complete re-qualification of product, including durability test.
Has someone have more detailed info on such requirements? :bonk:

Thank you for your help.

Sandro
 
Elsmar Forum Sponsor

al40

Quite Involved in Discussions
#2
Hi Bpillar,
Not sure if I fully understand your question but functional testing per section 8.6.2 states you shall perform functional testing to agreed upon standards per you and your customer as stated in their engineering material, performance standards, and what you have stated in your control plans.

Functional testing is validating that the product does what it is intended to do during your design and development phase.

I hope this helps,

Al40
 

bpillar

Starting to get Involved
#3
:bigwave:
Thank you Al40 for your reply. :thanx:

So, (sorry for my stupidity....:confused:), if I understood correctly, about "functional testing" I've to take into account all the functional tests required to perform product validation (or qualification), if no any specific agreement with customer exist, isn't it?

Thank you.
Bpillar
 
#4
Would this clause be applicable to a bulk material supplier? Ex. paint. My thoughts is this is for parts for a dimensional verification and layout.
 

AMIT BALLAL

Trusted Information Resource
#6
No. Layout inspection is done of a final product, where all parameters as specified in the drawing are verified. Whereas product audit requires an audit of the product (inspection) at production stages to delivery (can include packaging, labeling stages, etc.) In a product audit, important parameters are generally inspected.
 
#7
No. Layout inspection is done of a final product, where all parameters as specified in the drawing are verified. Whereas product audit requires an audit of the product (inspection) at production stages to delivery (can include packaging, labeling stages, etc.) In a product audit, important parameters are generally inspected.
Thanks a million for your help. I really appreciate it. Have you by any chance got a layout and a product audit report example for me?
 

minrah

Involved In Discussions
#10
Hello All,

Is Layout inspection needed to be carried out for components received from suppliers and assembled in our product.

Thanks in advance for your help.
 
Thread starter Similar threads Forum Replies Date
earl62 IATF 16949 Clause 9.1.1.1 - What is the batch conformance to specification method? IATF 16949 - Automotive Quality Systems Standard 3
P IATF 16949 Clause 8.4.2.3 - Justification for non-certified suppliers IATF 16949 - Automotive Quality Systems Standard 14
M IATF 16949:2016 clause 8.4.2.3 - We don't have ISO 9001:2015 certificate IATF 16949 - Automotive Quality Systems Standard 26
R Material safety data sheet (MSDS) related clause in IATF 16949 manual IATF 16949 - Automotive Quality Systems Standard 17
R IATF 16949 Clause 8.5.1.6 a) maintenance and repair facilities - Production tooling management and personnel IATF 16949 - Automotive Quality Systems Standard 4
QChas IATF 16949 Clause 8.5.1.2 - C -Standardized Work IATF 16949 - Automotive Quality Systems Standard 1
N Looking for input on the attached Process / IATF 16949 Clause Matrix IATF 16949 - Automotive Quality Systems Standard 4
R IATF 16949 Clause 6.1.2.1 - Lessons Learned and Risk Analysis IATF 16949 - Automotive Quality Systems Standard 6
L IATF 16949 Clause 9.2.2.2 Quality Management System Audit IATF 16949 - Automotive Quality Systems Standard 9
H IATF 16949 Clause 9.2.2.2 Audit System / CSR IATF 16949 - Automotive Quality Systems Standard 1
B IATF 16949 clause 7.1.5.1.1 - Statistical studies shall be conducted IATF 16949 - Automotive Quality Systems Standard 3
P Interesting Discussion IATF 16949:2016 Clause 9.2.2.3 and Layered Process Audits IATF 16949 - Automotive Quality Systems Standard 18
M Reference to IATF 16949 clause 8.4.3 in clause 8.3.4.4, Is it right? IATF 16949 - Automotive Quality Systems Standard 1
M IATF 16949 Clause 8.3.5.2 sub-clause (l) - Process maintainability requirements IATF 16949 - Automotive Quality Systems Standard 15
J IATF 16949 Clause 9.3.2.1 - How to understand "measures" IATF 16949 - Automotive Quality Systems Standard 4
J How to address IATF 16949 clause 5.1.1.1 in my Quality Manual IATF 16949 - Automotive Quality Systems Standard 6
B IATF 16949 clause 8.3.4.3 Prototype programme IATF 16949 - Automotive Quality Systems Standard 0
DeeDeeM IATF 16949 - Clause 8.5.2 Identification and Traceability IATF 16949 - Automotive Quality Systems Standard 7
W IATF 16949 Clause 6.1.1 - My first Major NCR (Management Review) IATF 16949 - Automotive Quality Systems Standard 57
A Escalation Process - IATF 16949 Clause 4.4.1.2 IATF 16949 - Automotive Quality Systems Standard 11
E IATF 16949 Clause of 8.4.3 - Approvals - Can you explain to me IATF 16949 - Automotive Quality Systems Standard 1
B IATF 16949 Clause 9.2.2.2 - Which QMS Processes are Included IATF 16949 - Automotive Quality Systems Standard 1
J What are sample documents of IATF 16949 Clause 8.6.4 a? IATF 16949 - Automotive Quality Systems Standard 2
S IATF 16949 Clause 8.3.3.3 - Documentation of all Special Characteristics in Drawings IATF 16949 - Automotive Quality Systems Standard 2
B IATF 16949 Section Clause 8.3.4.1 - Monitoring - Design and Development Input(s) IATF 16949 - Automotive Quality Systems Standard 3
B IATF 16949 Clause 9.3.2.1 - Management Review Inputs IATF 16949 - Automotive Quality Systems Standard 1
T Customer Authorization for Concession - IATF 16949 Clause 8.5.1.1 IATF 16949 - Automotive Quality Systems Standard 3
W IATF 16949 Clause 8.4.2.4.1 Second Party Audits (Supplier Management) IATF 16949 - Automotive Quality Systems Standard 45
T Record Retention Requirements - IATF 16949 Clause 7.5.3.2.1 Records and Data - Quality, Legal and Other Evidence 15
B IATF 16949 Clause 8.5.6.1.1 (Temporary Process Control Change) IATF 16949 - Automotive Quality Systems Standard 24
T Temporary Change of Process Controls - IATF 16949 Clause 8.5.5.1.1 IATF 16949 - Automotive Quality Systems Standard 16
B IATF 16949 Clause 8.4.1.2 - Supplier Selection Process - Service Providers IATF 16949 - Automotive Quality Systems Standard 11
J IATF 16949 Clause 8.7.1.7 Nonconforming Product Disposition - Scrap Rendered Unusable IATF 16949 - Automotive Quality Systems Standard 64
M IATF 16949 Clause 4.4.1.2 - Product Safety - Concept of the Title IATF 16949 - Automotive Quality Systems Standard 4
M IATF 16949 Clause 7.1.5.1.1 - What are "inspection equipment systems"? IATF 16949 - Automotive Quality Systems Standard 4
P Setup Verification in IATF 16949 Clause 8.5.1.3 IATF 16949 - Automotive Quality Systems Standard 6
D Does IATF 16949:2016 Clause 7.3 (now 8.3) Apply to "Grandfathered" Products IATF 16949 - Automotive Quality Systems Standard 4
J IATF 16949 Clause 8.7.1.7 Nonconforming Product Disposition Compliance IATF 16949 - Automotive Quality Systems Standard 38
M Exclusion of IATF 16949 Clause 4.4.1.2 - Product Safety IATF 16949 - Automotive Quality Systems Standard 2
P Problem with IATF 16949 Clause 7.2.3 Requirements (Internal Auditor Competency) IATF 16949 - Automotive Quality Systems Standard 3
M IATF 16949 Clause 4.4.1.2 - Product Safety IATF 16949 - Automotive Quality Systems Standard 13
M Compliance with IATF 16949 Clause 8.3.4.4 Product Approval Process IATF 16949 - Automotive Quality Systems Standard 2
dubrizo IATF 16949 Clause 8.7.1.6 - Customer Notification - Your Inputs Requested IATF 16949 - Automotive Quality Systems Standard 4
P IATF 16949 Clause 8.5.6.1.1 - Temporary Change of Process Controls IATF 16949 - Automotive Quality Systems Standard 21
M IATF 16949 Clause 8.3 - Rework Records Requirements IATF 16949 - Automotive Quality Systems Standard 1
J What results need to be defined in IATF 16949 Clause 8.3.4 IATF 16949 - Automotive Quality Systems Standard 3
P IATF 16949 Clause 10.2.4 - Error Proofing IATF 16949 - Automotive Quality Systems Standard 25
P IATF 16949 Clause 8.5.1.4 - Verification after Shutdown IATF 16949 - Automotive Quality Systems Standard 12
J How to understand IATF 16949 Clause 8.5.6.1.1 - Process Controls IATF 16949 - Automotive Quality Systems Standard 2
J How to understand IATF 16949 Clause 8.5.2.1 - Traceability IATF 16949 - Automotive Quality Systems Standard 5

Similar threads

Top Bottom