Internal Audit Finding in a sales department:

Following discrepancies were identified with the procedural requirments;
  • 1. Quotations sent to the client without the approval of authorised person
    1. 2. Quotations sent to the client donot carry the terms and conditions of sale as per procedure
      1. 3.Orders placed to the supplier without top management approval.

If it is an NCR? then let me know the ISO 9001 clause related to this non conformity.

Suresh
 
Elsmar Forum Sponsor

Stijloor

Staff member
Super Moderator
#2
Re: Not following the procedures is an NCR?

Internal Audit Finding in a sales department:

Following discrepancies were identified with the procedural requirements;
  • 1. Quotations sent to the client without the approval of authorised person
    1. 2. Quotations sent to the client donot carry the terms and conditions of sale as per procedure
      1. 3.Orders placed to the supplier without top management approval.

If it is an NCR? then let me know the ISO 9001 clause related to this non conformity.

Suresh
If the audit evidence provided is a violation of an organizational procedure, then it is a nonconformity.
Remember nonconformity is defined as: "non-fulfilment of a requirement."

Examples of requirements:
I
  • ISO 9001:2008
  • Company quality management system documentation (i.e.: Quality manual, procedures, work-instructions, control plans, etc.)
  • Customer requirements
  • Statutory requirements
  • Regulatory requirements
  • Other

Stijloor.
 

Jen Kirley

Quality and Auditing Expert
Staff member
Admin
#3
Re: Not following the procedures is an NCR?

Good day,

7.5.1 says "The organization shall plan and carry out production and service provision under controlled conditions." In plain terms, make a plan and do what has been planned.
 

eternal_atlas

Involved In Discussions
#4
Re: Not following the procedures is an NCR?

Thanks.

But, can i relate this specific violation to 7.2.2 i.e. review of the requirements related to the product?

Need reply please..
 
#6
Re: Not following the procedures is an NCR?

No, you refer to the company requirement that's been violated. There is no need to refer to an ISO 9001:2008 requirement.
:agree:

A nonconformity exists when the audit evidence does not match the audit criteria. When teaching internal auditing, I often say that you need to write nonconfomities to the lowest possible documentation level. A nonconformity will be much easier to understand and take action if it is written that way. In this case, it seems the criteria was your procedure. So, the nonconformity should be written against the procedure. Just leave the standard out of it.
 

Jen Kirley

Quality and Auditing Expert
Staff member
Admin
#7
Re: Not following the procedures is an NCR?

Thanks.

But, can i relate this specific violation to 7.2.2 i.e. review of the requirements related to the product?

Need reply please..
I do agree with my fellow Covers that it is best to refer to the local requirements.

But to specifically respond to the above question, 7.2.2 is a planning element and not an execution element. That is, the customer's requirements will be reviewed in order to make sure the products/services you provide meet the customer requirements. In very plain terms, that means no guessing what the customer wants.

But I presume you have already done that, since you have listed internal requirements for management reviewing quotations and orders before their submission. I am thinking by this point management knows what the customer wants.
 
#9
Internal Audit Finding in a sales department:

Following discrepancies were identified with the procedural requirments;
  • 1. Quotations sent to the client without the approval of authorised person
    1. 2. Quotations sent to the client donot carry the terms and conditions of sale as per procedure
      1. 3.Orders placed to the supplier without top management approval.

If it is an NCR? then let me know the ISO 9001 clause related to this non conformity.

Suresh
Are these requirement of your own process/procedures? If so, an internal auditor should report the situation against those references - it's no sufficient to say 'per procedures'. Also, we don't see any evidence of the effect of this or any quantitative details. If I were a manager I'd be asking 'so what'...?
 
Thread starter Similar threads Forum Replies Date
Q Supplier Disqualification - High Rejects and not following established Procedures ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 9
Q Personnel Not Following Procedures - How do you write up an audit finding? Internal Auditing 43
S Documents / Following Procedures - FDA 21 CFR Part 820 Quality System Regulation 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 12
A Reliable sources for following EU medical device regulatory EU Medical Device Regulations 0
T Root Cause Failure Analysis - Not following Customer packaging Specification Problem Solving, Root Cause Fault and Failure Analysis 9
M Informational The USFDA Continues to Remind Facilities of the Importance of Following Duodenoscope Reprocessing Instructions: FDA Safety Communication Medical Device and FDA Regulations and Standards News 0
M Medical Device News Brexit - Withdrawal Agreement and Political Declaration laid before Parliament following political agreement. EU Medical Device Regulations 4
D Design FMEA for a component - Should I make the following assumptions? FMEA and Control Plans 7
S Record Retention - How long must a company keep the following records? Records and Data - Quality, Legal and Other Evidence 17
S Supplier Classifications - Please give me a good definition of the following terms ISO 13485:2016 - Medical Device Quality Management Systems 5
K Nonconformance on training - Not following own processes (IATF 16949) Internal Auditing 14
P Is the next revision of ISO 15378 following the High Level Structure? Other ISO and International Standards and European Regulations 5
M Please explain the following Automotive Acronyms IATF 16949 - Automotive Quality Systems Standard 3
C Following Order of Work Instructions ISO 13485:2016 - Medical Device Quality Management Systems 23
M CAPA due to Consumer not following Maintenance Instructions... Nonconformance and Corrective Action 9
Crimpshrine13 ISO/TS 16949 CBs & Auditors not following up on the schedules IATF 16949 - Automotive Quality Systems Standard 43
R Which of the following indicators is important for Operations - Ppk, Cpk, or Cpm? Statistical Analysis Tools, Techniques and SPC 15
T What to do when Employees are not following Instructions Human Factors and Ergonomics in Engineering 65
F ANSI ASQ Z1.4 - Is the following process acceptable? Inspection, Prints (Drawings), Testing, Sampling and Related Topics 4
M QSR - Design Control on Existing Device not Designed following QSR 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 2
R QA Manager and Disciplining Employees for not following Processes Quality Manager and Management Related Issues 28
I Medical Device Registration details for the following Countries ISO 13485:2016 - Medical Device Quality Management Systems 5
M Sampling Inspection at QA - Inputs on the following sampling plan Statistical Analysis Tools, Techniques and SPC 3
N My FDA auditor asked the following: Other US Medical Device Regulations 12
Q How to determine the average baseline for the following data in SPC Quality Tools, Improvement and Analysis 3
M 7.6.2 Revisions following Engineering Changes - What is the right meaning? IATF 16949 - Automotive Quality Systems Standard 4
Marc Software gives visual representation of who?s following you online After Work and Weekend Discussion Topics 1
Ronen E European Commission calls for action following PIP's Breast Implant Saga EU Medical Device Regulations 1
T Employee not following Purchasing Process Other Medical Device Related Standards 27
Marc US east coast in chaos following rare October snowstorm - 2011 Coffee Break and Water Cooler Discussions 14
T Is the following flow for Training Needs Analysis correct? Training - Internal, External, Online and Distance Learning 6
L Consultant not following Process Approach ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 34
Q Can I use Regression Analysis in the following scenario Statistical Analysis Tools, Techniques and SPC 18
M Change Order Process - Stake holders not following through - Suggestions wanted Manufacturing and Related Processes 5
D Manufacturing Execution Systems (MES) - People Not Following Work Process (WPs) Manufacturing and Related Processes 5
L Fitted Splined Connections following DIN 5480 - Inspection Problems Inspection, Prints (Drawings), Testing, Sampling and Related Topics 1
H Meeting following an interview, what should I expect? Career and Occupation Discussions 15
T Labeling Control and trouble with labelers not following procedure ISO 13485:2016 - Medical Device Quality Management Systems 11
Ajit Basrur Teva recalls drug following Jackson death probe Pharmaceuticals (21 CFR Part 210, 21 CFR Part 211 and related Regulations) 1
A Audit NC (nonconformance) for not following guidelines on calibration! General Measurement Device and Calibration Topics 9
S Consequences of Shipping product with label not following CE rules EU Medical Device Regulations 2
Q Corrective Action - CAPA - Root Cause - Not following the training procedure! Problem Solving, Root Cause Fault and Failure Analysis 13
S Why people not following SPC charts regularly Training - Internal, External, Online and Distance Learning 10
G Not sequentially following steps in a work instruction Process Audits and Layered Process Audits 85
Q Work Environment - Which of the following is to be addressed as nonconformity? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 25
Z How to Establish Quality Manual Not Following the Structure of the Standard? Quality Management System (QMS) Manuals 3
D How do we interpret the following XmR Trend Chart data? Statistical Analysis Tools, Techniques and SPC 3
L Corrective action following a wrong answer of the auditee ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 19
T In the following statement, what does "Z" stand for? ISO 13485:2016 - Medical Device Quality Management Systems 7
Q Failure where the Root Cause was the Material Handler Not Following Procedure Problem Solving, Root Cause Fault and Failure Analysis 20

Similar threads

Top Bottom