Hi everybody
Do you have any idea about how to report monthly
progress in Corrective actions.
Something that could be useful and practical.
Let?s say something like this:
- Maybe to assign some % when analysys have been done
- Additionaly other % for task to be performed due to the analysis
- Other % until everything is finished
- The final % for verification
Do someone have any idea?
Thanks for sharing your toughts.