Hi Dears,
we have a part wich is already in serial build in another production site under injection molding process.
actually we have a prototype (1 cavity) mold under compression process, and our customer has required to perform 50 times measurements for 40 dimensions (on drawing).
I have told him that ISO TS require 50 measurements for capability study for product CS. and the requirements for ISIR is only dimension report for all cavities (in this case we have only 1 cavity).
the second thing is that even if i perform capability study using the prototype mold under compression will not provide the real situation and my process capability as the part is already in serial build and the serial mold will be 32 cavities under injection process.
please comment
we have a part wich is already in serial build in another production site under injection molding process.
actually we have a prototype (1 cavity) mold under compression process, and our customer has required to perform 50 times measurements for 40 dimensions (on drawing).
I have told him that ISO TS require 50 measurements for capability study for product CS. and the requirements for ISIR is only dimension report for all cavities (in this case we have only 1 cavity).
the second thing is that even if i perform capability study using the prototype mold under compression will not provide the real situation and my process capability as the part is already in serial build and the serial mold will be 32 cavities under injection process.
please comment