Hey there!
My small engineering company manufactures only one product (some liquid). Do I need to cover the whole 7.3 process for that?
Thanks for your help!!
~~~ Welcome to the COVE sesamina ~~~
Design and development process and size of the company are in no way tied up.
However small, if you are into design and development, you cover the whole of clause 7.3 to the extent they need to be addressed.
Do not confuse this process with the research and development process.
What ever some liquid you manufacture, how is its specifrications derived for manufacture. What all goes into it and in what proportions. Why so.
You may have answers to all these and more. A systamatic analysis of this maps to the design and development process.