7.3 Design and Development

I actually value most of the changes in the new ISO 9000:2000, i think it makes it a much more user friendly beast.

However Design and or Development still has me confused.

Can you help me out, can we take an unusual example ie the design of a NASCAR Racecar, and specify what each section could be. This is my understanding;

7.3.1 Design and/or development planning
OK so we need a procedure for how design is going to be done.

7.3.2 Design and/or development inputs.
Could the NASCAR regulations be described as design inputs? ie Car shall weigh at least 450Kgs and not be wider than 1.8 Meters etc

7.3.3 Design and/or developement outputs.
Could this simply be the drawings that come of the CAD machines for the chassis and suspension etc?

7.3.4 Design and/or development review
Could this simply be the weekly project meeting?

7.3.5 Design and/or developement verification.
What could this be? Can you offer any realistic suggestions. How can you verify designs,? FEM is the only thing that crosses my mind.

7.3.6 Design and/or development validation
What could this be? In this example does it actually mean doing a product test? ie taking the car to the race circuit. This seems to be more like a product test than a design test.

7.3.7 Control of Design and/or development changes.
This should be relatively clear, some form of Engineering Change System.

Any help greatfully accepted.

------------------
Andy B

[This message has been edited by Andy Bassett (edited 20 September 2000).]
 
Elsmar Forum Sponsor
S

Sherri O

#2
Andy, this may help. My company build racks that hold car parts (just for brief background). Here is how we respond to those items:
7.3.2 Inputs: Input is infomration received in order to begin. This can be written/verbal instructions from an engineer, parts, math data, etc.
7.3.3 Outputs: Ours are in the form of prints, disk, prototype racks, etc.
7.3.4 Review: FMC requires us to document reviews. We have concept(preliminary ideas/sketches), protoype(design only and sometimes includes an actual proto rack) and final design. The reviews are with the designer and the engineer and may include, estimating, production, and QC.
7.3.5 Verification: From our business we can verify a design by building a prototype for approval.
7.3.6 Validation: Our company cannot do validation for our products in house. Besides 95% of our customers who have us do design do the validation testing(which by the way for a rack usually means SHAKE / IMPACT tests)for us and copy us on the results(sometimes).
7.3.7 Changes: You're rights, you need to develop a way to track changes and how you relay these changes to the operations involved. We use a Design Revision Form with a distribution list on the bottom.
I hope this helps, I'm new to this site and don't want to make a fool of myself.
 
I

isodog

#3
hope this helps.

Verification checks whether the design meets the original specifications (design input).

Validation checks whether the new product works (does what it's supposed to).

Both are important, but different ways of looking at a new product.

Dave

------------------
 
A

Andy Basse

#4
Thanks for the help so far, sometines i need real examples to fully understand how the standard can be interpreted in real-life, your example was a very good one.

Sherri O dont worry if you make a fool of yourself, you are in good company.

BTW
7.3.5 Verification: From our business we can verify a design by building a prototype for approval.

How do you verify the prototype if you arent actually testing it? Do you say 'Yes this looks lie what the engineer wanted'. Who and how do you sing it off? Does somebody approve the BoM.

Regards
 
F

Fordisoman

#5
Andy,
Verification can begin before the prototype is built and tested. Verification should begin in the design stage using analyses, alternate calculations, simulation, modelling, whatever tools are available to the engineer.
 
S

Sherri O

#6
To verify our prototype against the design, we do dimensional checks and also part checks. We can load the prototype with parts to make sure they fit properly. The customer's engineer will usually come to ur plant and sign off on the protoype/design if approved and/or make changes to restart the process.
Yes i agree verification can begin before a prototype, but for most of our builds, racks are similar in design/function. We use past builds, TGR/TGW etc.
 
R

Rick Goodson

#7
Andy,

Re Verification and Validation

The input to your example would be the NASCR regs, but also would include and the owner/engineer/driver input. One of those inputs might have to do with the speed the vehicle needs to be capable of. That speed requirement is translated into an engine design in terms of displacement, horse power, torque, etc.

When the engine is designed and built we 'verify' that it is the displacement specified, does supply the specified torque, produces x amount of horsepower. This is design verification. We then take it to the track to determine if it can meet the speed requirement, which is the 'end user' requirement. Does it perform. This is design validation. Now, in theory, we should do the validation under use conditions, which would imply running it in a race. In fact, the validation probably is performed in a more 'sterile' condition with just that vehicle on the track.

Hope that helps.
 
A

Andy Bassett

#8
Thanks everyone, im just mulling over the responses to decide how best to translate them into a present problem. I now have a better understanding of how different companies are interpreting design verification and design validation.

My only problem at the moment is exactly how to insert the design verification into the sample NASCAR environment REALISTICALLY, ie without burdening somebody with the need to sign something that he doesnt really understand why he is doing it.

This type of environment is in someways an ISO nightmare, as development is not done in nice clean packets that can be completed and then signed off, rather development is a permanent activity taking place in the office, at the track and during the night.

Regards

------------------
Andy B
 
A

Alan Cotterell

#9
I think you are looking at ISO9000 to guide you in how you manage the design and development activity. Probably what you should look at is your 'project management' and 'configuration management' of the product.
The NASCAR rules could be seen as 'constraints' in a project management sense and 'inputs' in an ISO9000 sense.
Design verification is in my opinion essentially a paper based activity, validation is performance testing.
Controlling the 'data pack' involves verification and is known as 'configuration management'. It involves use of an 'engineering change control system'.
I think ISO9000 circumscribes a team activity in this application, and I suggest you follow the old axiom 'say what you do, do what you say, be able to prove it' , rather than trying to design using ISO9000 as a guide.
The following Australian Standards might be useful - AS3905.12 Guide to ISO9001 for architectural and engineering design practices. AS3905.16 Project Management. AS3907 Configuration Management.
All available from http://www.standards.com.au
 

Marc

Hunkered Down for the Duration
Staff member
Admin
#10
> ...7.3.1 Design and/or development planning OK so we need a procedure
> for how design is going to be done.

A general flow. will do. Include review points.

> 7.3.2 Design and/or development inputs. Could the NASCAR regulations
> be described as design inputs? ie Car shall weigh at least 450Kgs and
> not be wider than 1.8 Meters etc

Yes.

> 7.3.3 Design and/or developement outputs. Could this simply be the
> drawings that come of the CAD machines for the chassis and suspension
> etc?

Yes.

> 7.3.4 Design and/or development review Could this simply be the weekly
> project meeting?

Yes - you can - make sure you document the meetings and be ready to explain what you reviewed.

> 7.3.5 Design and/or developement verification. What could this be? Can
> you offer any realistic suggestions. How can you verify designs,? FEM
> is the only thing that crosses my mind.

Verification is review of the 'paper proposal(s)'. Your early stage computations.

> 7.3.6 Design and/or development validation What could this be? In this
> example does it actually mean doing a product test? ie taking the car
> to the race circuit. This seems to be more like a product test than a
> design test.

Yes. Run on track. 'Prove' design output.

> 7.3.7 Control of Design and/or development changes. This should be
> relatively clear, some form of Engineering Change System.

Yes - an engineering change system.
 
Thread starter Similar threads Forum Replies Date
S Changes I have to make in the QMS - ISO 9000:2000 to ISO 9000:2008 Software Quality Assurance 4
A Changes on the horizon for ISO 9000:2000 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 2
B Example of an ISO 9000-2000 QMS ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 2
sathis Is Master Sample a Document? - ISO 9000:2000, Clause 3.7.2 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 32
J Approval of Grandfathered Documents - ISO 9000:2000 Clauses 4.2.3 a&b Document Control Systems, Procedures, Forms and Templates 9
S ISO 9000:2000 Electronic Version - Word or Pdf Format? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 20
Z Updates / Amendments to the ISO 9000:2000 Standard ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
W Do I need ISO 9000:2005 to use ISO 9001:2000? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 21
A Difference between ISO 9000:1994 & ISO 9000:2000 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 3
K Differences Between Iso 9001:2000 And Qs-9000 QS-9000 - American Automotive Manufacturers Standard 9
N ISO 9000:2000 in a service company- Documentation - Do we have to explain exclusions? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 10
R PS 9000 - PS 9004 & PS 9100 Pharmaceutical vs. ISO 13485-2003 and ISO 9001-2000 Other ISO and International Standards and European Regulations 2
M QS-9000 to ISO 9001:2000 - Procedures, etc. - What do I do next? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
Q 6 Weeks to convert from QS-9000 TE Supplement to ISO 9001:2000 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 19
O Quality Systems Manual Ideas - Moving from QS-9000 / TE Supplement to ISO 9001:2000 Quality Management System (QMS) Manuals 8
Sidney Vianna ISO 9002:2000 - I did not know it existed - Not to mention QS-9000:2000 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 43
I ISO 9000:2000 and ISO 13485:2003 impact on the MDD 93/42/EEC ISO 13485:2016 - Medical Device Quality Management Systems 1
C ISO 9001:2000 E-Learning for people new to ISO 9000 Training - Internal, External, Online and Distance Learning 2
T Is QS-9000 certification acceptable for suppliers or must they be ISO 9001:2000? Supplier Quality Assurance and other Supplier Issues 4
G ISO 9000:2000 Document Control Procedure P423 Document Control Systems, Procedures, Forms and Templates 7
Sidney Vianna ISO wants Feedback: ISO Survey on USE of ISO 9000:2000 Series of Standards ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 19
S Is ISO 9001:2000 Required with QS-9000? QS-9000 - American Automotive Manufacturers Standard 8
L Use of Octupus and Turtle Diagrams in ISO 9000:2000 Internal Auditing Process Maps, Process Mapping and Turtle Diagrams 13
B ISO 9000:2000 Basics - Training Videos Training - Internal, External, Online and Distance Learning 17
S ISO 9000:2000 to TS 16949:2000 Gap Assessment Tool IATF 16949 - Automotive Quality Systems Standard 2
D ISO 9001:2000 TAG Committee - TC 176 is responsible for ISO 9000:2000 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
S ISO 9000:2000 Internal Auditing Resource Books - Process Auditing Process Audits and Layered Process Audits 5
N Upgrading to ISO 9000:2000 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 3
A How do I start the Transition ISO 9000:2000? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 1
A Transition from ISO 9000:1994 to ISO 9001:2000 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 3
A ISO 9001:2000 and the Process Approach vs. QS-9000 QS-9000 - American Automotive Manufacturers Standard 2
Raffy QS-9000 vs. ISO 9001:2000 - Which Should We Persue? QS-9000 - American Automotive Manufacturers Standard 9
I ISO 9000:2000 Conversion Presentation Request ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 1
V Table that compares ISO 9000:2000 vs. ISO 17025 ISO 17025 related Discussions 3
A QS-9000 Requires ISO 9001:2000 Suppliers Supplier Quality Assurance and other Supplier Issues 3
I QS 9000 based ISO 9000:2000 or ISO 9000:1994 QS-9000 - American Automotive Manufacturers Standard 9
B QS-9000 vs. ISO 9001:2000 vs. TS 16949 IATF 16949 - Automotive Quality Systems Standard 5
A Corrective Actions - ISO 9001:2000 vs. QS-9000 Clause 4.14 IATF 16949 - Automotive Quality Systems Standard 7
D ISO 9000:2000 Transition Plan General Auditing Discussions 2
M ISO 9000:2000 and "Quality Objectives" Philosophy, Gurus, Innovation and Evolution 2
A The more ISO 9000:2000 registered companies the better? Philosophy, Gurus, Innovation and Evolution 16
I Required ISO 9000:2000 Procedures - Are procedures still necessary? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 2
V Iso 9000:2000 / Iso 14000 Integrated Management Systems Quality Assurance and Compliance Software Tools and Solutions 1
A ISO 9000:2000 Clause 8.3 - Control of Non-Conforming Product Nonconformance and Corrective Action 7
J Implementing ISO 9000:2000 using the ISO 9000:1994 Numbering Structure ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 6
R 21CFR820 vs. ISO 9000:2000 - Cross Reference Matrix Attached ISO 13485:2016 - Medical Device Quality Management Systems 5
L Audit Definition in ISO 9000:2000 includes "documented process"? General Auditing Discussions 2
M Powerpoint .ppt presentation on ISO 9000:2000 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 2
R ISO 9001:2000 + QS-9000 Quality Manual Quality Management System (QMS) Manuals 1
U Software ISO 9000:2000 Quality Assurance and Compliance Software Tools and Solutions 1

Similar threads

Top Bottom