Is there a requirement in TS16949 that PO's show a revision level?

T

TROQC

is there a requirement in 16949 that PO's show a revision level? Thanks for your help!
 

Golfman25

Trusted Information Resource
Re: Is there a requirement in 16949 that PO's show a revision level?

No. But you need to have a way of ensuring that you are conforming to the current revision level of what is being ordered.
 

Jen Kirley

Quality and Auditing Expert
Leader
Admin
Re: Is there a requirement in 16949 that PO's show a revision level?

Do you mean the purchase order document revision level, or what is being ordered?
 
T

Taliesyn

Re: Is there a requirement in 16949 that PO's show a revision level?

We had this a couple of years ago. POs tend to be electronically generated but they are a key form within the QMS - so our CB demanded that we put a revision level on the PO document; and he also demanded that (despite the fact that we could prove that there wasn't a revision level on 'Stainless Steel xxxxxxx' - where xxxxxx was the stockholders own part number) he still wrote us up as there was no revision level on the actual goods being purchased!
 