Hi

I am on a case for our reverse logistics, to research for improvements. We are a distribution center/warehousing of among others CD/DVD's. As you might figured out it is not a marked for large longterm investments! So please, I need some further input on how to improve the simple tasks on the operational level.

Some of the goods that the stores/supermarkets did not sell, simply we get it back, and in this context reverse logistic is restricted to that. The overall things about what, how much, why and informations etc., we are working on that to reduce the input on a longer term.

______

So here is an example of the processes:

1) When the goods from a store arrive, normally on a pallet with several packages, they are placed for later threatment, marked with the date for arrival. A paper with a list of all the arrived unchecked goods is updated. The pallets can be placed on row a, b or c. So date and a/b/c helps them find it later on.

2) FIFO, so oldest dates from the list is taken first (so far no real planning, working on that).. The pallets with boxes are moved to the end of the ''unpacking tables''.

3) Workers find a box from the pallet, put it on their table, unboxing and find the papers for the goods, and note the track and trace number from the package on it.

4) Checking the goods are the most time consuming thing, and it depends a lot on the type of items. For some CD's without folio, they need to open every single cover to check for scracthes etc. (if we know they are going for resale). Anyway they count them and check on the paper that the correct amount is there. For broken items it is written on the paper, which another fellow are collecting and taking care of (manual not IT).

They sort them after titles and they try to place them in boxes for each titel on the table (you always hope for similar titels, which has something to do with the date of arrival, but it might overlap).
They might do this proces with like 3-5 packages, where they collect the titles in boxes - optimal 25 of the same titles in one box.

5) Lets say that both worker A and worker B have done proces 4) on their own table. So on the floor next to these working tables, a row of pallets is placed = an open location (like 5 pallets), and the items are placed there /sorted.

So Worker A takes from his table his sorted boxes and put them on an open location, and Worker B do the same with her sorted boxes to this shared open location.

So if Worker A are first and place a box with like 5 items with the titel ''Example'', then worker B must find these and put hers e.g. 9 titles of ''Example'' in this box, up to 25, then they start on a new box on the top of the other. (From the pallet you must be able to access all titles). The finding process is not an issue for small open locations, they make up their own system, but in another larger warehouse, we are working on IT-system to suupport this.

6) Then they continue with process 3-5...

7) At some point they choose to ''close'' the open location and moved it to a waiting position, the location number follow. And they start on a new open location with a new number.

8) The now closed location from the waiting position, is moved to the main warehouse, where some other workers set them out, ready to be shiped for new customers. Unfortunately the places are seperated, I cannot change that easily.
______


So how to speed up the process?

For process 4 and forward I see lots of similiar processes, but on the other hand to take one CD or DVD at a time an place it in the main warehouse, would be stupid too. So how large should the lots be? Should it follow the workers in the main warehouse and their rute?

Could the layout be done in a way, so worker A and B share table, so their table is = the open location?


Thanks for reading. Please leave a comment.
 
Elsmar Forum Sponsor
A

Al Dyer

#2
Mikael

I am on a case for our reverse logistics, to research for improvements. We are a distribution center/warehousing of among others CD/DVD's. As you might figured out it is not a marked for large longterm investments! So please, I need some further input on how to improve the simple tasks on the operational level............................

Thank you for your question!!

No matter what I may think and I will surely catch some crap here. Are you dealing in pirated material?

Al...
 

Mikael

Quite Involved in Discussions
#3
Ah sorry, its fully legal, getting it from real suppliers like Sony and Universal. I am not a fan of pirated material at all.

If it was pirated, we could just make a copy as needed, but in our case we must take specific lots to get discounts...
 

Wes Bucey

Quite Involved in Discussions
#4
As I see it, you have two main sorting tasks:

  1. sorting product by ID (title and whether CD/DVD)
  2. sorting product by resellable or scrap
I presume comments about "scratches, etc." were referring to "shelf-worn" packaging of unopened product. Can those be repackaged for resale or are they scrap, too?

You haven't discussed the financial aspect with the retailer. How is credit determined? How are claims handled for product claims of manufacturer defect?

Can more burden be placed on retailer for sorting product prior to return? At the least, I would expect separate product ID be grouped separately. I'm not sure I would accept opened individual product packages unless they came under "manufacturer defect" claim to a separate department within your operation (an inspection or "Manufacturer Review Board" to adjudicate they are, in fact, manufacturer defect.)

Most logistics problem solutions involve making "straight line" movement of goods. This means sorting for ID is different from sorting for defect so one activity of sorting should be complete (ID) before sorting for defect in packaging (inspection) so operator only makes one decision on each item passing through his hands. Definitely, any decision about manufacturer defect should be separate from straightforward sorting for visual defect.

The base problem I see is that quantity of product return was not anticipated and planned for, resulting in a mixed ad hoc process of one person required to make several decisions about an item at a time (ID, package condition, possible product damage.)

Reconfiguring process lines to be "linear" (one decision at a time) may even result in using LESS floor space.
 

Mikael

Quite Involved in Discussions
#5
Thank you Wes for an interesting answer, and sorry that I am not able to give a promt answer, I just needed to reflect upon it. PLZ let me be back with a more detailed answer soon.
 
M

Marchleo

#6
Well, Having the right warehouse management system is critical to running an accurate, efficient distribution operation. Cool resources!


Cheers,
 
Last edited by a moderator:

Wes Bucey

Quite Involved in Discussions
#7
Thank you Wes for an interesting answer, and sorry that I am not able to give a promt answer, I just needed to reflect upon it. PLZ let me be back with a more detailed answer soon.
Still waiting on that answer. Limbo is only fun when it's a game of sliding under a pole, fueled by alcoholic beverages. Limbo in the sense of waiting for something better to happen, is NEVER fun.
 
Thread starter Similar threads Forum Replies Date
A Warehouse Internal Audit - Seeking Tips and Advice Internal Auditing 17
E PEMS Hazards - IEC 60601 Clause 14.6 - Internal data use - Pressure sensor IEC 60601 - Medical Electrical Equipment Safety Standards Series 3
L Internal audit during COVID-19 restrictions ISO 13485:2016 - Medical Device Quality Management Systems 5
A QMS Overhaul - Reorganizing and Renaming Documents - Internal References Document Control Systems, Procedures, Forms and Templates 18
N Sampling Plan for Internal Audits - ISO 2859 or 3951 - Or Neither? Internal Auditing 6
O ISO13485 implementation - Are internal audits expected before stage 1 audit? Design and Development of Products and Processes 3
B Using Unreleased Documents & Process Maps for Internal Audit purposes ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 12
M Internal PPM Manufacturing and Related Processes 1
S ISO 13485 Lead Auditor - Debate between our Quality Team and Regulatory Auditor - Internal Auditor Training ISO 13485:2016 - Medical Device Quality Management Systems 15
S Risk based internal auditing Internal Auditing 6
O Informational Scaling back internal audits due to corona virus while avoiding a NC Internal Auditing 7
N Small Company - Internal audit process - Who does the audit? Internal Auditing 16
J Does anyone have an excel IATF 16949 Internal Audit checklist I could use? IATF 16949 - Automotive Quality Systems Standard 7
G Addressing Non-Conformances from an Internal Audit that are not product related ISO 13485:2016 - Medical Device Quality Management Systems 11
S Software for Supplier Charge back and internal PPM General Information Resources 2
G Internal Audits and Employee engagement Internal Auditing 16
I What direction do you provide your internal auditors on OFIs? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 38
S Internal calibrations - Part of an ISO 17025 accredited testing laboratory (Automotive) ISO 17025 related Discussions 3
F AS9100D Internal auditing requirements Internal Auditing 3
B Internal and external auditor competency to CSR's IATF 16949 - Automotive Quality Systems Standard 20
R Does any here use an internal auditing tool that works on different platforms? Internal Auditing 3
D Impartiality of Internal Auditor ISO 9001/13485 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 18
W Does anyone have an API Q2 checklist for internal auditing? Oil and Gas Industry Standards and Regulations 1
S Internal audit discrepancy - We missed a few audits that were scheduled Internal Auditing 12
Raffy ISO 14001 9.2.2 Internal Audit Programme Content Internal Auditing 3
N Internal Audit Schedule – Who gets to set the schedule? Internal Auditing 16
Ron Rompen Internal Quality Alert Program Document Control Systems, Procedures, Forms and Templates 0
V IATF 16949 9.2.2.1 Internal Audit Program - "Process Changes" IATF 16949 - Automotive Quality Systems Standard 11
F ISO 17025 8.8 Internal Audits in a segmented company ISO 17025 related Discussions 5
U Changes to Internal Processes and Risk Evaluation - Mitigations Risk Management Principles and Generic Guidelines 10
Q Internal Audits - Categories of non conformances Internal Auditing 12
G Non Conformance During ISO 9001 Audit - Not All Internal Audits Completed General Auditing Discussions 19
B Using external FDA and ISO 13485 audit as internal audit Internal Auditing 6
T Internal Audit Schedule when Hiring Out Internal Auditing 7
K A way to monitor our Internal Audits as a KPI AS9100, IAQG 9100, Nadcap and related Aerospace Standards and Requirements 7
M IATF 16949 7.2.3 Internal Auditor Competency - Trainer's competency Internal Auditing 7
D ISO 9001:2015 Internal Audit Training Advice Internal Auditing 10
C Recommendations for UK-based ISO 13485 internal auditor training ISO 13485:2016 - Medical Device Quality Management Systems 1
M Internal audit consultant ISO 13485 (English speaker) Consultants and Consulting 3
blackholequasar Internal Auditing Inspiration - Getting volunteers to perform internal audits. Internal Auditing 22
S Implementing a 45001 Health & Safety standard - Internal audit plan wanted Internal Auditing 1
V PCB internal insulation treated as insulation formed by insulating compound IEC 60601 - Medical Electrical Equipment Safety Standards Series 2
F Internal Audit - Procedure example Internal Auditing 5
C Internal Audit - Process Clause Matrix / Audit Checklist ISO 13485:2016 - Medical Device Quality Management Systems 7
CPhelan Internal audit - Combine similar nonconformities in one or keep separate? Internal Auditing 6
A External Auditor issue with Internal Audits Internal Auditing 7
M Internal Audit Plan in Retail Internal Auditing 10
W Internal Auditing carried out by a 3rd party - Review of previous audits AS9100, IAQG 9100, Nadcap and related Aerospace Standards and Requirements 3
D Necessity of external watchdog next to internal watchdog ISO 14971 - Medical Device Risk Management 1
QAQT Internal Auditor competence for ISO 14001 ISO 14001:2015 Specific Discussions 11
Similar threads


















































Top Bottom