We have an ISO9000 certification. We do quite a few one part job shop things here along with our regular production. Is there any reason why we could not separate those small 1-2 part lots into a streamlined "One-Off" process?
 
Elsmar Forum Sponsor
R

Reg Morrison

#2
Actually you have a certification to ISO 9001 (not ISO 9000).

It is a mistake to think parts should be run outwith of a QMS. The key is to have agile, lean, cost effective processes WITHIN the QMS to run the low quantity orders.

Quality processes have to be scalable and adaptable to the needs of the customer and product.
 

somashekar

Staff member
Super Moderator
#3
We have an ISO9000 certification. We do quite a few one part job shop things here along with our regular production. Is there any reason why we could not separate those small 1-2 part lots into a streamlined "One-Off" process?
You do quite a few one part job as you say.
So I am sure you have a system in place just as much necessary for one-off.
The process is no different but for the scale of system operations.
By separating., tell us what differently you wish to do, which seems to bother you .....
There is no reason why you could not separate those small 1-2 part lots into a streamlined "One-Off" process, as long as you aim and meet the customer requirement and assure quality. This one-off process will simply be within your QMS operation.
 
Last edited:

Russ

Quite Involved in Discussions
#4
Actually you have a certification to ISO 9001 (not ISO 9000).

It is a mistake to think parts should be run outwith of a QMS. The key is to have agile, lean, cost effective processes WITHIN the QMS to run the low quantity orders.

Quality processes have to be scalable and adaptable to the needs of the customer and product.
Not wanting to run these outside the system just unsure how to streamline and wondering if anyone else has done this and maybe an example. I know it has to be simple or it will never work here but will be ignored.:frust:
 

John Broomfield

Staff member
Super Moderator
#5
Not wanting to run these outside the system just unsure how to streamline and wondering if anyone else has done this and maybe an example. I know it has to be simple or it will never work here but will be ignored.:frust:
Russ,

You choose how to define the scope of your management system; what services and products to include and exclude.

You can eliminate this service from the scope of your certification.

The bigger question is assuming that quality services and products cost more than the alternative.

John
 

somashekar

Staff member
Super Moderator
#6
You can eliminate this service from the scope of your certification.
John.
There is nothing to say that the one-part job is not in the scope of the certified QMS.
The questions seems simple and straight.
Can they implement two processes, one that covers small 1-2 parts and other perhaps the volume parts. Perhaps the OP is running into difficulty in certain processes of their QMS that they have more aligned with volume parts.
Touching the scope here perhaps is deviating.
 

John Broomfield

Staff member
Super Moderator
#7
Somashekar,

Deviating from what?

The scopes of the management system and its certification are determined by the organization provided the certification scope is no larger than the scope of the management system.

And, I agree, that the management system's processes and controls should be tailored according to the needs of the customer as a result of planning (7.1).

For some reason the latter seems not to be happening.

Perhaps Russ will advise.

John
 

Ninja

Looking for Reality
Trusted Information Resource
#8
Not wanting to run these outside the system just unsure how to streamline and wondering if anyone else has done this and maybe an example. I know it has to be simple or it will never work here but will be ignored.:frust:
Hi Russ,

As John mentioned, you CAN run these outside of the QMS...but I'm not sure why you would do so.

Run them outside of SPC, CpK and other things built for an ongoing production line, sure. But there is no reason to run outside of your QMS.

Example: If the one-off part ships and the customer complains about it...how would you handle the complaint? The customer feedback would go right into your QMS processes wouldn't it?

It is easy enough to document that jobs meeting {X criteria} will be handled "this way", totally within your QMS.
Not knowing what you're doing, so drawing from my own one-off things instead, it could be a single document defining how job-shop items are handled. It does not have to be a whole suite of procedures.

Picture a single document stating that
"Short run fabrication as defined by the Production controller {or equivalent} shall be handled as follows: ...."
(and remember that it is always best to have a positive record that 'this job' was defined as short-run....a $10 Rubber Stamp "Short-Run" and an initial on the job ticket would get it done)
It doesn't need to be complicated.
 

Jen Kirley

Quality and Auditing Expert
Staff member
Admin
#9
Not wanting to run these outside the system just unsure how to streamline and wondering if anyone else has done this and maybe an example. I know it has to be simple or it will never work here but will be ignored.:frust:
Job shops need the QMS to cover the "onesies and twosies" at least as much as places who make thousands of assembly line products because there is no room for error.

But process realization does not need to be difficult. A work order/traveler can start with a template and be filled out to contain all of the specific criteria for receipt inspection, set up, first article and final inspection criteria, and even special shipping instructions. The work order/traveler can have blanks for responsible persons to sign completion and acceptance, plus which instruments were used to measure or test the produced items. The work order/traveler can then be filed by customer name along with the PO, raw material invoices, CofAs, prints etc. plus whatever other communication took place, to refer to later as needed. As always, if there are changes to the criteria in the work order/traveler I would expect them to be approved by a person with defined authority.

A central list of approved suppliers and customer satisfaction data should still be used, and corrective actions, if any, should refer to the customer name/work order number from an index, etc. for tractability's sake.

In this way you can avoid making a bunch of, or long and complicated procedures and test/inspection methods. Filing can be largely centralized. All of the standard and customer requirements can be met and you can pull out these files for auditors who ask about purchasing information, inspection criteria and results, etc.

I hope this helps!
 

Russ

Quite Involved in Discussions
#10
Hi Russ,

As John mentioned, you CAN run these outside of the QMS...but I'm not sure why you would do so.

Run them outside of SPC, CpK and other things built for an ongoing production line, sure. But there is no reason to run outside of your QMS.

Example: If the one-off part ships and the customer complains about it...how would you handle the complaint? The customer feedback would go right into your QMS processes wouldn't it?

It is easy enough to document that jobs meeting {X criteria} will be handled "this way", totally within your QMS.
Not knowing what you're doing, so drawing from my own one-off things instead, it could be a single document defining how job-shop items are handled. It does not have to be a whole suite of procedures.

Picture a single document stating that
"Short run fabrication as defined by the Production controller {or equivalent} shall be handled as follows: ...."
(and remember that it is always best to have a positive record that 'this job' was defined as short-run....a $10 Rubber Stamp "Short-Run" and an initial on the job ticket would get it done)
It doesn't need to be complicated.
Thanks! I was kinda thinking along those lines so I believe I will do just that. I want to keep them in the QMS, now I just have to come to an agreement here on the content.

Thanks to all for your input, it really helped me think it through!!!!:applause:
 
Thread starter Similar threads Forum Replies Date
S Do we need separate stand alone procedure for Suspect Unapproved Parts? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 0
S Regulations for Selling Convenience Kit vs. Selling Separate Parts Other US Medical Device Regulations 2
M Identifying Applied Parts IEC 60601 - Medical Electrical Equipment Safety Standards Series 3
M Nonconforming parts accepted by operator with intention Human Factors and Ergonomics in Engineering 31
J Mechanical inspection techniques of close tolerance parts Inspection, Prints (Drawings), Testing, Sampling and Related Topics 4
J Sister-company providing parts is only ISO 9001 registered IATF 16949 - Automotive Quality Systems Standard 7
A AS9100D 8.1.4 Prevention of Counterfeit Parts AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
C Difficulties getting RoHS/REACH for cheap parts RoHS, REACH, ELV, IMDS and Restricted Substances 1
G Same parts but new customer - What will the auditor ask me? IATF 16949 - Automotive Quality Systems Standard 2
G Need to change KPI we called NC parts (maximum 3%.) to FTQ (first time quality) IATF 16949 - Automotive Quality Systems Standard 4
Q Do you classify applied parts? IEC 60601 - Medical Electrical Equipment Safety Standards Series 1
R Defib-proof applied parts IEC 60601 - Medical Electrical Equipment Safety Standards Series 0
S Earthing of moving parts, designing tips IEC 60601 - Medical Electrical Equipment Safety Standards Series 2
C Quantifying risk in choosing the number of parts, operators and replicates in a GR&R Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 4
Ed Panek Corona Virus impact on Supplier Audits and Received Parts ISO 13485:2016 - Medical Device Quality Management Systems 4
E IEC 60601-1 - Unearthed Medical Device Metal Parts IEC 60601 - Medical Electrical Equipment Safety Standards Series 1
bryan willemot Shipping Aerospace parts without Stress certs Manufacturing and Related Processes 20
H Capability Data for Paint Thickness on Painted Parts Statistical Analysis Tools, Techniques and SPC 10
J SPC - Stamping parts - Small batch size Statistical Analysis Tools, Techniques and SPC 6
D 3 Companies - Medical device parts and substances - Responsibilities EU Medical Device Regulations 4
B Accessible parts per 8.4.2 b) - Touch currents in combination with MOOP or MOPP? IEC 60601 - Medical Electrical Equipment Safety Standards Series 3
J Traceability of component parts - Bolts, screws and washers ISO 13485:2016 - Medical Device Quality Management Systems 3
R Traceability on Unmarked Parts - AS9100 requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
CPhelan Best metrics for monitoring low volume (<1000) parts per vendors Supply Chain Security Management Systems 1
DuncanGibbons Best practice for identifying "items" of parts for DFMEA analysis AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
L PPM - wrong parts or defective parts? IATF 16949 - Automotive Quality Systems Standard 18
DuncanGibbons Classification of aerospace parts depending on their risk and criticality etc. Federal Aviation Administration (FAA) Standards and Requirements 3
K Counterfeit parts prevention - Audit Nonconformance - AS9100 8.2.2 AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 25
bryan willemot Looking for a certified test report for aerospace parts AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 0
S Managing specification changes on standard parts purchased through trading companies Document Control Systems, Procedures, Forms and Templates 2
L PMA and Non-PMA parts in same finished goods area? Federal Aviation Administration (FAA) Standards and Requirements 1
SKM.Sunil Detachable parts vs Off the Shelf parts EU Medical Device Regulations 8
D Do purchasing controls apply to non-medical parts? ISO 13485:2016 - Medical Device Quality Management Systems 5
B Using non CE parts in a machine CE Marking (Conformité Européene) / CB Scheme 1
C AS9100D -8.5.1j - Accountability For All Products Tiny Parts AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
I Containment procedure for parts after a power outage. IATF 16949 - Automotive Quality Systems Standard 1
D How long should we keep the spare parts available for our medical device, after we have stopped the production? ISO 13485:2016 - Medical Device Quality Management Systems 0
Ron Rompen 2D matrix issue - Parts (machined steel) returned from the customer Design and Development of Products and Processes 0
bryan willemot Looking for a good CoC to put with my certification sheets when we send parts Document Control Systems, Procedures, Forms and Templates 1
K Packaging and Damaged Parts returned from a Service Provider (Anodize) - Who is Responsible? Manufacturing and Related Processes 20
D AS9102 - Assembly FAI for Use As Is or Repaired Parts AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 6
B F-type applied part - Separation from ALL(?) other parts IEC 60601 - Medical Electrical Equipment Safety Standards Series 8
A AQL sampling bags of parts Inspection, Prints (Drawings), Testing, Sampling and Related Topics 5
S Returned but Customer damaged parts. Is it a NC? Misc. Quality Assurance and Business Systems Related Topics 27
O Identifying KPI for AS9100 8.1.4 - Prevention of Counterfeit Parts - PCB assembly contract manufacturer AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 16
shimonv Design input/output traceability for mechanical parts ISO 13485:2016 - Medical Device Quality Management Systems 13
Ahang Separation between secondary circuit and accessible parts IEC 60601 - Medical Electrical Equipment Safety Standards Series 2
erozas2003 Color test on molded plastic parts Inspection, Prints (Drawings), Testing, Sampling and Related Topics 1
P ISO 80369-7 standard - Interpreting which Parts should be in scope Other Medical Device Related Standards 7
DuncanGibbons Documentation aerospace OEMs require with purchase of parts from manufacturers/suppliers Manufacturing and Related Processes 0

Similar threads

Top Bottom