I’m in trouble to define a Machine set-up sheets, user friendly for more than one kind of equipment. I have some Ideas, but, like ever I would like do the best, so I think that ask suggestion here is a good way to have the best.
I don’t know if there are Manuals, like those AIAG for APQP for control plans, that suggest the contents and the form for Machine set-up sheet.
Wherevere I went I have seen differents kinds of Machine set-up sheet.
Someone without the Unit of measurements of the value to set-up, someone whit only the nominal value and other whit minimum and maximum, others whit references to instructions, others writings so synthetic to looks like to the divine comedy.
Could someone could give a suggestions?
Many Thanks in advance.
By
 
Last edited:
Elsmar Forum Sponsor

Jen Kirley

Quality and Auditing Expert
Staff member
Admin
#2
Re: Machine set-up sheets

Hi Cavanna,

What kind of machines are we talking about, and what are they making please? A little more information might help me guess what a template could look like.

Other things matter too, such as the set up person's skill level and the nature of your spec requirements.
 

Ettore

Quite Involved in Discussions
#3
Hello, Coils of steel and hot rolled tube.
We have all the information for set-up and control all the equipment of the lines on Corporate and line network.
Anyway during some audit we saw that in many lines there are the needs to write and attaching on the wall the Machine Set-Up Sheets, but those at the moment are out of controls
By
 
Last edited:

Jen Kirley

Quality and Auditing Expert
Staff member
Admin
#4
Okay Cavanna, I did some looking around and didn't find anything.

So, if it was me I would do a tally sheet of the items that are on existing machine setup sheets. A spreadsheet would work well for this job.

I would then select among those most-used and minimum items (not specifics like settings, but the functions, as in types of settings) what set up steps are usually done.

Next I would sort these steps in their likely sequence.

If you want to include the actual settings, make space for them in the proper steps by inserting lines where they belong.

Let production people review a rough draft. After all, they would be the ones using it and they would know what's required and what is "fluff". Make changes as appropriate based on the production people's input.

If you are using a spreadsheet, the cell holding the description of a step can simply be written over by entering information in that step's cell. More lines can be inserted as the need arises.

When done, the spreadsheet can be formatted to print in one sheet or several, of any type you choose--including a small laminated flip chart of step-by-step instructions.

I hope this helps!
 
K

KWalls - 2008

#5
Cavanna,

I don't know if this helps, but I have an example of what we use on our machines (lathes and mills)... Here's to hoping it gives you an idea to come up with one that works for you!
 

Attachments

Jen Kirley

Quality and Auditing Expert
Staff member
Admin
#8
Hi Cavanna,

Your set up template appears to have all the requirements met, but I have a couple of questions about approvals.

Are the Verified and Approved blocks for the entire set up of the tool, or for the set up plan before it goes to the production phase?

Are you an automotive supplier?
 

Ettore

Quite Involved in Discussions
#9
Thank, you
Are the Verified and Approved blocks for the entire set up of the tool, or for the set up plan before it goes to the production phase?
Before it goes to the production phase we have all set up data approved via LIV.III of EDP system. We have also control plan for every production line via Intranet and attached at the wall of every Phase of production, issued reviewed and approved after FMEA. The production plan referred to machine set up cards.

Are you an automotive supplier?
We have a lot of sub supplier of automotive in Europe. we aren't again ISO/TS 16949

:bigwave:
 

Ettore

Quite Involved in Discussions
#10
Re: Machine Set-Up Sheets UNIVERSAL STANDARDIZATION

Jennifer Kirley said : Your set up template appears to have all the requirements met, but I have a couple of questions about approvals .....

I'm waiting for suggestion from Jennifer or others cove member thinking that some suggestions on this arguments could be useful to other here. for what concern may experience I remember that many little company use write down technical sheet without a guidline so that the output is determined from the inventive of the people that issued the document.

Could we create here in the Cove the ultimate universal "Forms for Machine Set-Up sheets "? :magic:
:bigwave:
 
Last edited:
Thread starter Similar threads Forum Replies Date
C Implementing a set of bore gages at a machine Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 1
M AS9100C Document Control for Machine Set Up Work Instructions AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
S SMED on Punching Machine - Reducing Set-Up Time Lean in Manufacturing and Service Industries 4
T Failure Modes for Machine Set-up/Production Dimensional Checks FMEA and Control Plans 2
E Tensile test machine, tinius olsen 602 Manufacturing and Related Processes 1
M Class II type machine , and its compliance with 60601-1 IEC 60601 - Medical Electrical Equipment Safety Standards Series 14
B SOP for CNC turret punching machine for sheet metal process Manufacturing and Related Processes 0
S Any ISO standards around Artificial Intelligence and Machine Learning? Medical Information Technology, Medical Software and Health Informatics 4
K Machine Capability Capability, Accuracy and Stability - Processes, Machines, etc. 2
H Software Validation for FFS Packaging Machine Qualification and Validation (including 21 CFR Part 11) 1
M Determining if an Insulin Pen Testing Machine is a Medical Device? EU Medical Device Regulations 4
K Regulatory requirement of SaMD with machine learning component IEC 62304 - Medical Device Software Life Cycle Processes 3
P Need a programmer for QVI's VMS software for optical inspection machine Inspection, Prints (Drawings), Testing, Sampling and Related Topics 0
B IQ/OQ/PQ of CNC Milling Machine Qualification and Validation (including 21 CFR Part 11) 2
G Engineering retest in line - Machine stability issues IATF 16949 - Automotive Quality Systems Standard 8
R Machine directory (2006/42/EEC) is applicable or not Other Medical Device Related Standards 0
B Product Safety Responsibility - Job shop such as a machine shop AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
Marc The German Enigma Machine of World War II After Work and Weekend Discussion Topics 0
R Revalidation machine line and Stability Studies impact. Medical Device and FDA Regulations and Standards News 3
K Validation of new machine (second machine of the same type) Pharmaceuticals (21 CFR Part 210, 21 CFR Part 211 and related Regulations) 2
P How far an operator can reach into a machine before it becomes an ergonomic problem CE Marking (Conformité Européene) / CB Scheme 5
GreatNate Qualifying a CNC machine Manufacturing and Related Processes 3
C Machine Verification Plan Manufacturing and Related Processes 2
F AS9100D Process Matrix for a small cnc machine shop AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
B Using non CE parts in a machine CE Marking (Conformité Européene) / CB Scheme 1
Marco Bernardi Plane measurement with a 3D touch machine like a CMM. Calibration and Metrology Software and Hardware 3
Marco Bernardi Diameters measurement with 3D touch machine like a CMM Calibration and Metrology Software and Hardware 4
S Companies that maintain your machine should be in ASL? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
S Machine Setup for a CNC Machine Capability Study Capability, Accuracy and Stability - Processes, Machines, etc. 1
GoSpeedRacer Veterinary anesthesia machine CE Marking (Conformité Européene) / CB Scheme 1
H Should I mention machine/Equipment password In SOP? Qualification and Validation (including 21 CFR Part 11) 4
R How to properly use Survival Analysis to predict time to machine failure Reliability Analysis - Predictions, Testing and Standards 0
K Mammography Machine Bench Testing - FDA 510(K) US Food and Drug Administration (FDA) 5
J Extent of Validation - New machine installed in manufacturing ISO 13485:2016 - Medical Device Quality Management Systems 8
P Average access height into an industrial machine (average base plate height) Human Factors and Ergonomics in Engineering 2
B Machine process sheet requirements for pill bottling operation Pharmaceuticals (21 CFR Part 210, 21 CFR Part 211 and related Regulations) 1
B Does EMC Directive 2014/30/EU cease to apply when the Machine Directive 2006/42/EC is applicable? CE Marking (Conformité Européene) / CB Scheme 4
Q Gage R&R for Instant Measurement Machine Manufacturing and Related Processes 6
J Implementing Machine Replacement Part Reverse engineering technology Manufacturing and Related Processes 3
T QMS Template Help - Small machine shop/job shop Manufacturing and Related Processes 1
D 4M (Man, machine, method, materials) Management Manufacturing and Related Processes 3
J Starting from scratch - a plethora of challenges for a new Lumber Mill Machine Shop Quality Management System (QMS) Manuals 11
P Calculating a weight for a machine for the CE label CE Marking (Conformité Européene) / CB Scheme 0
K Is Compliance Testing of IEC 60601-2-63 mandatory for Europe - Dental X-Ray machine CE Marking (Conformité Européene) / CB Scheme 3
K IEC 60601-1-9 Compliance mendatory or Not - CT Scan machine CE Marking (Conformité Européene) / CB Scheme 8
M (How To) Getting Data From Vision Machine To Reporting Software Misc. Quality Assurance and Business Systems Related Topics 0
G Assigning a calibration tolerance - An x-y coordinate machine - Uncertainty as my verification tolerance General Measurement Device and Calibration Topics 4
T EN 10204 3.1 Inspection Certificate - Machine Shop Various Other Specifications, Standards, and related Requirements 4
N IATF 16949 7.1.5.3.2 External Laboratory - Calibration of Nikon machine in factory IATF 16949 - Automotive Quality Systems Standard 24
M AS9100d (section 7.1.3) example of compliance in machine shop environment. AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3

Similar threads

Top Bottom