Hi every one,

I just received an email from one of my customers. He changed the numbers (codes) of 22 parts. For example, the number was PRT233 and now it is PRT233-00. He says I will have to submit again all 22 PPAP´s.

Is there any other way? I think it´s all waste of time and paper.

Thanks

Celso
 

Wes Bucey

Prophet of Profit
celso klitzke said:
Hi every one,

I just received an email from one of my customers. He changed the numbers (codes) of 22 parts. For example, the number was PRT233 and now it is PRT233-00. He says I will have to submit again all 22 PPAP´s.

Is there any other way? I think it´s all waste of time and paper.

Thanks

Celso
IMO, if the only change is the customer's part numbering system, with no design change, you are justified in resubmitting exisiting PPAP documents with a "rider" explaining that since there was no change in the form, fit, function of the product, you did not have to change the production method.

Personally, I'd try to negotiate just the submission of the rider for the customer to add to his files rather than destroying a forest to reprint the PPAP documents.
 

The Taz!

Quite Involved in Discussions
Good advice Wes. . .

In addition to Wes' comments, a Level 1 PPAP with only the Warrant being sent in this case might suffice. It would be a "Change" and state in the comments section that only the P/N was changed. No change to F,For F. Of course, you'll either need a cross-reference index for your process documentation, or you'll have to update all process control docs; Control Plan, FMEA's, Work Instructions, etc.

Either way, you have some work to do. Get your customer in bed with what ever you do, and see what THEY require. Get it in writing if you can (Objective Evidence).
 
S

SteelWoman

Turn to pages 11 and 12 in the PPAP manual. It lists the conditions under which you do have to notify the customer and/or re-ppap. Basically, if the change does not impact the form, fit, function, performance etc then you're fine. 'Course this table refers to situations where YOU need to notify the CUSTOMER, but I've used it on occasion (successfully, I might add) to point out why a new PPAP is not necessary. This would be, in my book anyway, a HUGE case of not necessary. I've often found that customer's ask for new ppaps in this kind of situation because THEY think THEY are required to - once you point out that it is actually really NOT required, they sometimes just breathe a thankful sigh of relief and go about their business. Worth a shot, anyway.

At BEST, if pushed into a corner on this, I would supply a new warrant, but certainly nothing beyond that.
 
S

Sam

Some, but not all, PPAP documentation may change under certain circumstances. Do you have control of the design records? There may be changesrequired to BOM or drawing. Is shipping part of your control plan? If so it may need to be revised to include the new number.
Is your customer quality rep. asking for the PPAP? If not I would contact him for clarification.
 

bpritts

Involved - Posts
Some of our suppliers are charging $1000 to do a PPAP. This is common
in the fastener industry. Why not tell the customer you'd be glad to do
the ppap on a billable basis and have your sales rep give him a quote?

This may motivate them to consider the value.
Obviously you need to be judicious and not p*$(% them off - rather
point out that this takes time and $.

Brad
 

Wes Bucey

Prophet of Profit
bpritts said:
Some of our suppliers are charging $1000 to do a PPAP. This is common
in the fastener industry. Why not tell the customer you'd be glad to do
the ppap on a billable basis and have your sales rep give him a quote?

This may motivate them to consider the value.
Obviously you need to be judicious and not p*$(% them off - rather
point out that this takes time and $.

Brad
$1,000. Wow! that's very reasonable. The products must be very simple ones.
Some of my production machines alone booked out at $200 to $300 an hour. Add to that the cost of other personnel involved in a PPAP and the $$$ runs up very quickly. We once took over 6 weeks to fine tune feeds, speeds, tooling, order of cut, in-process inspection, etc. on one family of parts. It was imperative for everyone from customer down through the supplier of a special alloy used in the part that the cycle time be reduced while holding a cpk of 2.0. The machine was out of regular production the entire time.
 

Howard Atkins

Forum Administrator
Leader
Admin
IF the customer part number is on the various documents that you submitted then you will have to change the documents so that the corect part number appears.
Did he change the drawing as well? sometimes the part number appears on the drawing., then you have a changed drawing. Does the part number appear on the part? this is then a change to the part.

I agree that a level 1 PPAP should be enough with the reason of change part number no other change.
If the customer part number is on the documents then you must change this as if you are audited on this part there will not be an agreement with the documents and the part.

You could annotate with date and reference to the change document the CP, FMEA etc. This would save the forest.

I hope this will help.
 
S

Sam

PPAP's are not billable items. They are a requirement as part of the QMS and CSR's that were agreed to when the order was accepted.
Buyers for OEM products normally only know how to say the word PPAP. They don't know what letters mean or what it consists of; and they won't take the time to find out.
Any questions you have concerning PPAP's should be discussed only with the customer quality rep.
 

Wes Bucey

Prophet of Profit
Sam said:
PPAP's are not billable items. They are a requirement as part of the QMS and CSR's that were agreed to when the order was accepted.
Buyers for OEM products normally only know how to say the word PPAP. They don't know what letters mean or what it consists of; and they won't take the time to find out.
Any questions you have concerning PPAP's should be discussed only with the customer quality rep.
It is so sad this ignorance about the process behind the acronym (whether PPAP or FMEA or even FAI) is so rampant throughout corporate puchasing departments throughout the world. Even the purchasing guys with APICS certification would be hard pressed to tell you what the acronym stands for.

Of course, a similar disconnect occurs in the Human Resources department when they ask for BB and MBB and really only want and need a bench technician to do redundant metrology. (Plus, they only want to pay the bench technician wage.)

Any "Champions" out there?

In regard to the Contract Review and payment for PPAP, it only goes to show you how important it is to cover ALL bases when negotiating a contract. PPAP can be expensive. It should be billed separately. (perhaps with a price cap versus "time and materials) No one says you can't negotiate or renegotiate the request for proposal from the customer. (defense contractors do it all the time)

If your company allows itself to be part of a herd, instead of the "partner" so many OEMs give lip service to, then the company has no complaint when it is treated as cattle by the OEM. Ask yourself if your sales department are "order takers" or "sellers."
 
Thread starter Similar threads Forum Replies Date
V PPAP documentation - Submission required in English APQP and PPAP 3
S PPAP Submission Required for Electronics Components i.e., Resistors, Capacitors, etc. APQP and PPAP 3
A PPAP Submission NOT required by customer... but... Do I have to do it anyway? APQP and PPAP 8
W PPAP (Production Part Approval Process) - Clarify When submission is required APQP and PPAP 10
K Level 1 PPAP Submission APQP and PPAP 12
J Part submission warrant for Level 1 PPAP APQP and PPAP 1
M Level 3 PPAP submission of intentional defective parts APQP and PPAP 4
S Looking for a PPAP PSW, Part Submission Warrant, in Chinese APQP and PPAP 5
B PPAP: Submission, requirement to have all data in one file? APQP and PPAP 4
W Using a sub-supplier's PFMEA in PPAP Submission APQP and PPAP 4
B PPAP Level 3 Process Submission Capability, Accuracy and Stability - Processes, Machines, etc. 5
C Sample size for GM PPAP Submission APQP and PPAP 3
Q Faking Data - Refusing to sign Falsified PPAP Submission package Nonconformance and Corrective Action 27
S PPAP Supplier Submission Questions - Automotive Paint IATF 16949 - Automotive Quality Systems Standard 2
T Who signs PSW's? (PPAP Part Submission Warrants) APQP and PPAP 1
B TS16949 Annual PPAP Submission Requirements for Ford and Chrysler Parts IATF 16949 - Automotive Quality Systems Standard 2
R PPAP Submission vs. Completion all of the PPAP Elements APQP and PPAP 11
C PPAP Submission - Point in Time Record or Live Document APQP and PPAP 4
M PPAP Submission Template Document Control Systems, Procedures, Forms and Templates 2
S PPAP Requirements for Submission to our Customers for a New Supplier APQP and PPAP 1
B Injection Molding Capability Studies for PPAP Submission Capability, Accuracy and Stability - Processes, Machines, etc. 19
automoto PPAP Forms - Part Submission (Warrant) form .xls Document Control Systems, Procedures, Forms and Templates 2
P Supplier Responsibilities to Initiate a PPAP Submission APQP and PPAP 15
S Problem with Falsified Data in PPAP Submission APQP and PPAP 29
P Reverting back to old and previously approved material - PPAP Re-submission? APQP and PPAP 24
S Customer PPAP notification and submission for a Change APQP and PPAP 2
P PPAP Approval - Customer approval of PSW (part submission warrant) APQP and PPAP 5
H How to refuse PPAP submission to a customer? APQP and PPAP 7
P PPAP submission for a new customer of an existing product APQP and PPAP 7
I Confused on PPAP re-submission - Help on PSW (Part Submission Warrant) APQP and PPAP 3
S New Edition of Ford Phased PPAP Submission Check List APQP and PPAP 9
S Supplier requesting Customer PPAP submission APQP and PPAP 5
R Engineering changes for customer notification - PPAP Submission APQP and PPAP 5
W PPAP Submission Items - Metal Stamping - Tooling Transfer, Replacement, Refurbishment APQP and PPAP 6
B PPAP Document Submission and Retention requirements APQP and PPAP 21
M How to do a PPAP Plan Submission - What do I submit? APQP and PPAP 4
B Quality Stand Down form - Part of a PPAP submission to Johnson Controls Document Control Systems, Procedures, Forms and Templates 12
kedarg6500 PPAP Purpose And Benefits - What is the purpose of PPAP Submission? APQP and PPAP 28
B New PSW (Part Submission Warrant) - 4th Edition PPAP Manual APQP and PPAP 38
J Outside vendor (supplier) Certified to do GMW3359 - Certification for PPAP submission Supplier Quality Assurance and other Supplier Issues 9
M how to decide the submission level for PPAP APQP and PPAP 2
A ProE for PPAP - Has anyone used ProE modelling tool during PPAP submission? Quality Assurance and Compliance Software Tools and Solutions 1
Y PPAP requirements: Submission date and PSW (Statistical Process Package) APQP and PPAP 6
D Seeking CURRENT PPAP Part Submission Warrant APQP and PPAP 7
A Help needed for PPAP submission requirements including contents APQP and PPAP 3
J GM PPAP Specific Requirements - How many pieces for layout, submission - Gage R&R? Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 4
J PPAP Submission Package - Tier II supplier to a Tier I APQP and PPAP 14
J PPAP (Production Part Approval Process) Submission Level Differences - Forms attached APQP and PPAP 17
S PPAP and ISO/TS 16949 - PPAP Submission - What are the SHALLs? APQP and PPAP 17
Q Level of PPAP submission for Subcontractor APQP and PPAP 3

Similar threads

Top Bottom