Hello everybody,
I have serious problem with our PFMEAs.
Our PFMEAs are process related documents. For example process Incoming inspection or process Final test...
Most of our customers require PFMEA to be made for their product only (for example: start with Incoming inspection and finishing with Shipping)
We cannot generate PFMEA for every single devise - they are hundreds!
Please advice is there any written rule? How to convince customers to accept PFMEAs made in such way?
Second question: Is there any written rule describing how Process flow and Control plan to be linked to the PFMEA? I need comprehensive guide (different from AIAG FMEA book)
I have serious problem with our PFMEAs.
Our PFMEAs are process related documents. For example process Incoming inspection or process Final test...
Most of our customers require PFMEA to be made for their product only (for example: start with Incoming inspection and finishing with Shipping)
We cannot generate PFMEA for every single devise - they are hundreds!
Please advice is there any written rule? How to convince customers to accept PFMEAs made in such way?
Second question: Is there any written rule describing how Process flow and Control plan to be linked to the PFMEA? I need comprehensive guide (different from AIAG FMEA book)