Thanks for the reply!
Anything that is related to a line shutdown would drive CAPA which would require RCA. Risk / impact assessment drives inclusion in the CAPA system. Highest risk classification requires
8D.
Most of the items are a little more serious than tables for the company picnic, but they quite often look like "Sam talk to Ted to assure planning for changeover", "Bill to report on project status in two weeks" or "Assure everyone has completed health and safety training". I'm struggling with adding any extra overhead to these sorts of things. I really like the fact they are tracked in the action list and that seems more than sufficient.
Every single day, take a step back and look at things from a big picture point of view.
- "Sam talk to Ted to assure planning for changeover"
This does not belong in the CAPA system...no way.
The plan for the changeover, if it is not followed, might belong there but even that is a stretch. It belongs in Mgmt or in Design Control.
Not meeting the customer need because of failure in changeover...THAT belongs in CAPA.
- "Bill to report on project status in two weeks"
Under no circumstances does this belong in CAPA.
The project not meeting its goals might, but I would WAY rather handle that through design control than CAPA.
- "Assure everyone has completed health and safety training"
Only belongs in CAPA if not met...I assume there is a time target attached to this. Typical entry of this into CAPA is failure to meet time target.
If you don't want to increase overhead, don't use your CAPA system as Maslow's Hammer.
Just saw Golfman's post...I totally agree.