we had a NADCAP audit recently.

There was an NCR related to Violation of specification. The parameters we maintained for our Periodic test were not matching with the Specification requirements.( for salt spray testing, inclined angle is 30 as per B117 & 6 as per MIL-8625 spec, we done at 30)

According to us this is a wrong interpretation & related to adequacy of document review system.

But the auditor commented it as a failure of contract review process..


Any comments
 
Elsmar Forum Sponsor

lanley liao

Involved In Discussions
#2
Hi, Jins, This NCR mentioned you were not clear and i suggest that you should post the objective evidence and nonconformance description in order to help you better. but i can sure that this is an NCR related to the design and development, contract review, inspection and testing as well as production,etc.
 
#3
Hi, Jins, This NCR mentioned you were not clear and i suggest that you should post the objective evidence and nonconformance description in order to help you better. but i can sure that this is an NCR related to the design and development, contract review, inspection and testing as well as production,etc.
Requirement :
AC7108/4 Rev. C Δ1 B9.3 : Is testing performed in accordance with applicable specification?
Applicable specification # MIL-A-8625F, Para 4.5.5 requires that the test specimens shall be tested for abrasion resistance in accordance with Method 6192.1 of FED-STD-141 (ASTM D4060) using CS-17 wheels with 1000 gram load.

Finding :
The test specimens were not tested using CS-17 wheels. Upon further review of abrasion resistance periodic report for May 2021, It was noticed that the test was performed using CS-10 wheels in place of CS-17 wheels.
 

lanley liao

Involved In Discussions
#4
Hi, Jin. This finding was addressed as follows:
1.Correction:
a) The test specimens were tested anew for abrasion resistance by us in accordance with Method 6192.1 of FED-STD-141 (ASTM D4060) using CS-17 wheels with 1000 gram load and the results were qualified.
b) The related functional departments organized to review this NCR, no similar questions were found, and no manufactured or delivered nonconforming product as a result of the nonconformance.
c) communicated with the client for this NCR and the client feedback that the product quality was very good in its application.
2.Root cause Analysis:
a) you can analyze it through the execution aspects and check aspects and defined the root cause according to your actual conditions.
b) explain"why" the nonconformance occurred and was not simply a re-wording of the nonconformance statement;
c) you should provide an explanation of the gaps in your QMS that led to the nonconformance, and then revised your QMS documents accordingly
3.Corrective Actions:
a) revised xxx document,Section xxx,Specified:“.........”;
b) training records.
c)......, etc.
FYI, I hope that it helps you. Good Luck.
 
#5
Dear Liao,

This is the first time we had done our NDACAP & implemented this systems. till audit we were not knowing this also.

So how to do the root cause analysis
 

gpainter

Quite Involved in Discussions
#7
What was the conversation with the auditor? Looks like maybe that you needed to figure out what test the Customer wanted and maybe you only had the capability to do just the one? Not sure?
 
Thread starter Similar threads Forum Replies Date
S The difference between NCR vs. FRACAS (Failure reporting, analysis, and corrective action system) Nonconformance and Corrective Action 4
Thee Bouyyy Internal NCR - API Q1 5.4.2b - API 16C Clause 4.1.3 Internal Auditing 9
C NCR (Nonconformance System) Software Nonconformance and Corrective Action 7
K My question is, what/when is a nonconformity? Therefore what requires an NCR? Nonconformance and Corrective Action 9
L How to write a proper defect description in a NCR Nonconformance and Corrective Action 4
qualprod When to write up a nonconformance and require a NCR - We produce labels ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 14
B How to reply NCR on ineffectiveness of corrective action during IATF external audit? This is repeated issue whereby some mistake was done. IATF 16949 - Automotive Quality Systems Standard 7
M Issuing NCR for improper method statement submissions Internal Auditing 10
A Scrap is NCR or not - What regulation ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 33
Q Interaction of Processes IOP NCR Process Maps, Process Mapping and Turtle Diagrams 7
W Surveillance report along side an NCR program Nonconformance and Corrective Action 2
A NCR, NCMR, CAPA, Deviations - Medical Device Distributor Nonconformance and Corrective Action 2
D Can an AS9100 auditor issue an NCR a month after the audit? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
K AS9100 - No NCR's or CA's during Stage 2 Audit AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
W IATF 16949 Clause 6.1.1 - My first Major NCR (Management Review) IATF 16949 - Automotive Quality Systems Standard 57
K NCR or CA? We're taking any issue we have and saying its a nonconformance Nonconformance and Corrective Action 11
S Re-validation NCR - In which cases re-validation of processes is required Oil and Gas Industry Standards and Regulations 6
Pancho United Airlines NCR Nonconformance and Corrective Action 43
Q Practical Way to raise NCR's in an Assembly Workshop ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 8
W NCR Performance KPI Monitoring in an Industry like Construction Nonconformance and Corrective Action 1
A ISO/TS 16949 - Sharing Certification Audit Report (NCR's) with the Customer IATF 16949 - Automotive Quality Systems Standard 8
N Any comment, if a supplier raise an NCR to the Client? Oil and Gas Industry Standards and Regulations 5
W Auditor Remorse for not issuing an NCR AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
Q Criteria for not rising NCR's in 8.3 of ISO 9001:2008 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 10
I NCR for Customer not updating their drawings AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 14
R How do you perform verification of a NCR (Nonconformance)? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 10
N New to ISO 9001 - NCR for every defect? Nonconformance and Corrective Action 5
B Combining a CAR, an NCR, and an Accident Report ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 9
K Validity of Using NCR's to evaluate Performance Nonconformance and Corrective Action 7
P Differences between an NCR and CAR Internal Auditing 9
N NCR and CAPA in the FMCG (Fast Moving Consumer Goods) Industry Nonconformance and Corrective Action 1
T Do Customer Returns = NCR and CAR? Nonconformance and Corrective Action 5
K Nadcap (AC7107/7 C, paragraph 6.1.b) NCR - Machining Tensile Specimens AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
L How to track the NCR (Quality Notification, Services Notification) Nonconformance and Corrective Action 2
F AS9100 Management Review NCR help - Output of the MR is not Adequate AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
Q ECR (Engineering Change Request) or NCR (Nonconformance Report) in Fabrication? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 12
Q NCR before the Product is delivered to the Customer? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 13
D Is an NCR required in this Customer Complaint scenario? Nonconformance and Corrective Action 6
W Process Effectiveness NCR's (Nonconformance Reports) ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
R Internal Auditing Checklist - Major NCR because the Checklist was not Completed Internal Auditing 17
S Is an 8D Report and a NCR (Nonconformance Report) the same? Nonconformance and Corrective Action 10
N NCR (Nonconformance Report) Combined with Corrective Action Report? Nonconformance and Corrective Action 1
B Format for Discrepant Material Report (DMR) - Nonconformance Report (NCR) Document Control Systems, Procedures, Forms and Templates 1
C AS9100 8.3 Procedure for Non-Conforming Parts - When should an NCR be filled out? Nonconformance and Corrective Action 5
J What is the time limit for an auditor to respond to NCR's and submit audit report? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
K Customer NCR - How to respond to a non-applicable NCR? Nonconformance and Corrective Action 7
C NCR (Nonconformance Report) Root Cause - Cause Code AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
Q How raise en ECO starting from a NC - ECO after NCR? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 8
Q Why ECOing if can use NCR's ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
Q Please recommend NCR / CAPA Software capable of embedding pictures Nonconformance and Corrective Action 12

Similar threads

Top Bottom