Machine Shop Yield and Cost - Productivity, Yield and Absorption Performance

B

bruceliu222

#1
Medium size Scew Machine shop with 25 ACME 6~8 spindle machines and 10 Davenport machines which are struggling about the productivity, yield and absorption performance.
Scrap rate is at 5% while the productivity is <80%. Frankly the machines are relative old which most of them are 20~40 years old and we don't have a big replacement plan.
From the process improvement perspectives, what will be the most important sequences to improve above KPIs? What are the key data we need to collect?
 
Elsmar Forum Sponsor

Michael_M

Trusted Information Resource
#2
Of coarse it depends on what you are after.

If you speed up the machines will your scrap rate increase beyond a reasonable level?

At a 5% scrap rate, are you confident that no 'scrap' part escapes

What is the actual performance at? 79% has a different answer than 60%.

Is the performance time set at what is actually doing or based on what you 'want it to do'?

Can the machines actually produce this requirement?

What (if any) is the on-going cost of maintenance?

Answering these questions may help to get you to an answer you want. I assume the machines are paid for so there really is less burden for the cost of the machine (no monthly payments) and this might help 'justifying' the reduced production cycle time.

If you got 'new' machines, can the burden of the machines be offset by the speed/quality improvement? Don't forget to add in less inspection time (if you can) because the newer machines should produce better parts
 
B

bruceliu222

#3
Thanks for your reply.
I am relatively new to this department so I am starting digging into more details. Here is what I observed in this beginning stage:
The setup time takes more than it was set up in the system. For example, some of the machine setup takes 50% longer than it was budgeted. We are working on the new training program to improve the setup efficiency, however it takes time.
Secondary, the TPY (throughput yield) is relatively low: while with 5% scrap, the TPY is actually about 85%. Operators do not strictly follow the 3-pan audit process well and parts rejection are caught in the final audit stage...
Third, the machine down time. With old machine, the downtime is also another contributor to drag down all the KPI performances.

What are your thoughts about the starting steps to approach the improvement in the machine shop?
 

Michael_M

Trusted Information Resource
#4
There are several issues that concern me here:

Operators do not strictly follow the 3-pan audit process well and parts rejection are caught in the final audit stage...
I am not sure exactly what you mean by this but if the 'scrap' parts are being caught in a final inspection this really concerns me. Inspection should be a double check not an actual check. One of the things I have heard and agree with is "100% inspection will not catch every part".

Mostly I would ask how the inspection process is being performed? Is it mechanical (say a camera system) or human interaction (human with a measurement device). Also, if parts are found in final inspection, would this not trigger some type of action "why did final inspection find bad parts".


the TPY is actually about 85%
The output is running at 85% and 5% scrap. Personally, I would worry about reducing scrap then worry about the 85%. I don't know the process you are running or the qty of parts run, but 5% scrap (to me) seems a bit high and should be the first 'fix' (if possible). I say if possible as some older machines just cannot hold some requirements. Are the machines capable of running the parts to the requirements?

Are the requirements acceptable? For example, long ago I had heard of something call 'SPC creep', where each year an improvement of CPK was required. After 10 years or so, a tolerance of .005, an easy tolerance to hold, became .0003 because they had to improve. Are the tolerances reasonable to your process?


The setup time takes more than it was set up in the system.
I have seen this as a common issue, we experience it here as well. We are addressing it in two ways. 1. We are looking at the setup time and asking 'is this realistic?' and 2. is there something we can do to speed up the setup time.

For question 1, if we give 1 hour for setup and everyone takes 3 hours (or the average is 3 hours) we change the setup time to 3 hours. On question 2, we look at cost vs. benifit, we setup a part once a year and the cost to speed up the setup is $500. We don't perform and suck up the 'extra' time. If however, for $500 we can save 25 hours a year then we will do so.

Just my thoughts, hope they help.
 
Thread starter Similar threads Forum Replies Date
Q Machine Shop Yield & Sampling Plan Inspection, Prints (Drawings), Testing, Sampling and Related Topics 15
B Product Safety Responsibility - Job shop such as a machine shop AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
F AS9100D Process Matrix for a small cnc machine shop AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
T QMS Template Help - Small machine shop/job shop Manufacturing and Related Processes 1
jjmusicjr Starting from scratch - a plethora of challenges for a new Lumber Mill Machine Shop Quality Management System (QMS) Manuals 11
T EN 10204 3.1 Inspection Certificate - Machine Shop Various Other Specifications, Standards, and related Requirements 4
M AS9100d (section 7.1.3) example of compliance in machine shop environment. AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
B ISO 9001:2015 for a Small Machine Shop need Resources ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
H AS9100D Cert question - Small machine shop - Where can I buy a certificate? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
S Need Continuous improvement Suggestions - Small (30 of us) all-CNC machine shop ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 28
M Industry Standards - Sheet Metal a Machine Shop Manufacturing and Related Processes 1
J Suggestions on Inadequate Resources in a Small Machine Shop Nonconformance and Corrective Action 2
M API Monogram License for a Small Machine Shop Oil and Gas Industry Standards and Regulations 1
J QMS and ISO 9001 for a Single Person Machine Shop ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 24
S Job travelers through a machine shop AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
A Start Up of a small AS9100 Machine Shop AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
S How will ISO 9001 help the machinists in a very small Machine Shop ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 23
M Start New Machine Shop OR BUY Business Continuity & Resiliency Planning (BCRP) 9
B Determing Machine Capability in a High Mix, Low Volume Sheet Metal Shop Manufacturing and Related Processes 4
M Machine Shop Process Instructions (Traveler) question AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
J Use of PPMs in Low Volume Machine Shop AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
S Product FMEA vs. Process FMEA - Aerospace Industry Machine Shop FMEA and Control Plans 5
P Machine Shop Tool Crib Procedure - Tooling for CNC mills Quality Tools, Improvement and Analysis 1
N Setting up MSA system in a machine shop environment. Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 5
N Setting up a new Calibration Room in a Machine Shop Calibration and Metrology Software and Hardware 3
A Nonconformances and Rework in a Machine Shop Nonconformance and Corrective Action 6
H AS9100C 6.2.2 Compliance - Machine Shop AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
C Microscope Power to use for Visual Inspections in an Aerospace Machine Shop AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
K Defect Reporting and Tracking Software for a Small Machine Shop Quality Assurance and Compliance Software Tools and Solutions 1
Project Man The "Ifs" in ISO 13485 Clause 6.4 Work Environment - Machine Shop which makes parts ISO 13485:2016 - Medical Device Quality Management Systems 1
E Configuration Managment in an Engineering Sub-Contract Machine Shop (3 people) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
N Where to begin defining and monitoring Quality Metrics in a Machine Shop Manufacturing and Related Processes 9
bobdoering Measurement Expert Advice - Modern Machine Shop Magazine Column General Measurement Device and Calibration Topics 0
E Production Planning in an Industrial Machine JOB SHOP Lean in Manufacturing and Service Industries 1
B SPC Software Selection for use in a CNC Machine Shop - InfinityQS and Lighthouse Quality Assurance and Compliance Software Tools and Solutions 3
W Special Training Tools for the Deaf in a Machine Shop Training - Internal, External, Online and Distance Learning 16
Douglas E. Purdy Sample Production FMEA for Machine Shop wanted FMEA and Control Plans 3
C What to expect in a GE Aerospace Audit of a 100 Person Machine Shop Customer and Company Specific Requirements 5
M Training and Competence requirements in a Small Machine Shop AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
S What is the Secret of Excellent Quality in a Machine shop? Misc. Quality Assurance and Business Systems Related Topics 29
S Implementing Dock To Stock in a Small Machine Shop Misc. Quality Assurance and Business Systems Related Topics 6
O NET-INSPECT is it worth it? Small Machine Shop doing AS9100 Quality Manager and Management Related Issues 2
D AS9100 Design - Machine shop offering Drafting Services? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
R 7.2.1 Customer Requirements Checklist for a Small Contract Manufacturing Machine Shop AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
H Contract Machine and Fabrication Shop - AS9100 Exemptions AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
K Paperless Electronic Records in a Machine Shop Records and Data - Quality, Legal and Other Evidence 8
L In-Process and Final Inspection for a job shop (Machine) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 11
C Is SPC a requirement of AS9100? Small Machine Shop and Assembly AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
B Requirements for AS9100 Contract Machine Shop in FAA Certification Process Federal Aviation Administration (FAA) Standards and Requirements 2