Hello,

I was wondering if I could get some clarification...

The scope of our product realization process includes Production (Fabrication/Assembly) + Installation + Service. We manufacture, install and service capital equipment.

As a level II procedure, what would I need to describe to meet the requirement for Control of Production?

I am struggling with how to articulate what controls are in place for the Fabrication/Assembly processes. Since each machine that we build is different, many of the fabrication/assly processes wont be exactly the same the next time we build a machine.

We can general work instructions that describe how to conduct fabrication in a generic sense, but im not sure this serves as a control?

Any thoughts?
 
Elsmar Forum Sponsor
T

Ted Schmitt

#2
Re: 7.5.1 control of production & service clarification

Hello,

I was wondering if I could get some clarification...

The scope of our product realization process includes Production (Fabrication/Assembly) + Installation + Service. We manufacture, install and service capital equipment.

As a level II procedure, what would I need to describe to meet the requirement for Control of Production?

I am struggling with how to articulate what controls are in place for the Fabrication/Assembly processes. Since each machine that we build is different, many of the fabrication/assly processes wont be exactly the same the next time we build a machine.

We can general work instructions that describe how to conduct fabrication in a generic sense, but im not sure this serves as a control?

Any thoughts?
Welcome to the Cove !

One of the outcomes of your design and development process (I´m assuming it´s one of your core processes by your description), should be an assembly type drawing/blue print... as you state that each machine is different, a start could be the drawings... along with checks done by Inspectors (or by the machine operators themselves).
 
S

shotblaster

#3
Re: 7.5.1 control of production & service clarification

thank you for the welcome and the reply,

i like the idea of using eng. drawings with work-instructions as a control - but if each design is, at least in part unique/different, i guess that means we need unique "one-off" inspection sheets that pertain directly to that design as oppossed to generic inspection sheets - im assuming i will need to address this once i start developing the control of design process :)
 

atitheya

Quite Involved in Discussions
#4
Re: 7.5.1 control of production & service clarification

You have to start with design and development process and base your specific instructions as one of the outputs of the process.

One of my clients is in the business of manufacturing transformers. For each order they develop a design. One of the outputs of the design process is a Job Instruction which detailed the technical specifications while working on the components for eg say winding, then, the number of turns, left and right margins etc. This job instruction is in addition to other technical specifications such as those of raw material etc.

The job is then carried out as per a general work instruction for that activity, in above example would be WI for winding (which, as I gather from your description, in your case would be an output of the design activity).

The flow of process of entire manufacturing (through various sections) is described in a procedure.
 

Cari Spears

Super Moderator
Staff member
Super Moderator
#5
Re: 7.5.1 control of production & service clarification

i like the idea of using eng. drawings with work-instructions as a control - but if each design is, at least in part unique/different, i guess that means we need unique "one-off" inspection sheets that pertain directly to that design as oppossed to generic inspection sheets
Not at all. We are a job shop full of skilled tradesmen - we use the engineering drawings along with the router for our work instructions for most products and record our inspection results on an "inspection copy" of the drawing.

For more complex products or where specific inspection reporting formats are required (like for our aerospace and military products) we create a specific report for each part but it's just a matter of ballooning the drawing and typing the specs into our inspection report template.

Building capitol equipment is obviously much different than building ballscrews (like we do) but you get the drift - do what makes sense for your organization and the skill level of your employees.
 
Thread starter Similar threads Forum Replies Date
C Example Work Instruction/Procedure for AQL (Acceptable Quality Level) AQL - Acceptable Quality Level 4
M Documentation of Who Approves a Level 2 Procedure Document Control Systems, Procedures, Forms and Templates 3
R Level of Detail in a Quality Manual vs. a Procedure ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 21
H Calibration Procedure Level of Detail - ISO Procedure question Document Control Systems, Procedures, Forms and Templates 8
Q CMMI Level 2 Procedure for Design & Development Program Software Quality Assurance 1
W Procedure Clause ?Level? Numbering System explanation ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
G When to have top level procedure in order to have a work instruction for a process Document Control Systems, Procedures, Forms and Templates 6
R References to Level III Work Instruction within a Level II Procedure ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 6
A Level 2 Sampling Plan SOP (Standard Operating Procedure) Request Inspection, Prints (Drawings), Testing, Sampling and Related Topics 9
S Top level CAPA (Corrective and Preventive Action) procedure ISO 13485:2016 - Medical Device Quality Management Systems 26
W Example of level 1, level 2, level 3 procedure Document Control Systems, Procedures, Forms and Templates 2
T Electronic Differential Level Gage R&R Procedure Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 2
R Customer Feedback - Customer Service Level Procedure Service Industry Specific Topics 6
S Quality Procedure and Work Instruction templates - Level 2 and Level 3 Document Control Systems, Procedures, Forms and Templates 5
R Customer Focus - Level 1 Procedure - Addressing ISO 9001 Clause 5.2 Document Control Systems, Procedures, Forms and Templates 3
E Procedure Numbering Change? Still the need for maintaining Level 1, 2, 3, documents? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 10
N Level 3 PPAPs APQP and PPAP 2
J Part submission warrant for Level 1 PPAP APQP and PPAP 1
A Defining a lower ESD test level in IEC 60601 safety test IEC 60601 - Medical Electrical Equipment Safety Standards Series 5
was named killer Onsite Level II N.D.T. Training in Florida Training - Internal, External, Online and Distance Learning 0
D High level understanding of EUDAMED EU Medical Device Regulations 3
D Supplier Quality level category help - high level ISO 13485:2016 - Medical Device Quality Management Systems 6
silentmonkey Rationalising the level of effort and depth of software validation based on risk ISO 13485:2016 - Medical Device Quality Management Systems 10
Y What are different Special Inspection Level 1-4 and General spesification 1-3 ? AQL - Acceptable Quality Level 0
D Supplier Quality - How to classify a supplier level Medical Device and FDA Regulations and Standards News 10
E Received a Major finding during IATF Surveillance audit for loss of BIQS Level 3 (more than 6 SPPS in 6 months)...how should we address SYSTEMIC CA? IATF 16949 - Automotive Quality Systems Standard 11
J Level 3 KPI Excel Template Manufacturing and Related Processes 1
M Informational How to perform a clinical evaluation of medical devices – Part 2 – Level of clinical evidence and what sufficient clinical evidence means Medical Device and FDA Regulations and Standards News 9
R Bottom up approach versus system level ISO 14971 - Medical Device Risk Management 2
C Failure nets - Same level effects FMEA and Control Plans 0
H Graphical analysis of results - Confidence level bands nomenclature Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 2
S Level of Clinical Evidence - MDR EU Medical Device Regulations 3
D GM BIQS level 5 requirements Customer and Company Specific Requirements 5
I Sampling processes - Who must define the AQL level? AQL - Acceptable Quality Level 9
R Identifying internal issues.. at what level? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 9
I What level of change in documentation requires re-training? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
M Level 3 PPAP submission of intentional defective parts APQP and PPAP 4
eule del ayre List of Level 3 PPAP requirements for automotive suppliers APQP and PPAP 20
I Document levels and approval requirements for lower level documents like work instructions, forms etc. Document Control Systems, Procedures, Forms and Templates 18
B AS9102 FAI & Lower Level Drawings - How should we perform the FAI? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
Rameshwar25 What is a Control Plan at "Material Level"? IATF 16949 - Automotive Quality Systems Standard 4
N How to resolve discrepancies in Level 3 PPAP supplier dimensional reports? APQP and PPAP 11
M Creating a Plant Level Value Stream Map Process Maps, Process Mapping and Turtle Diagrams 1
K Defining Acceptance Quality Level, I need clarity on AQL 1.5, 2.5, 4.0 AQL - Acceptable Quality Level 5
P GM BIQS level 5 training? Training - Internal, External, Online and Distance Learning 2
Ron Rompen Dual level holes - Measurement method suggestions wanted General Measurement Device and Calibration Topics 9
A Level of details required for Class IIb Product Verification and Validation CE Marking (Conformité Européene) / CB Scheme 1
D System Level FMEA example wanted FMEA and Control Plans 2
samer Do we have to determine Educational level for all Staff as pr 7.2 b clause? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
J What level PPAP for 5 critical parts? APQP and PPAP 8

Similar threads

Top Bottom